The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

PART 1231—CONTRACT COST PRINCIPLES AND PROCEDURES

Source:

87 FR 61159, Oct. 7, 2022, unless otherwise noted.

Subpart 1231.2—Contracts With Commercial Organizations

1231.205 Selected costs.

1231.205-3270 Precontract costs—incurrence of costs.

(a) The decision to incur precontract costs is the responsibility of the contractor. DOT officials shall not authorize, demand, or require a contractor to incur precontract costs. The contracting officer may advise the prospective contractor that any costs incurred before contract award are at the contractor's sole risk and that if negotiations fail to result in a binding contract, payment of these costs may not be made by the Government.

(b) When the contracting officer determines that incurring precontract costs was necessary to meet the proposed contract delivery schedule of a cost-reimbursement contract, the clause at 1252.231-70, Date of Incurrence of Costs, may be inserted in the resultant contract.