The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

Contents of the Construction and Operations Plan

§ 585.626 What must I include in my COP?

(a) Project information may be provided using a PDE. When you provide information using a PDE, BOEM reserves the right to determine what range of values for any given parameter is acceptable. Your COP must include the following project-specific information, as applicable:

Project information: Including:
(1) Contact information The name, address, email address, and phone number of an authorized representative.
(2) Designation of operator, if applicable As provided in § 585.405.
(3) Commercial lease stipulations and compliance A description of the measures you took, or will take, to satisfy the conditions of any lease stipulations related to your proposed activities.
(4) A location plat, or indicative layout The range of surface locations and associated water depths for proposed structures, facilities, and appurtenances located both offshore and onshore, including all anchor and mooring data, and the location and associated water depths of all existing structures.
(5) General structural and project design, fabrication, and installation Preliminary design information for each facility associated with your project including information needed to justify any request for an operations period exceeding the length provided in this part or the lease.
(6) Deployment activities A description of safety, prevention, and environmental protection features or measures that you will use.
(7) A list of solid and liquid wastes generated Disposal methods and locations.
(8) A listing of chemical products used (if stored volume exceeds Environmental Protection Agency (EPA) reportable quantities) A list of chemical products used; the volume stored on location; their treatment, discharge, or disposal methods used; and the name and location of the onshore waste receiving, treatment, and/or disposal facility. A description of how these products would be brought onsite, the number of transfers that may take place, and the quantity that will be transferred each time.
(9) A description of any vessels, vehicles, and aircraft you will use to support your activities An estimate of the frequency and duration of vessel, vehicle, or aircraft traffic.
(10) A general description of the operating procedures and systems (i) Under normal conditions.
(ii) In the case of accidents or emergencies, including those that are natural or manmade.
(11) Decommissioning and site clearance procedures A discussion of general concepts and methodologies.
(12) A listing of all Federal, State, and local authorizations or approvals required to conduct the proposed activities, including commercial operations A statement indicating whether you have applied for or obtained such authorization or approval from the U.S. Coast Guard, U.S. Army Corps of Engineers, and any other applicable Federal, State, or local authorizers pertaining to energy gathering, transmission, or distribution (e.g., interconnection authorizations).
(13) Your proposed measures for avoiding, minimizing, reducing, eliminating, and monitoring environmental impacts A description of the measures you will use to avoid or minimize adverse effects and any potential incidental take before you conduct activities on your lease, and how you will mitigate environmental impacts from your proposed activities, including a description of the measures you will use as required by §§ 585.700 through 585.703.
(14) Information you incorporate by reference A list of the documents you have incorporated by reference and their public availability.
(15) A list of agencies and persons with whom you have communicated, or with whom you will communicate, regarding potential impacts associated with your proposed activities Contact information and issues discussed.
(16) References A bibliographic list of any document or published source that you cite as part of your plan. You may reference information and data discussed in other plans you previously submitted or that are otherwise readily available to BOEM.
(17) Financial assurance Statements attesting that the activities and facilities proposed in your COP are or will be covered by an appropriate bond or other approved financial assurance instrument as required in § 585.516 and §§ 585.525 through 585.529.
(18) Project verification strategy You must describe your strategy for compliance with 30 CFR285.705 through 285.714.
(19) Construction schedule A reasonable schedule of construction activity showing significant milestones, including the commencement of commercial operations consistent with the requirements of 30 CFR part 285, subpart G.
(20) Air quality information Information as described in § 585.700.
(21) Other information Additional information as required by BOEM.

(b) You must include reports that document the results of surveys and investigations that characterize and model the site of your proposed project. Your reports must address the following topics:

Topic: Purpose of report: Including:
(1) Geological and geotechnical To define the baseline geological conditions of the seabed and provide sufficient data to develop a geologic model, assess geologic hazards, and determine the feasibility of the proposed site for your proposed facility (i) Desktop studies to collect available data from published sources and nearby sites.
(ii) Geophysical surveys of the proposed area with sufficient areal coverage, depth penetration, and resolution to define the geological conditions of the site's seabed that could impact, or be impacted by, the proposed project.
(iii) Geotechnical investigations of sufficient scope and detail to: ground truth the geophysical surveys; support development of a geological model; assess potential geological hazards that could impact the proposed project; and provide geotechnical data for preliminary design of the facility, including type and approximate dimensions of the foundation.
(iv) An overall site characterization report for your facility that integrates the findings of your studies, surveys, and investigations; describes the geological model; contains supporting data and findings; and states your recommendations.
(2) Biological To determine the presence of biological features and marine resources A description of the results of biological surveys used to determine the presence of live bottoms, hard bottoms, topographic features, and other marine resources, including migratory populations such as fish, marine mammals, sea turtles, and sea birds.
(3) Archaeological resources and other historic properties To provide BOEM with required information to conduct review of the COP under NHPA Archaeological resources and other historic properties.
(4) Meteorological and oceanographic (metocean) To provide an overall understanding of the meteorological and oceanographic conditions at the site of the proposed facility, and to identify conditions that may pose a significant risk to the facility Desktop studies to collect available data from hindcast or re-analysis models and field measurements in sufficient detail to support preliminary design of the facility and support the analysis of wake effects, sediment mobility and scour, and navigational risks.

§ 585.627 What information and certifications must I submit with my COP to assist BOEM in complying with NEPA and other applicable laws?

(a) Your COP must contain detailed information and analysis to assist BOEM in complying with NEPA and other applicable laws. Your COP must contain information about those resources, conditions, and activities listed in the following table that your proposed activities may significantly affect, or that may have a significant effect on your proposed activities (including where the potential significance of the effect is unknown) and must contain any other information required by law:

Type of information: Including:
(1) Hazard information Meteorology, oceanography, sediment transport, geology, and shallow geological or manmade hazards.
(2) Water quality Turbidity and total suspended solids from construction; impact from vessel discharges.
(3) Biological resources Benthic communities, marine mammals, sea turtles, coastal and marine birds, fish and shellfish, plankton, seagrasses, and plant life.
(4) Threatened or endangered species As required by ESA.
(5) Sensitive biological resources or habitats Essential fish habitat, refuges, preserves, special management areas identified in coastal management programs, nearby marine protected areas, including State and Federal coastal and nearby marine protected areas, as well as national marine sanctuaries and nearby marine national monuments, rookeries, hard bottom habitat, chemosynthetic communities, calving grounds, barrier islands, beaches, dunes, and wetlands.
(6) Archaeological resources use, other historic property use, Indigenous traditional cultural use, or use pertaining to treaty and reserved rights with Native Americans or other Indigenous peoples Required information to conduct review of the COP under the NHPA or other applicable laws or policies, including treaty and reserved rights with Native Americans or other Indigenous peoples.
(7) Social and economic resources Employment, existing offshore and coastal infrastructure (including major sources of supplies, services, energy, and water), land use, subsistence resources and harvest practices, recreation, recreational and commercial fishing (including typical fishing seasons, location, and type), minority and lower income groups, coastal zone management programs, and a visual impact assessment.
(8) Coastal and marine uses Military activities, vessel traffic, fisheries, and exploration and development of other natural resources. This includes a navigational safety risk assessment that provides a description of the predicted impacts of the project to navigation and the measures you will use to avoid or minimize such adverse impacts. This document also must be submitted to the U.S. Coast Guard to assist with its analysis.
(9) Consistency Certification If required by CZMA regulations:
(i) 15 CFR part 930, subpart D, if your COP is submitted before lease issuance.
(ii) 15 CFR part 930, subpart E, if your COP is submitted after lease issuance.
(10) Other resources, conditions, and activities As identified by BOEM.

(b) You must submit one copy of your consistency certification. Your consistency certification must include:

(1) One copy of your consistency certification either under subsection 307(c)(3)(B) of the CZMA (16 U.S.C. 1456(c)(3)(B)) and 15 CFR 930.76, or under subsection 307(c)(3)(A) of the CZMA (16 U.S.C. 1456(c)(3)(A)) and 15 CFR 930.57, stating that the proposed activities described in detail in your plans comply with the enforceable policies of the applicable States' approved coastal management programs and will be conducted in a manner that is consistent with such programs; and

(2) “Necessary data and information,” as required by 15 CFR 930.58.

(c) You must submit a detailed description of an oil spill response plan to BSEE in compliance with 33 U.S.C. 1321, including information identified in 30 CFR part 254 that is applicable to your activities.

(d) You must submit a detailed description of your safety management system to BSEE as required by 30 CFR 285.810.

§ 585.628 How will BOEM process my COP?

(a) BOEM will review your submitted COP, including the information provided under § 585.627, to determine if it contains the information necessary to conduct our technical and environmental reviews. We will notify you if your submitted COP lacks any necessary information.

(b) BOEM will prepare an appropriate NEPA analysis.

(c) If your COP is subject to Federal consistency review under CZMA regulations at 15 CFR part 930, subpart E, you must submit your COP, consistency certification, and associated data and information under CZMA to BOEM after all information requirements for the COP are met, and the appropriate environmental assessment or draft environmental impact statement, if required, has been published. BOEM will forward the COP, consistency certification, and associated data and information to the applicable State CZMA agencies.

(d) As appropriate, BOEM will coordinate and consult with relevant Federal, State, and local agencies and affected federally recognized Indian Tribes, and provide to them relevant nonproprietary data and information pertaining to your proposed activities.

(e) During the review process, we may request additional information if we determine that the information provided is not sufficient to complete the review and approval process. If you fail to provide the requested information, BOEM may disapprove your COP.

(f) Upon completion of our technical and environmental reviews and other reviews required by Federal law (e.g., CZMA), BOEM will approve, disapprove, or approve your COP with conditions.

(1) If we approve your COP, we will specify terms and conditions to be incorporated into your COP. You must certify compliance with certain of those terms and conditions, as required under 30 CFR 285.633(a); and

(2) If we disapprove your COP, we will inform you of the reasons and allow you an opportunity to submit a revised plan addressing our concerns, and we may suspend the COP review period of your lease, as appropriate, to give you a reasonable amount of time to submit the revised plan.

(g) If BOEM approves your project easement, BOEM will issue an addendum to your lease specifying the terms of the project easement.

(1) The project easement will provide sufficient off-lease area to accommodate potential changes at the design and installation phases with respect to any facilities or activities necessary for your project.

(2) Unused portions of the project easement may be relinquished after construction is complete.

(3) A project easement is subject to the following conditions:

(i) The rights granted will not prevent the granting of other rights by the United States, either before or after the granting of the project easement, provided that any subsequent authorization issued by BOEM in the area of a previously issued project easement may not unreasonably interfere with activities approved or impede existing operations under the project easement; and

(ii) If the project easement is granted in an area where a lease, ROW or RUE grant has previously been issued, the project easement holder must agree that its activities will not unreasonably interfere with or impede existing operations under the lease or ROW or RUE grant.

§§ 585.629-585.630 [Reserved]