The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

Table 9 to Subpart VVVVVV of Part 63—Applicability of General Provisions to Subpart VVVVVV

As required in § 63.11501(a), you must comply with the requirements of the NESHAP General Provisions (40 CFR part 63, subpart A) as shown in the following table.

Table 9 to Subpart VVVVVV of Part 63—Applicability of General Provisions to Subpart VVVVVV

[As required in § 63.11501(a), you must comply with the requirements of the NESHAP General Provisions (40 CFR part 63, subpart A) as shown in the following table.]

Citation Subject Applies to this subpart? Explanation
63.1(a)(1), (a)(2), (a)(3), (a)(4), (a)(6), (a)(10)-(a)(12) (b)(1), (b)(3), (c)(1), (c)(2), (c)(5), (e) Applicability Yes
63.1(a)(5), (a)(7)-(a)(9), (b)(2), (c)(3), (c)(4), (d) Reserved No
63.2 Definitions Yes
63.3 Units and Abbreviations Yes
63.4 Prohibited Activities and Circumvention Yes
63.5 Preconstruction Review and Notification Requirements Yes
63.6(a), (b)(1)-(b)(5), (b)(7), (c)(1), (c)(2), (c)(5), (e)(1)(iii), (g), (i), (j) Compliance with Standards and Maintenance Requirements Yes
63.6(b)(6), (c)(3), (c)(4), (d), (e)(2) Reserved No
63.6(e)(1)(i) and (ii), (e)(3), and (f)(1) SSM Requirements No See § 63.11495(d) for general duty requirement. The standards in this subpart apply at all times.
63.6(f) Compliance with Nonopacity Emission Standards Yes
63.6(h) Compliance with Opacity and Visible Emission Standards No This subpart does not include opacity or visible emissions (VE) standards or require a continuous opacity monitoring system (COMS).
63.7(a)(1), (a)(3), (a)(4), (c), (e)(4), and (f)-(h) Performance Testing Requirements Yes Except this subpart specifies how and when the performance test results are reported.
63.7(a)(2), (b), (d), (e)(2)-(e)(3) Performance Testing Schedule, Notification of Performance Test, Performance Testing Facilities, and Conduct of Performance Tests Yes/No Requirements apply if conducting test for metal HAP control; requirements in §§ 63.997(c)(1), (d), (e), and 63.999(a)(1) apply, as referenced in § 63.11496(g), if conducting test for organic HAP or hydrogen halide and halogen HAP control device.
63.7(e)(1) Performance Testing No See § 63.11496(f)(3)(ii) if conducting a test for metal HAP emissions. See §§ 63.11496(g) and 63.997(e)(1) if conducting a test for continuous process vents or for hydrogen halide and halogen emissions. See §§ 63.11496(g) and 63.2460(c) if conducting a test for batch process vents.
63.8(a)(1), (b), (c)(1)(ii), (c)(2)-(c)(3), (f)(1)-(5) Monitoring Requirements Yes
63.8(a)(2) Monitoring Requirements No
63.8(a)(3) Reserved No
63.8(a)(4) Monitoring Requirements Yes
63.8(c)(1)(i) General Duty to Minimize Emissions and CMS Operation No
63.8(c)(1)(iii) Requirement to Develop SSM Plan for CMS No
63.8(c)(4) Yes Only for CEMS. CPMS requirements in subpart SS of this part are referenced from § 63.11496. Requirements for COMS do not apply because this subpart does not require COMS.
63.8(c)(5) No This subpart does not require COMS.
63.8(c)(6)-(c)(8), (d)(1)-(d)(2), (e), (f)(6) Yes Requirements apply only if you use a continuous emission monitoring system (CEMS) to demonstrate compliance with the alternative standard in § 63.11496(e). Additionally, this subpart specifies how and when the performance evaluation results are reported.
63.8(d)(3) Written Procedures for CMS Yes Requirement applies except for last sentence, which refers to an SSM plan. SSM plans are not required.
63.8(g)(1)-(g)(4) Yes Data reduction requirements apply only if you use CEMS to demonstrate compliance with alternative standard in § 63.11496(e). COMS requirements do not apply. Requirement in § 63.8(g)(2) does not apply because data reduction for CEMS are specified in subpart FFFF of this part.
63.8(g)(5) No Data reduction requirements for CEMS are specified in § 63.2450(j)(4), as referenced from § 63.11496. CPMS requirements are specified in subpart SS of this part, as referenced from § 63.11496.
63.9(a), (b)(1), (b)(2), (b)(4), (b)(5), (c), (d), (e), (i) Notification Requirements Yes
63.9(b)(3), (h)(4) Reserved No
63.9(f) No This subpart does not contain opacity or VE limits.
63.9(g) Yes Additional notification requirement applies only if you use CEMS to demonstrate compliance with alternative standard in § 63.11496(e).
63.9(h)(1)-(h)(3), (h)(5)-(h)(6) Yes Except as specified in § 63.11501(b) and this subpart does not contain opacity or VE limits.
63.9(j) Change in Information Already Provided No Notification of process changes that affect a compliance determination are required in § 63.11501(d)(4).
63.9(k) Electronic Submission of Notifications or Reports Yes As specified in §§ 63.11496(g)(1)(iv), 63.11497(f)(1)(iv), and 63.11501(b) and (d).
63.10(a) Recordkeeping Requirements Yes
63.10(b)(1) Yes
63.10(b)(2)(i) Recordkeeping of Occurrence and Duration of Startups and Shutdowns No See § 63.11501(c)(8) for recordkeeping of occurrence and duration of each startup and shutdown for continuous process vents that are subpart to table 3 to this subpart.
63.10(b)(2)(ii) Recordkeeping of Malfunctions No See § 63.11501(c)(1)(vii) and (viii) for recordkeeping requirements.
63.10(b)(2)(iii) Maintenance Records Yes
63.10(b)(2)(iv) and (v) Actions Taken to Minimize Emissions During SSM No
63.10(b)(2)(vi), (x), (xi), (xiii) Yes Apply only if you use CEMS to demonstrate compliance with alternative standard in § 63.11496(e).
63.10(b)(2)(vii)-(b)(2)(ix), (b)(2)(xii), (b)(2)(xiv) Yes
63.10(b)(3) Yes
63.10(c)(1), (c)(5)-(c)(6), (c)(13)-(c)(14) Yes Apply only if you use CEMS to demonstrate compliance with alternative standard in § 63.11496(e).
63.10(c)(7)-(8) Additional Recordkeeping Requirements for CMS—Identifying Exceedances and Excess Emissions Yes
63.10(c)(10) Recordkeeping Nature and Cause of Malfunctions No See § 63.11501(c)(1)(vii) and (viii) for recordkeeping requirements.
63.10(c)(11) Recording Corrective Actions No See § 63.11501(c)(1)(vii) and (viii) for recordkeeping requirements.
63.10(c)(12) Yes
63.10(c)(15) Use of SSM Plan No
63.10(c)(2)-(c)(4), (c)(9) Reserved No
63.10(d)(1), (d)(4), (f) Reporting Requirements Yes
63.10(d)(2) No See §§ 63.11496(g)(1)(iv) and 63.11497(f)(1)(iv) for performance test reporting.
63.10(d)(3) No This subpart does not include opacity or VE limits.
63.10(d)(5) SSM Reports No See § 63.11501(d)(1) and (8) for reporting requirements.
63.10(e)(1)-(e)(2) Yes Apply only if you use CEMS to demonstrate compliance with alternative standard in § 63.11496(e). Additionally, this subpart specifies how and when the performance evaluation results are reported.
63.10(e)(3) No Except as provided in § 63.11501(d).
63.10(e)(4) No This subpart does not include opacity or VE limits.
63.11 Control Device Requirements Yes
63.12 State Authorities and Delegations Yes
63.13 Addresses Yes
63.14 Incorporations by Reference Yes
63.15 Availability of Information and Confidentiality Yes
63.16 Performance Track Provisions Yes

[74 FR 56041, Oct. 29, 2009, as amended at 77 FR 75762, Dec. 21, 2012; 91 FR 16536, Apr. 1, 2026]