The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

Preparing an Application

§ 35.505 Components of a complete application.

A complete application for an environmental program grant must:

(a) Meet the requirements in 2 CFR part 200, subpart C.

(b) Include a proposed work plan (§ 35.507 of this subpart); and

(c) Specify the environmental program and the amount of funds requested.

[66 FR 3795, Jan. 16, 2001, as amended at 79 FR 76055, Dec. 19, 2014]

§ 35.506 Time frame for submitting an application.

An applicant should submit a complete application to EPA at least 60 days before the beginning of the proposed funding period.

§ 35.507 Work plans.

(a) Bases for negotiating work plans. The work plan is negotiated between the applicant and the Regional Administrator and reflects consideration of national, regional, and Tribal environmental and programmatic needs and priorities.

(1) Negotiation considerations. In negotiating the work plan, the Regional Administrator and applicant will consider such factors as national program guidance; any regional supplemental guidance; goals, objectives, and priorities proposed by the applicant; other jointly identified needs or priorities; and the planning target.

(2) National program guidance. If an applicant proposes a work plan that differs significantly from the goals and objectives, priorities, or performance measures in the national program guidance associated with the proposed work plan activities, the Regional Administrator must consult with the appropriate National Program Manager before agreeing to the work plan.

(3) Use of existing guidance. An applicant should base the grant application on the national program guidance in place at the time the application is being prepared.

(b) Work plan requirements.

(1) The work plan is the basis for the management and evaluation of performance under the grant agreement.

(2) An approvable work plan must specify:

(i) The work plan components to be funded under the grant;

(ii) The estimated work years and estimated funding amounts for each work plan component;

(iii) The work plan commitments for each work plan component, and a time frame for their accomplishment;

(iv) A performance evaluation process and reporting schedule in accordance with § 35.515 of this subpart; and

(v) The roles and responsibilities of the recipient and EPA in carrying out the work plan commitments.

(3) The work plan must be consistent with applicable federal statutes; regulations; circulars; executive orders; and delegations, approvals, or authorizations.

(c) Tribal Environmental Agreement as work plan. An applicant may use a Tribal Environmental Agreement or a portion of the Tribal Environmental Agreement as the work plan or part of the work plan for an environmental program grant if the portion of the Tribal Environmental Agreement that is to serve as the grant work plan:

(1) Is clearly identified as the grant work plan and distinguished from other portions of the Tribal Environmental Agreement; and

(2) Meets the requirements in § 35.507(b).

§ 35.508 Funding period.

The Regional Administrator and applicant may negotiate the length of the funding period for environmental program grants, subject to limitations in appropriations and authorizing statutes.

§ 35.509 Consolidated grants.

Any applicant eligible to receive funds from more than one environmental program may submit an application for a consolidated grant. For consolidated grants, an applicant prepares a single budget and work plan covering all of the environmental programs included in the application. The consolidated budget must identify each environmental program to be included, the amount of each program's funds, and the extent to which each program's funds support each work plan component. Recipients of consolidated grants must account for grant funds in accordance with the funds' environmental program sources; funds included in a consolidated grant from a particular environmental program may be used only for that program.