The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

Subpart 207.70—Buy-to-Budget—Additional Quantities of End Items

Source:

68 FR 43331, July 22, 2003, unless otherwise noted.

207.7001 Definition.

End item, as used in this subpart, means a production product assembled, completed, and ready for issue or deployment.

207.7002 Authority to acquire additional quantities of end items.

10 U.S.C. 3069 authorizes DoD to use funds available for the acquisition of an end item to acquire a higher quantity of the end item than the quantity specified in a law providing for the funding of that acquisition, if the head of an agency determines that—

(a) The agency has an established requirement for the end item that is expected to remain substantially unchanged throughout the period of the acquisition;

(b) It is possible to acquire the higher quantity of the end item without additional funding because of production efficiencies or other cost reductions;

(c) The amount of funds used for the acquisition of the higher quantity of the end item will not exceed the amount provided under that law for the acquisition of the end item; and

(d) The amount provided under that law for the acquisition of the end item is sufficient to ensure that each unit of the end item acquired within the higher quantity is fully funded as a complete end item.

[68 FR 43331, July 22, 2003, as amended at 87 FR 76990, Dec. 16, 2022]

207.7003 Limitation.

For noncompetitive acquisitions, the acquisition of additional quantities is limited to not more than 10 percent of the quantity approved in the justification and approval prepared in accordance with FAR part 6 for the acquisition of the end item.