The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

§ 250.1743 How do I certify that a site is clear of obstructions?

(a) For a well site, you must submit to the appropriate District Manager within 30 days after you complete the verification activities a form BSEE-0124, Application for Permit to Modify, to include the following information:

(1) A signed certification that the well site area is cleared of all obstructions;

(2) The date the verification work was performed and the vessel used;

(3) The extent of the area surveyed;

(4) The survey method used;

(5) The results of the survey, including a list of any debris removed or a statement from the trawling contractor that no objects were recovered; and

(6) A post-trawling job plot or map showing the trawled area.

(b) For a platform or other facility site, you must submit the following information to the appropriate Regional Supervisor within 30 days after you complete the verification activities:

(1) A letter signed by an authorized company official certifying that the platform or other facility site area is cleared of all obstructions and that a company representative witnessed the verification activities;

(2) A letter signed by an authorized official of the company that performed the verification work for you certifying that it cleared the platform or other facility site area of all obstructions;

(3) The date the verification work was performed and the vessel used;

(4) The extent of the area surveyed;

(5) The survey method used;

(6) The results of the survey, including a list of any debris removed or a statement from the trawling contractor that no objects were recovered; and

(7) A post-trawling job plot or map showing the trawled area.