The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

Contents of the Site Assessment Plan

§ 585.610 What must I include in my SAP?

(a) Project information may be provided using a PDE. When you provide information using a PDE, BOEM reserves the right to determine what range of values for any given parameter is acceptable. Your SAP must include the following project-specific information, as applicable:

Project information: Including:
(1) Contact information The name, address, email address, and phone number of an authorized representative.
(2) The site assessment or technology testing concept A discussion of the objectives; description of the proposed activities, including the technology you will use; and proposed schedule from start to completion.
(3) Designation of operator, if applicable As provided in § 585.405.
(4) Commercial lease stipulations and compliance A description of the measures you took, or will take, to satisfy the conditions of any lease stipulations related to your proposed activities.
(5) A location plat, or indicative layout The range of surface locations and associated water depths for proposed structures, facilities, and appurtenances located both offshore and onshore, including all anchor and mooring data; and the location and associated water depths of all existing structures.
(6) General structural and project design, fabrication, and installation For facilities deemed complex or significant you must provide preliminary design information for each facility associated with your site assessment activity and subpart G of 30 CFR part 285 applies. For facilities not deemed complex or significant you must provide final design information.
(7) Deployment activities A description of the safety, prevention, and environmental protection features or measures that you will use.
(8) Your proposed measures for avoiding, minimizing, reducing, eliminating, and monitoring environmental impacts A description of the measures you will use to avoid or minimize adverse effects and any potential incidental take, before you conduct activities on your lease, and how you will mitigate environmental impacts from your proposed activities, including a description of the measures you will use as required by §§ 585.700 through 585.703.
(9) Project verification strategy An analysis supporting your recommendation as to whether your site assessment activities should be determined complex or significant. If your recommendation supports a complex or significant determination, describe your strategy for compliance with 30 CFR 285.705 through 285.714.
(10) References A bibliographic list of any document or published source that you cite as part of your plan. You may reference information and data discussed in other plans that you previously submitted or that are otherwise readily available to BOEM.
(11) Decommissioning and site clearance procedures A discussion of general concepts and methodologies.
(12) Air quality information Information as described in § 585.700.
(13) A listing of all Federal, State, and local authorizations or approvals required to conduct site assessment activities A statement indicating whether you have applied for or obtained such authorization or approval from the U.S. Coast Guard, U.S. Army Corps of Engineers, and any other applicable Federal, State, or local authorizers.
(14) A list of agencies and persons with whom you have communicated, or with whom you will communicate, regarding potential impacts associated with your proposed activities Contact information and issues discussed.
(15) Financial assurance information Statements attesting that the activities and facilities proposed in your SAP are or will be covered by an appropriate bond or other approved financial assurance instrument as required in § 585.516 and §§ 585.525 through 585.529.
(16) Information you incorporate by reference A list of the documents you have incorporated by reference and their public availability.
(17) Other information Additional information as required by BOEM.

(b) You must include reports that document the results of surveys and investigations that characterize and model the site of your proposed assessment activities. Your reports must address the following topics:

Topic: Purpose of report: Including:
(1) Geological and geotechnical To define the baseline geological conditions of the seabed and provide sufficient data to develop a geologic model, assess geologic hazards, and determine the feasibility of the proposed site for your assessment facility (i) Desktop studies to collect available data from published sources and nearby sites.
(ii) Geophysical surveys of the proposed area with sufficient areal coverage, depth penetration, and resolution to define the geological conditions of the seabed at the site that could impact, or be impacted by, your proposed site assessment activities.
(iii) Geotechnical investigations of sufficient scope and detail to: ground truth the geophysical surveys; support development of a geological model; assess potential geological hazards that could impact the proposed site assessment activities; and provide geotechnical data for design of the site assessment facility, including type and approximate dimensions of the foundation.
(iv) An overall site characterization report for your site assessment facility that integrates the findings of your studies, surveys, and investigations; describes the geological model; contains supporting data and findings; and states your recommendations.
(2) Biological To determine the presence of biological features and marine resources A description of the results of surveys used to evaluate the spatial and temporal distribution and abundance of biological species in the site area, including migratory and non-migratory species of vertebrate animals such as fish, marine mammals, sea turtles, and coastal and marine birds; invertebrate animals; plants; algae; and other organisms; also including the presence of live bottoms, hard bottoms, topographic features, and other marine resources.
(3) Archaeological resources and other historic properties To provide BOEM with required information to conduct review of your SAP under NHPA Archeological resource and other historic property identification surveys with supporting data.
(4) Meteorological and oceanographic (metocean) To provide an overall understanding of the meteorological and oceanographic conditions at the site of your proposed facility, and to identify conditions that may pose a significant risk to your facility Desktop studies to collect available data from hindcast or re-analysis models and field measurements in sufficient detail to support design of your facility and support the analysis of wake effects, sediment mobility and scour, and navigation risks.

§ 585.611 What information and certifications must I submit with my SAP to assist BOEM in complying with NEPA and other applicable laws?

(a) Your SAP must contain detailed information and analysis to assist BOEM in complying with NEPA and other applicable laws.

(b) When proposing site assessment activities in an area where BOEM has no previous experience, your SAP must contain information about resources, conditions, and activities listed in the following table that your proposed activities may significantly affect or that may have a significant effect on your proposed activities (including where the potential significance of the effect is unknown) and must contain any other information required by law.

Type of information: Including:
(1) Hazard information Meteorology, oceanography, sediment transport, geology, and shallow geological or manmade hazards.
(2) Water quality Turbidity and total suspended solids from construction; impact from vessel discharges.
(3) Biological resources Characterization of the spatial and temporal distribution and abundance of biological species in the site area, such as benthic communities, marine mammals, sea turtles, coastal and marine birds, fish and shellfish, plankton, sea grasses, and other plant life.
(4) Threatened or endangered species As needed for ESA consultation.
(5) Sensitive biological resources or habitats Essential fish habitat, refuges, preserves, special management areas identified in coastal management programs, nearby marine protected areas, including State and Federal coastal and marine protected areas, as well as nearby national marine sanctuaries, and nearby marine national monuments, rookeries, hard bottom habitat, chemosynthetic communities, calving grounds, barrier islands, beaches, dunes, and wetlands.
(6) Archaeological resources use, other historic property use, Indigenous traditional cultural use, or use pertaining to treaty and reserved rights with Native Americans or other Indigenous peoples Required information to conduct review of the COP under the NHPA or other applicable laws or policies, including treaty and reserved rights with Native Americans or other Indigenous peoples.
(7) Social and economic conditions Employment, existing offshore and coastal infrastructure (including major sources of supplies, services, energy, and water), land use, subsistence resources and harvest practices, recreation, recreational and commercial fishing (including typical fishing seasons, location, and type), minority and lower income groups, coastal zone management programs, and a visual impact assessment.
(8) Coastal and marine uses Military activities, vessel traffic, fisheries, and exploration and development of other natural resources. This includes a navigational safety risk assessment that provides a description of the predicted impacts of the project to navigation, and the measures you will use to avoid or minimize adverse impacts. This document must also be submitted to the U.S. Coast Guard to assist with its analysis if your proposal identifies potential impediments to safe navigation.
(9) Consistency Certification If required by CZMA, under:
(i) 15 CFR part 930, subpart D, if the SAP is submitted before lease issuance;
(ii) 15 CFR part 930, subpart E, if the SAP is submitted after lease issuance.
(10) Other resources, conditions, and activities As identified by BOEM.

(c) When proposing site assessment activities in an area BOEM previously considered, BOEM will review your SAP to determine if its impacts are consistent with those previously considered. If the anticipated effects of your proposed SAP activities are significantly different than those previously anticipated, we may determine that additional NEPA and other relevant Federal reviews are required. In that case, BOEM will notify you of such determination, and you must submit information required in paragraph (b) of this section as appropriate.

§ 585.612 How will my SAP be processed for Federal consistency under the Coastal Zone Management Act?

Your SAP will be processed based on whether it is submitted before or after your lease is issued:

If your SAP is submitted: Consistency review of your SAP will be handled as follows:
(a) Before lease issuance You will furnish a copy of your SAP, consistency certification, and necessary data and information to conduct an adequate consistency review to the applicable State CZMA agency or agencies if required by 15 CFR part 930, subpart D. and submit a copy to BOEM in accordance with § 585.111.
(b) After lease issuance You must submit a copy of your SAP, consistency certification, and necessary data and information pursuant to 15 CFR part 930, subpart E, to BOEM only if BOEM did not consider the proposed site assessment activities for your lease area under its previously submitted consistency determination under 15 CFR part 930, subpart C, and if required by 15 CFR part 930, subpart E. BOEM will forward to the applicable State CZMA agency or agencies one copy of your SAP, consistency certification, and necessary data and information required to conduct an adequate consistency review under 15 CFR part 930, subpart E, after BOEM has determined that all information requirements for the SAP are met.

§ 585.613 How will BOEM process my SAP?

(a) BOEM will review your submitted SAP, and additional information provided pursuant to § 585.611, to determine if it contains the information necessary to conduct our technical and environmental reviews.

(1) We will notify you if we deem your proposed facility or combination of facilities to be complex or significant; and

(2) We will notify you if your submitted SAP lacks any necessary information.

(b) BOEM will prepare a NEPA analysis, as appropriate.

(c) As appropriate, we will coordinate and consult with relevant Federal and State agencies, affected federally recognized Indian Tribes and executives of relevant local governments and will provide to other Federal, State, and local agencies and affected federally recognized Indian Tribes relevant nonproprietary data and information pertaining to your proposed activities.

(d) During the review process, we may request additional information if we determine that the information provided is not sufficient to complete the review and approval process. If you fail to provide the requested information, BOEM may disapprove your SAP.

(e) Upon completion of our technical and environmental reviews and other reviews required by Federal laws (e.g., CZMA), BOEM will approve, disapprove, or approve with conditions your SAP.

(1) If we approve your SAP, we will specify terms and conditions to be incorporated into your SAP. You must certify compliance with those terms and conditions, required under 30 CFR 285.615(b); and

(2) If we disapprove your SAP, we will inform you of the reasons and allow you an opportunity to submit a revised plan addressing our concerns, and we may suspend your lease, as appropriate, to give you a reasonable amount of time to resubmit the SAP.