The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

Title 40Protection of EnvironmentPart / Section
Chapter IEnvironmental Protection Agency1 – 1099
Subchapter CAir Programs50 – 99
Part 60Standards of Performance for New Stationary Sources60.1 – 60.6685
Subpart WWWWEmission Guidelines and Compliance Times for Large Municipal Waste Combustors Constructed on or Before January 23, 202460.6250 – 60.6685
Introduction60.6250 – 60.6295
§ 60.6250What is the purpose of this subpart?
§ 60.6255Am I affected by this subpart? What authorities does the EPA Administrator retain?
§ 60.6260Is a state plan required for all states?
§ 60.6265What must I include in my state plan?
§ 60.6270Is there an approval process for my state plan?
§ 60.6275What if my state plan is not approvable?
§ 60.6280Is there an approval process for a negative declaration letter?
§ 60.6285What compliance schedule must I include in my state plan?
§ 60.6290Are there any state plan requirements for this subpart that supersede the requirements specified in subpart B?
§ 60.6295Does this subpart directly affect municipal waste combustor owners and operators in my state?
Applicability of State Plans60.6300 – 60.6310
§ 60.6300What municipal waste combustors must I address in my state plan?
§ 60.6305Are any large municipal waste combustors exempt from my state plan?
§ 60.6310What subcategories of large municipal waste combustors must I include in my state plan?
Use of Model Rule60.6315 – 60.6325
§ 60.6315What is the “model rule” in this subpart?
§ 60.6320How does the model rule relate to the required elements of my state plan?
§ 60.6325What are the principal components of the model rule?
Model Rule—Increments or Progress60.6330 – 60.6385
§ 60.6330What are my requirements for meeting increments of progress and achieving final compliance?
§ 60.6335When must I complete each increment of progress?
§ 60.6340What must I include in the notifications of achievement of my increments of progress?
§ 60.6345When must I submit the notifications of achievement of increments of progress?
§ 60.6350What if I do not meet an increment of progress?
§ 60.6355How do I comply with the increment of progress for submittal of a control plan?
§ 60.6360How do I comply with the increment of progress for awarding contracts?
§ 60.6365How do I comply with the increment of progress for initiating onsite construction?
§ 60.6370How do I comply with the increment of progress for completing onsite construction?
§ 60.6375How do I comply with the increment of progress for achieving final compliance?
§ 60.6380What must I do if I close my municipal waste combustor and then restart my municipal waste combustor?
§ 60.6385What must I do if I plan to permanently close my municipal waste combustor and not restart it?
Model Rule—Good Combustion Practices: Operator Training60.6390 – 60.6415
§ 60.6390What types of training must I do?
§ 60.6395Who must complete the operator training course? By when?
§ 60.6400Who must complete the site-specific training course?
§ 60.6405What site-specific training must I provide?
§ 60.6410What information must I include in the site-specific operating manual?
§ 60.6415Where must I keep the site-specific operating manual?
Model Rule—Good Combustion Practices: Operator Certification60.6420 – 60.6430
§ 60.6420What types of operator certification must the chief facility operator and shift supervisor obtain and by when must they obtain it?
§ 60.6425After the required date for operator certification, who may operate the municipal waste combustor?
§ 60.6430What if all the certified operators must be temporarily offsite?
Model Rule—Good Combustion Practices: Operating Requirements60.6435 – 60.6440
§ 60.6435What are the operating practice requirements for my municipal waste combustor?
§ 60.6440What happens to the operating requirements during periods of startup, shutdown, and malfunction?
Model Rule—Emission Limits60.6445 – 60.6455
§ 60.6445What pollutants are regulated by this subpart?
§ 60.6450What emission limits must I meet? By when?
§ 60.6455What happens to the emission limits during periods of startup, shutdown, and malfunction?
Model Rule—Continuous Emission Monitoring60.6460 – 60.6510
§ 60.6460What types of continuous emission monitoring must I perform?
§ 60.6465What continuous emission monitoring systems must I install for gaseous pollutants?
§ 60.6470How are the data from the continuous emission monitoring systems used?
§ 60.6475How do I make sure my continuous emission monitoring systems are operating correctly?
§ 60.6480What is my schedule for evaluating continuous emission monitoring systems?
§ 60.6485What must I do if I choose to monitor carbon dioxide instead of oxygen as a diluent gas?
§ 60.6490What is the minimum amount of monitoring data I must collect with my continuous emission monitoring systems?
§ 60.6495How do I convert my 1-hour arithmetic averages into appropriate averaging times and units?
§ 60.6500What is required for my continuous opacity monitoring system and how are the data used?
§ 60.6505What additional requirements must I meet for the operation of my continuous emission monitoring systems and continuous opacity monitoring system?
§ 60.6510What must I do if any of my continuous emission monitoring systems are temporarily unavailable to meet the data collection requirements?
Model Rule—Stack Testing60.6515 – 60.6540
§ 60.6515What types of stack tests must I conduct?
§ 60.6520How are the stack test data used?
§ 60.6525What schedule must I follow for the stack testing?
§ 60.6530What procedures and test methods must I use to stack test?
§ 60.6535May I conduct stack testing less often?
§ 60.6540May I conduct continuous monitoring or sampling in lieu of stack testing?
Model Rule—Other Monitoring Requirements60.6545 – 60.6570
§ 60.6545Must I meet other requirements for continuous monitoring?
§ 60.6550How do I monitor the load of my municipal waste combustor?
§ 60.6555How do I monitor the temperature of flue gases at the inlet of my particulate matter control device?
§ 60.6560How do I monitor the injection rate of activated carbon?
§ 60.6565What is the minimum amount of monitoring data I must collect with my continuous parameter monitoring systems?
§ 60.6570What requirements must I meet for estimating my municipal waste combustor capacity?
Model Rule—Recordkeeping60.6575 – 60.6600
§ 60.6575What records must I keep?
§ 60.6580Where must I keep my records and for how long?
§ 60.6585What records must I keep for operator training and certification?
§ 60.6590What records must I keep for stack tests?
§ 60.6595What records must I keep for continuously monitored pollutants or parameters?
§ 60.6600What records must I keep for municipal waste combustors that use activated carbon?
Model Rule—Reporting60.6605 – 60.6650
§ 60.6605What reports must I submit and in what form?
§ 60.6610What are the appropriate units of measurement for reporting my data?
§ 60.6615When must I submit the initial performance test report?
§ 60.6620What must I include in my initial performance test report?
§ 60.6625When must I submit the annual report?
§ 60.6630What must I include in my annual report?
§ 60.6635What must I do if I am out of compliance with the requirements of this subpart?
§ 60.6640If a semiannual report is required, when must I submit it?
§ 60.6645What must I include in the semiannual out-of-compliance reports?
§ 60.6650Can reporting dates be changed?
Model Rule—Air Curtain Incinerators That Burn 100 Percent Wood Waste, Clean Lumber, and Yard Waste60.6655 – 60.6680
§ 60.6655What is an air curtain incinerator?
§ 60.6660What is yard waste?
§ 60.6665What are the emission limits for air curtain incinerators that burn 100 percent wood waste, clean lumber, and/or yard waste?
§ 60.6670How must I monitor opacity for air curtain incinerators that burn 100 percent wood waste, clean lumber, and/or yard waste?
§ 60.6675What are the recordkeeping and reporting requirements for air curtain incinerators that burn 100 percent wood waste, clean lumber, and/or yard waste?
§ 60.6680What equations must I use?
Definitions60.6685
§ 60.6685What definitions apply to this subpart?
Table 1 to Subpart WWWW of Part 60
Model Rule—Compliance Schedules and Increments of Progress
Table 2 to Subpart WWWW
Municipal Waste Combustor Carbon Monoxide Guidelines
Table 3 to Subpart WWWW of Part 60
Model Rule—Emission Limits for Existing Large Municipal Waste Combustors
Table 4 to Subpart WWWW of Part 60
Requirements for Continuous Emission Monitoring Systems (CEMS)
Table 5 to Subpart WWWW
Performance Test Requirements for Compliance With Emissions Limits Under § 60.6450