The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

23.303 Notice of radioactive materials.

(a) The clause at 52.223-7, Notice of Radioactive Materials, requires the contractor to notify the contracting officer prior to delivery of radioactive material.

(b) Upon receipt of the notice, the contracting officer shall notify receiving activities so that appropriate safeguards can be taken.

(c) The clause permits the contracting officer to waive the notification if the contractor states that the notification on prior deliveries is still current. The contracting officer may waive the notice only after consultation with cognizant technical representatives.

(d) The contracting officer is required to specify in the clause at 52.223-7, the number of days in advance of delivery that the contractor will provide notification. The determination of the number of days should be done in coordination with the installation/facility radiation protection officer (RPO). The RPO is responsible for ensuring the proper license, authorization, or permit is obtained prior to receipt of the radioactive material.

[89 FR 30243, Apr. 22, 2024]