The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

§ 4280.260 Reporting requirements.

Recipients are required to submit reports on financial status and performance, as described below.

(a) Financial reports. Financial reports must be submitted using Form SF-425 and any additional information specified in the Financial Assistance Agreement (FAA).

(1) Semi-annual. Semi-annual financial reports are due 30 calendar days after the reporting period ends, or as directed by 2 CFR 200.328(c). The reporting periods are October 1-March 31 and April 1-September 30.

(2) Final. A final financial report is due 120 calendar days after the Period of Performance ends, or the Project is completed, whichever occurs sooner, or as directed by 2 CFR 200.328(c).

(b) Performance report. Performance reports must include the information specified in the FAA. Typically, performance reports are required to include a description of the objective(s) for the reporting period; whether the objective(s) were met and if not, what action is being taken to ensure the objective(s) is met during the next reporting period; and all written work product(s) such as copies of Energy Audits, Renewable Energy Site Assessments, Resource Assessments, and Feasibility Studies to demonstrate that the objective was carried out.

(1) Semi-annual. Semi-annual performance reports are due 30 calendar days after the reporting period ends, or as directed by 2 CFR 200.329(c). The reporting periods are October 1-March 31 and April 1-September 30.

(2) Final. A final performance report is due 120 calendar days after the Period of Performance ends, or the Project is completed, whichever occurs sooner, or as directed by 2 CFR 200.329(c).