The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

PART 250 - OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF
Source:

76 FR 64462, Oct. 18, 2011, unless otherwise noted.

Subpart A - General
Authority and Definition of Terms
§ 250.101 Authority and applicability.

The Secretary of the Interior (Secretary) authorized the Bureau of Safety and Environmental Enforcement (BSEE) to regulate oil, gas, and sulphur exploration, development, and production operations on the Outer Continental Shelf (OCS). Under the Secretary's authority, the Director requires that all operations:

(a) Be conducted according to the OCS Lands Act (OCSLA), the regulations in this part, BSEE orders, the lease or right-of-way, and other applicable laws, regulations, and amendments; and

(b) Conform to sound conservation practice to preserve, protect, and develop mineral resources of the OCS to:

(1) Make resources available to meet the Nation's energy needs;

(2) Balance orderly energy resource development with protection of the human, marine, and coastal environments;

(3) Ensure the public receives a fair and equitable return on the resources of the OCS;

(4) Preserve and maintain free enterprise competition; and

(5) Minimize or eliminate conflicts between the exploration, development, and production of oil and natural gas and the recovery of other resources.

§ 250.102 What does this part do?

(a) This part 250 contains the regulations of the BSEE Offshore program that govern oil, gas, and sulphur exploration, development, and production operations on the OCS. When you conduct operations on the OCS, you must submit requests, applications, and notices, or provide supplemental information for BSEE approval.

(b) The following table of general references shows where to look for information about these processes.

For information about . . . Refer to . . .
(1) Applications for permit to drill, 30 CFR part 250, subpart D.
(2) Development and Production Plans (DPP), 30 CFR part 550, subpart B.
(3) Downhole commingling, 30 CFR part 250, subpart K.
(4) Exploration Plans (EP), 30 CFR part 550, subpart B.
(5) Flaring, 30 CFR part 250, subpart K.
(6) Gas measurement, 30 CFR part 250, subpart L.
(7) Off-lease geological and geophysical permits, 30 CFR part 551.
(8) Oil spill financial responsibility coverage, 30 CFR part 553.
(9) Oil and gas production safety systems, 30 CFR part 250, subpart H.
(10) Oil spill response plans, 30 CFR part 254.
(11) Oil and gas well-completion operations, 30 CFR part 250, subpart E.
(12) Oil and gas well-workover operations, 30 CFR part 250, subpart F.
(13) Decommissioning Activities, 30 CFR part 250, subpart Q.
(14) Platforms and structures, 30 CFR part 250, subpart I.
(15) Pipelines and Pipeline Rights-of-Way, 30 CFR part 250, subpart J and 30 CFR part 550, subpart J.
(16) Sulphur operations, 30 CFR part 250, subpart P.
(17) Training, 30 CFR part 250, subpart O.
(18) Unitization, 30 CFR part 250, subpart M.
(19) Safety and Environmental Management Systems (SEMS), 30 CFR part 250, subpart S.

[76 FR 64462, Oct. 18, 2011, as amended at 36148, June 6, 2016]

§ 250.103 Where can I find more information about the requirements in this part?

BSEE may issue Notices to Lessees and Operators (NTLs) that clarify, supplement, or provide more detail about certain requirements. NTLs may also outline what you must provide as required information in your various submissions to BSEE.

§ 250.104 How may I appeal a decision made under BSEE regulations?

To appeal orders or decisions issued under BSEE regulations in 30 CFR parts 250 to 282, follow the procedures in 30 CFR part 290.

§ 250.105 Definitions.

Terms used in this part will have the meanings given in the Act and as defined in this section:

Act means the OCS Lands Act, as amended (43 U.S.C. 1331 et seq.).

Affected State means with respect to any program, plan, lease sale, or other activity proposed, conducted, or approved under the provisions of the Act, any State:

(1) The laws of which are declared, under section 4(a)(2) of the Act, to be the law of the United States for the portion of the OCS on which such activity is, or is proposed to be, conducted;

(2) Which is, or is proposed to be, directly connected by transportation facilities to any artificial island or installation or other device permanently or temporarily attached to the seabed;

(3) Which is receiving, or according to the proposed activity, will receive oil for processing, refining, or transshipment that was extracted from the OCS and transported directly to such State by means of vessels or by a combination of means including vessels;

(4) Which is designated by the Secretary as a State in which there is a substantial probability of significant impact on or damage to the coastal, marine, or human environment, or a State in which there will be significant changes in the social, governmental, or economic infrastructure, resulting from the exploration, development, and production of oil and gas anywhere on the OCS; or

(5) In which the Secretary finds that because of such activity there is, or will be, a significant risk of serious damage, due to factors such as prevailing winds and currents to the marine or coastal environment in the event of any oil spill, blowout, or release of oil or gas from vessels, pipelines, or other transshipment facilities.

Air pollutant means any airborne agent or combination of agents for which the Environmental Protection Agency (EPA) has established, under section 109 of the Clean Air Act, national primary or secondary ambient air quality standards.

Analyzed geological information means data collected under a permit or a lease that have been analyzed. Analysis may include, but is not limited to, identification of lithologic and fossil content, core analysis, laboratory analyses of physical and chemical properties, well logs or charts, results from formation fluid tests, and descriptions of hydrocarbon occurrences or hazardous conditions.

Ancillary activities mean those activities on your lease or unit that you:

(1) Conduct to obtain data and information to ensure proper exploration or development of your lease or unit; and

(2) Can conduct without Bureau of Ocean Energy Management (BOEM) approval of an application or permit.

Archaeological interest means capable of providing scientific or humanistic understanding of past human behavior, cultural adaptation, and related topics through the application of scientific or scholarly techniques, such as controlled observation, contextual measurement, controlled collection, analysis, interpretation, and explanation.

Archaeological resource means any material remains of human life or activities that are at least 50 years of age and that are of archaeological interest.

Arctic OCS means the Beaufort Sea and Chukchi Sea Planning Areas (for more information on these areas, see the Proposed Final OCS Oil and Gas Leasing Program for 2012-2017 (June 2012) at http://www.boem.gov/Oil-and-Gas-Energy-Program/Leasing/Five-Year-Program/2012-2017/Program-Area-Maps/index.aspx).

Arctic OCS conditions means, for the purposes of this part, the conditions operators can reasonably expect during operations on the Arctic OCS. Such conditions, depending on the time of year, include, but are not limited to: Extreme cold, freezing spray, snow, extended periods of low light, strong winds, dense fog, sea ice, strong currents, and dangerous sea states. Remote location, relative lack of infrastructure, and the existence of subsistence hunting and fishing areas are also characteristic of the Arctic region.

Attainment area means, for any air pollutant, an area that is shown by monitored data or that is calculated by air quality modeling (or other methods determined by the Administrator of EPA to be reliable) not to exceed any primary or secondary ambient air quality standards established by EPA.

Best available and safest technology (BAST) means the best available and safest technologies that the BSEE Director determines to be economically feasible wherever failure of equipment would have a significant effect on safety, health, or the environment.

Best available control technology (BACT) means an emission limitation based on the maximum degree of reduction for each air pollutant subject to regulation, taking into account energy, environmental and economic impacts, and other costs. The Regional Supervisor will verify the BACT on a case-by-case basis, and it may include reductions achieved through the application of processes, systems, and techniques for the control of each air pollutant.

Cap and flow system means an integrated suite of equipment and vessels, including a capping stack and associated flow lines, that, when installed or positioned, is used to control the flow of fluids escaping from the well by conveying the fluids to the surface to a vessel or facility equipped to process the flow of oil, gas, and water. A cap and flow system is a high pressure system that includes the capping stack and piping necessary to convey the flowing fluids through the choke manifold to the surface equipment.

Capping stack means a mechanical device, including one that is pre-positioned, that can be installed on top of a subsea or surface wellhead or blowout preventer to stop the uncontrolled flow of fluids into the environment.

Coastal environment means the physical, atmospheric, and biological components, conditions, and factors that interactively determine the productivity, state, condition, and quality of the terrestrial ecosystem from the shoreline inward to the boundaries of the coastal zone.

Coastal zone means the coastal waters (including the lands therein and thereunder) and the adjacent shorelands (including the waters therein and thereunder) strongly influenced by each other and in proximity to the shorelands of the several coastal States. The coastal zone includes islands, transition and intertidal areas, salt marshes, wetlands, and beaches. The coastal zone extends seaward to the outer limit of the U.S. territorial sea and extends inland from the shorelines to the extent necessary to control shorelands, the uses of which have a direct and significant impact on the coastal waters, and the inward boundaries of which may be identified by the several coastal States, under the authority in section 305(b)(1) of the Coastal Zone Management Act (CZMA) of 1972.

Competitive reservoir means a reservoir in which there are one or more producible or producing well completions on each of two or more leases or portions of leases, with different lease operating interests, from which the lessees plan future production.

Containment dome means a non-pressurized container that can be used to collect fluids escaping from the well or equipment below the sea surface or from seeps by suspending the device over the discharge or seep location. The containment dome includes all of the equipment necessary to capture and convey fluids to the surface.

Correlative rights when used with respect to lessees of adjacent leases, means the right of each lessee to be afforded an equal opportunity to explore for, develop, and produce, without waste, minerals from a common source.

Data means facts and statistics, measurements, or samples that have not been analyzed, processed, or interpreted.

Departures mean approvals granted by the appropriate BSEE or BOEM representative for operating requirements/procedures other than those specified in the regulations found in this part. These requirements/procedures may be necessary to control a well; properly develop a lease; conserve natural resources, or protect life, property, or the marine, coastal, or human environment.

Development means those activities that take place following discovery of minerals in paying quantities, including but not limited to geophysical activity, drilling, platform construction, and operation of all directly related onshore support facilities, and which are for the purpose of producing the minerals discovered.

Development geological and geophysical (G&G) activities mean those G&G and related data-gathering activities on your lease or unit that you conduct following discovery of oil, gas, or sulphur in paying quantities to detect or imply the presence of oil, gas, or sulphur in commercial quantities.

Director means the Director of BSEE of the U.S. Department of the Interior, or an official authorized to act on the Director's behalf.

District Manager means the BSEE officer with authority and responsibility for operations or other designated program functions for a district within a BSEE Region. For activities on the Alaska OCS, any reference in this part to District Manager means the BSEE Regional Supervisor.

Easement means an authorization for a nonpossessory, nonexclusive interest in a portion of the OCS, whether leased or unleased, which specifies the rights of the holder to use the area embraced in the easement in a manner consistent with the terms and conditions of the granting authority.

Eastern Gulf of Mexico means all OCS areas of the Gulf of Mexico the BOEM Director decides are adjacent to the State of Florida. The Eastern Gulf of Mexico is not the same as the Eastern Planning Area, an area established for OCS lease sales.

Emission offsets mean emission reductions obtained from facilities, either onshore or offshore, other than the facility or facilities covered by the proposed Exploration Plan (EP) or Development and Production Plan (DPP).

Enhanced recovery operations mean pressure maintenance operations, secondary and tertiary recovery, cycling, and similar recovery operations that alter the natural forces in a reservoir to increase the ultimate recovery of oil or gas.

Existing facility, as used in 30 CFR 550.303, means an OCS facility described in an Exploration Plan or a Development and Production Plan approved before June 2, 1980.

Exploration means the commercial search for oil, gas, or sulphur. Activities classified as exploration include but are not limited to:

(1) Geophysical and geological (G&G) surveys using magnetic, gravity, seismic reflection, seismic refraction, gas sniffers, coring, or other systems to detect or imply the presence of oil, gas, or sulphur; and

(2) Any drilling conducted for the purpose of searching for commercial quantities of oil, gas, and sulphur, including the drilling of any additional well needed to delineate any reservoir to enable the lessee to decide whether to proceed with development and production.

Facility means:

(1) As used in § 250.130, all installations permanently or temporarily attached to the seabed on the OCS (including manmade islands and bottom-sitting structures). They include mobile offshore drilling units (MODUs) or other vessels engaged in drilling or downhole operations, used for oil, gas or sulphur drilling, production, or related activities. They include all floating production systems (FPSs), variously described as column-stabilized-units (CSUs); floating production, storage and offloading facilities (FPSOs); tension-leg platforms (TLPs); spars, etc. They also include facilities for product measurement and royalty determination (e.g., lease Automatic Custody Transfer Units, gas meters) of OCS production on installations not on the OCS. Any group of OCS installations interconnected with walkways, or any group of installations that includes a central or primary installation with processing equipment and one or more satellite or secondary installations is a single facility. The Regional Supervisor may decide that the complexity of the individual installations justifies their classification as separate facilities.

(2) As used in 30 CFR 550.303, means all installations or devices permanently or temporarily attached to the seabed. They include mobile offshore drilling units (MODUs), even while operating in the “tender assist” mode (i.e., with skid-off drilling units) or other vessels engaged in drilling or downhole operations. They are used for exploration, development, and production activities for oil, gas, or sulphur and emit or have the potential to emit any air pollutant from one or more sources. They include all floating production systems (FPSs), including column-stabilized-units (CSUs); floating production, storage and offloading facilities (FPSOs); tension-leg platforms (TLPs); spars, etc. During production, multiple installations or devices are a single facility if the installations or devices are at a single site. Any vessel used to transfer production from an offshore facility is part of the facility while it is physically attached to the facility.

(3) As used in § 250.490(b), means a vessel, a structure, or an artificial island used for drilling, well completion, well-workover, or production operations.

(4) As used in §§ 250.900 through 250.921, means all installations or devices permanently or temporarily attached to the seabed. They are used for exploration, development, and production activities for oil, gas, or sulphur and emit or have the potential to emit any air pollutant from one or more sources. They include all floating production systems (FPSs), including column-stabilized-units (CSUs); floating production, storage and offloading facilities (FPSOs); tension-leg platforms (TLPs); spars, etc. During production, multiple installations or devices are a single facility if the installations or devices are at a single site. Any vessel used to transfer production from an offshore facility is part of the facility while it is physically attached to the facility.

(5) As used in subpart S of this part, all types of structures permanently or temporarily attached to the seabed (e.g., mobile offshore drilling units (MODUs); floating production systems; floating production, storage and offloading facilities; tension-leg platforms; and spars) that are used for exploration, development, and production activities for oil, gas, or sulphur in the OCS. Facilities also include DOI-regulated pipelines.

Flaring means the burning of natural gas as it is released into the atmosphere.

Gas reservoir means a reservoir that contains hydrocarbons predominantly in a gaseous (single-phase) state.

Gas-well completion means a well completed in a gas reservoir or in the associated gas-cap of an oil reservoir.

Geological and geophysical (G&G) explorations mean those G&G surveys on your lease or unit that use seismic reflection, seismic refraction, magnetic, gravity, gas sniffers, coring, or other systems to detect or imply the presence of oil, gas, or sulphur in commercial quantities.

Governor means the Governor of a State, or the person or entity designated by, or under, State law to exercise the powers granted to such Governor under the Act.

H2S absent means:

(1) Drilling, logging, coring, testing, or producing operations have confirmed the absence of H2S in concentrations that could potentially result in atmospheric concentrations of 20 ppm or more of H2S; or

(2) Drilling in the surrounding areas and correlation of geological and seismic data with equivalent stratigraphic units have confirmed an absence of H2S throughout the area to be drilled.

H2S present means drilling, logging, coring, testing, or producing operations have confirmed the presence of H2S in concentrations and volumes that could potentially result in atmospheric concentrations of 20 ppm or more of H2S.

H2S unknown means the designation of a zone or geologic formation where neither the presence nor absence of H2S has been confirmed.

Human environment means the physical, social, and economic components, conditions, and factors that interactively determine the state, condition, and quality of living conditions, employment, and health of those affected, directly or indirectly, by activities occurring on the OCS.

Interpreted geological information means geological knowledge, often in the form of schematic cross sections, 3-dimensional representations, and maps, developed by determining the geological significance of data and analyzed geological information.

Interpreted geophysical information means geophysical knowledge, often in the form of schematic cross sections, 3-dimensional representations, and maps, developed by determining the geological significance of geophysical data and analyzed geophysical information.

Lease means an agreement that is issued under section 8 or maintained under section 6 of the Act and that authorizes exploration for, and development and production of, minerals. The term also means the area covered by that authorization, whichever the context requires.

Lease term pipelines mean those pipelines owned and operated by a lessee or operator that are completely contained within the boundaries of a single lease, unit, or contiguous (not cornering) leases of that lessee or operator.

Lessee means a person who has entered into a lease with the United States to explore for, develop, and produce the leased minerals. The term lessee also includes the BOEM-approved assignee of the lease, and the owner or the BOEM-approved assignee of operating rights for the lease.

Major Federal action means any action or proposal by the Secretary that is subject to the provisions of section 102(2)(C) of the National Environmental Policy Act of 1969, 42 U.S.C. (2)(C) (i.e., an action that will have a significant impact on the quality of the human environment requiring preparation of an environmental impact statement under section 102(2)(C) of the National Environmental Policy Act).

Marine environment means the physical, atmospheric, and biological components, conditions, and factors that interactively determine the productivity, state, condition, and quality of the marine ecosystem. These include the waters of the high seas, the contiguous zone, transitional and intertidal areas, salt marshes, and wetlands within the coastal zone and on the OCS.

Material remains mean physical evidence of human habitation, occupation, use, or activity, including the site, location, or context in which such evidence is situated.

Maximum efficient rate (MER) means the maximum sustainable daily oil or gas withdrawal rate from a reservoir that will permit economic development and depletion of that reservoir without detriment to ultimate recovery.

Maximum production rate (MPR) means the approved maximum daily rate at which oil or gas may be produced from a specified oil-well or gas-well completion.

Minerals include oil, gas, sulphur, geopressured-geothermal and associated resources, and all other minerals that are authorized by an Act of Congress to be produced.

Natural resources include, without limiting the generality thereof, oil, gas, and all other minerals, and fish, shrimp, oysters, clams, crabs, lobsters, sponges, kelp, and other marine animal and plant life but does not include water power or the use of water for the production of power.

Nonattainment area means, for any air pollutant, an area that is shown by monitored data or that is calculated by air quality modeling (or other methods determined by the Administrator of EPA to be reliable) to exceed any primary or secondary ambient air quality standard established by EPA.

Nonsensitive reservoir means a reservoir in which ultimate recovery is not decreased by high reservoir production rates.

Oil reservoir means a reservoir that contains hydrocarbons predominantly in a liquid (single-phase) state.

Oil reservoir with an associated gas cap means a reservoir that contains hydrocarbons in both a liquid and gaseous (two-phase) state.

Oil-well completion means a well completed in an oil reservoir or in the oil accumulation of an oil reservoir with an associated gas cap.

Operating rights mean any interest held in a lease with the right to explore for, develop, and produce leased substances.

Operator means the person the lessee(s) designates as having control or management of operations on the leased area or a portion thereof. An operator may be a lessee, the BSEE-approved or BOEM-approved designated agent of the lessee(s), or the holder of operating rights under a BOEM-approved operating rights assignment.

Outer Continental Shelf (OCS) means all submerged lands lying seaward and outside of the area of lands beneath navigable waters as defined in section 2 of the Submerged Lands Act (43 U.S.C. 1301) whose subsoil and seabed appertain to the United States and are subject to its jurisdiction and control.

Person includes a natural person, an association (including partnerships, joint ventures, and trusts), a State, a political subdivision of a State, or a private, public, or municipal corporation.

Pipelines are the piping, risers, and appurtenances installed for transporting oil, gas, sulphur, and produced waters.

Processed geological or geophysical information means data collected under a permit or a lease that have been processed or reprocessed. Processing involves changing the form of data to facilitate interpretation. Processing operations may include, but are not limited to, applying corrections for known perturbing causes, rearranging or filtering data, and combining or transforming data elements. Reprocessing is the additional processing other than ordinary processing used in the general course of evaluation. Reprocessing operations may include varying identified parameters for the detailed study of a specific problem area.

Production means those activities that take place after the successful completion of any means for the removal of minerals, including such removal, field operations, transfer of minerals to shore, operation monitoring, maintenance, and workover operations.

Production areas are those areas where flammable petroleum gas, volatile liquids or sulphur are produced, processed (e.g., compressed), stored, transferred (e.g., pumped), or otherwise handled before entering the transportation process.

Projected emissions mean emissions, either controlled or uncontrolled, from a source or sources.

Prospect means a geologic feature having the potential for mineral deposits.

Regional Director means the BSEE officer with responsibility and authority for a Region within BSEE.

Regional Supervisor means the BSEE officer with responsibility and authority for operations or other designated program functions within a BSEE Region.

Right-of-use means any authorization issued under 30 CFR Part 550 to use OCS lands.

Right-of-way pipelines are those pipelines that are contained within:

(1) The boundaries of a single lease or unit, but are not owned and operated by a lessee or operator of that lease or unit;

(2) The boundaries of contiguous (not cornering) leases that do not have a common lessee or operator;

(3) The boundaries of contiguous (not cornering) leases that have a common lessee or operator but are not owned and operated by that common lessee or operator; or

(4) An unleased block(s).

Routine operations, for the purposes of subpart F, mean any of the following operations conducted on a well with the tree installed:

(1) Cutting paraffin;

(2) Removing and setting pump-through-type tubing plugs, gas-lift valves, and subsurface safety valves that can be removed by wireline operations;

(3) Bailing sand;

(4) Pressure surveys;

(5) Swabbing;

(6) Scale or corrosion treatment;

(7) Caliper and gauge surveys;

(8) Corrosion inhibitor treatment;

(9) Removing or replacing subsurface pumps;

(10) Through-tubing logging (diagnostics);

(11) Wireline fishing;

(12) Setting and retrieving other subsurface flow-control devices; and

(13) Acid treatments.

Sensitive reservoir means a reservoir in which the production rate will affect ultimate recovery.

Significant archaeological resource means those archaeological resources that meet the criteria of significance for eligibility to the National Register of Historic Places as defined in 36 CFR 60.4, or its successor.

Source control and containment equipment (SCCE) means the capping stack, cap and flow system, containment dome, and/or other subsea and surface devices, equipment, and vessels the collective purpose of which is to control a spill source and stop the flow of fluids into the environment or to contain fluids escaping into the environment. “Surface devices” refers to equipment mounted or staged on a barge, vessel, or facility to separate, treat, store and/or dispose of fluids conveyed to the surface by the cap and flow system or the containment dome. “Subsea devices” includes, but is not limited to, remotely operated vehicles, anchors, buoyancy equipment, connectors, cameras, controls and other subsea equipment necessary to facilitate the deployment, operation, and retrieval of the SCCE. The SCCE does not include a blowout preventer.

Suspension means a granted or directed deferral of the requirement to produce (Suspension of Production (SOP)) or to conduct leaseholding operations (Suspension of Operations (SOO)).

Venting means the release of gas into the atmosphere without igniting it. This includes gas that is released underwater and bubbles to the atmosphere.

Waste of oil, gas, or sulphur means:

(1) The physical waste of oil, gas, or sulphur;

(2) The inefficient, excessive, or improper use, or the unnecessary dissipation of reservoir energy;

(3) The locating, spacing, drilling, equipping, operating, or producing of any oil, gas, or sulphur well(s) in a manner that causes or tends to cause a reduction in the quantity of oil, gas, or sulphur ultimately recoverable under prudent and proper operations or that causes or tends to cause unnecessary or excessive surface loss or destruction of oil or gas; or

(4) The inefficient storage of oil.

Welding means all activities connected with welding, including hot tapping and burning.

Wellbay is the area on a facility within the perimeter of the outermost wellheads.

Well-completion operations mean the work conducted to establish production from a well after the production-casing string has been set, cemented, and pressure-tested.

Well-control fluid means drilling mud, completion fluid, or workover fluid as appropriate to the particular operation being conducted.

Western Gulf of Mexico means all OCS areas of the Gulf of Mexico except those the BOEM Director decides are adjacent to the State of Florida. The Western Gulf of Mexico is not the same as the Western Planning Area, an area established for OCS lease sales.

Workover operations mean the work conducted on wells after the initial well-completion operation for the purpose of maintaining or restoring the productivity of a well.

You means a lessee, the owner or holder of operating rights, a designated operator or agent of the lessee(s), a pipeline right-of-way holder, or a State lessee granted a right-of-use and easement.

[76 FR 64462, Oct. 18, 2011, as amended at 78 FR 20439, Apr. 5, 2013; 81 FR 46560, July 15, 2016]

Performance Standards
§ 250.106 What standards will the Director use to regulate lease operations?

The Director will regulate all operations under a lease, right-of-use and easement, or right-of-way to:

(a) Promote orderly exploration, development, and production of mineral resources;

(b) Prevent injury or loss of life;

(c) Prevent damage to or waste of any natural resource, property, or the environment; and

(d) Cooperate and consult with affected States, local governments, other interested parties, and relevant Federal agencies.

§ 250.107 What must I do to protect health, safety, property, and the environment?

(a) You must protect health, safety, property, and the environment by:

(1) Performing all operations in a safe and workmanlike manner;

(2) Maintaining all equipment and work areas in a safe condition;

(3) Utilizing recognized engineering practices that reduce risks to the lowest level practicable when conducting design, fabrication, installation, operation, inspection, repair, and maintenance activities; and

(4) Complying with all lease, plan, and permit terms and conditions.

(b) You must immediately control, remove, or otherwise correct any hazardous oil and gas accumulation or other health, safety, or fire hazard.

(c) Best available and safest technology.

(1) On all new drilling and production operations and, except as provided in paragraph (c)(3) of this section, on existing operations, you must use the best available and safest technologies (BAST) which the Director determines to be economically feasible whenever the Director determines that failure of equipment would have a significant effect on safety, health, or the environment, except where the Director determines that the incremental benefits are clearly insufficient to justify the incremental costs of utilizing such technologies.

(2) Conformance with BSEE regulations will be presumed to constitute the use of BAST unless and until the Director determines that other technologies are required pursuant to paragraph (c)(1) of this section.

(3) The Director may waive the requirement to use BAST on a category of existing operations if the Director determines that use of BAST by that category of existing operations would not be practicable. The Director may waive the requirement to use BAST on an existing operation at a specific facility if you submit a waiver request demonstrating that the use of BAST would not be practicable.

(d) BSEE may issue orders to ensure compliance with this part, including, but not limited to, orders to produce and submit records and to inspect, repair, and/or replace equipment. BSEE may also issue orders to shut-in operations of a component or facility because of a threat of serious, irreparable, or immediate harm to health, safety, property, or the environment posed by those operations or because the operations violate law, including a regulation, order, or provision of a lease, plan, or permit.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 26014, Apr. 29, 2016; 81 FR 61915, Sept. 7, 2016]

§ 250.108 What requirements must I follow for cranes and other material-handling equipment?

(a) All cranes installed on fixed platforms must be operated in accordance with American Petroleum Institute's Recommended Practice for Operation and Maintenance of Offshore Cranes, API RP 2D (as incorporated by reference in § 250.198).

(b) All cranes installed on fixed platforms must be equipped with a functional anti-two block device.

(c) If a fixed platform is installed after March 17, 2003, all cranes on the platform must meet the requirements of American Petroleum Institute Specification for Offshore Pedestal Mounted Cranes, API Spec 2C (as incorporated by reference in § 250.198).

(d) All cranes manufactured after March 17, 2003, and installed on a fixed platform, must meet the requirements of API Spec 2C.

(e) You must maintain records specific to a crane or the operation of a crane installed on an OCS fixed platform, as follows:

(1) Retain all design and construction records, including installation records for any anti-two block safety devices, for the life of the crane. The records must be kept at the OCS fixed platform.

(2) Retain all inspection, testing, and maintenance records of cranes for at least 4 years. The records must be kept at the OCS fixed platform.

(3) Retain the qualification records of the crane operator and all rigger personnel for at least 4 years. The records must be kept at the OCS fixed platform.

(f) You must operate and maintain all other material-handling equipment in a manner that ensures safe operations and prevents pollution.

§ 250.109 What documents must I prepare and maintain related to welding?

(a) You must submit a Welding Plan to the District Manager before you begin drilling or production activities on a lease. You may not begin welding until the District Manager has approved your plan.

(b) You must keep the following at the site where welding occurs:

(1) A copy of the plan and its approval letter; and

(2) Drawings showing the designated safe-welding areas.

§ 250.110 What must I include in my welding plan?

You must include all of the following in the welding plan that you prepare under § 250.109:

(a) Standards or requirements for welders;

(b) How you will ensure that only qualified personnel weld;

(c) Practices and procedures for safe welding that address:

(1) Welding in designated safe areas;

(2) Welding in undesignated areas, including wellbay;

(3) Fire watches;

(4) Maintenance of welding equipment; and

(5) Plans showing all designated safe-welding areas.

(d) How you will prevent spark-producing activities (i.e., grinding, abrasive blasting/cutting and arc-welding) in hazardous locations.

§ 250.111 Who oversees operations under my welding plan?

A welding supervisor or a designated person in charge must be thoroughly familiar with your welding plan. This person must ensure that each welder is properly qualified according to the welding plan. This person also must inspect all welding equipment before welding.

§ 250.112 What standards must my welding equipment meet?

Your welding equipment must meet the following requirements:

(a) All engine-driven welding equipment must be equipped with spark arrestors and drip pans;

(b) Welding leads must be completely insulated and in good condition;

(c) Hoses must be leak-free and equipped with proper fittings, gauges, and regulators; and

(d) Oxygen and fuel gas bottles must be secured in a safe place.

§ 250.113 What procedures must I follow when welding?

(a) Before you weld, you must move any equipment containing hydrocarbons or other flammable substances at least 35 feet horizontally from the welding area. You must move similar equipment on lower decks at least 35 feet from the point of impact where slag, sparks, or other burning materials could fall. If moving this equipment is impractical, you must protect that equipment with flame-proofed covers, shield it with metal or fire-resistant guards or curtains, or render the flammable substances inert.

(b) While you weld, you must monitor all water-discharge-point sources from hydrocarbon-handling vessels. If a discharge of flammable fluids occurs, you must stop welding.

(c) If you cannot weld in one of the designated safe-welding areas that you listed in your safe welding plan, you must meet the following requirements:

(1) You may not begin welding until:

(i) The welding supervisor or designated person in charge advises in writing that it is safe to weld.

(ii) You and the designated person in charge inspect the work area and areas below it for potential fire and explosion hazards.

(2) During welding, the person in charge must designate one or more persons as a fire watch. The fire watch must:

(i) Have no other duties while actual welding is in progress;

(ii) Have usable firefighting equipment;

(iii) Remain on duty for 30 minutes after welding activities end; and

(iv) Maintain a continuous surveillance with a portable gas detector during the welding and burning operation if welding occurs in an area not equipped with a gas detector.

(3) You may not weld piping, containers, tanks, or other vessels that have contained a flammable substance unless you have rendered the contents inert and the designated person in charge has determined it is safe to weld. This does not apply to approved hot taps.

(4) You may not weld within 10 feet of a wellbay unless you have shut in all producing wells in that wellbay.

(5) You may not weld within 10 feet of a production area, unless you have shut in that production area.

(6) You may not weld while you drill, complete, workover, or conduct wireline operations unless:

(i) The fluids in the well (being drilled, completed, worked over, or having wireline operations conducted) are noncombustible; and

(ii) You have precluded the entry of formation hydrocarbons into the wellbore by either mechanical means or a positive overbalance toward the formation.

§ 250.114 How must I install, maintain, and operate electrical equipment?

The requirements in this section apply to all electrical equipment on all platforms, artificial islands, fixed structures, and their facilities.

(a) You must classify all areas according to API RP 500, Recommended Practice for Classification of Locations for Electrical Installations at Petroleum Facilities Classified as Class I, Division 1 and Division 2 (as incorporated by reference in § 250.198), or API RP 505, Recommended Practice for Classification of Locations for Electrical Installations at Petroleum Facilities Classified as Class I, Zone 0, Zone 1, and Zone 2 (as incorporated by reference in § 250.198).

(b) Employees who maintain your electrical systems must have expertise in area classification and the performance, operation and hazards of electrical equipment.

(c) You must install all electrical systems according to API RP 14F, Recommended Practice for Design and Installation of Electrical Systems for Fixed and Floating Offshore Petroleum Facilities for Unclassified and Class I, Division 1, and Division 2 Locations (as incorporated by reference in § 250.198), or API RP 14FZ, Recommended Practice for Design and Installation of Electrical Systems for Fixed and Floating Offshore Petroleum Facilities for Unclassified and Class I, Zone 0, Zone 1, and Zone 2 Locations (as incorporated by reference in § 250.198).

(d) On each engine that has an electric ignition system, you must use an ignition system designed and maintained to reduce the release of electrical energy.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 36149, June 6, 2016]

§ 250.115 What are the procedures for, and effects of, incorporation of documents by reference in this part?

For the documents incorporated by reference in this part:

(a) Incorporation by reference of a document is limited to the edition of the document, or the specific edition and supplement or addendum, that is cited in § 250.198. Future amendments or revisions of the incorporated document are not included. BSEE will publish any changes to the incorporation of the document in the Federal Register and amend § 250.198 as appropriate.

(b) BSEE may make a rule amending the incorporation of a document effective without prior opportunity for public comment when BSEE determines:

(1) That the revisions to the document result in safety improvements or represent new industry standard technology and do not impose undue costs on the affected parties; and

(2) BSEE meets the requirements for making a rule immediately effective under 5 U.S.C. 553.

(c) The effect of incorporation by reference of a document into the regulations in this part is that the incorporated document is a requirement. When a section in this part refers to an incorporated document, you are responsible for complying with the provisions of that entire document, except to the extent that the section that refers to the document provides otherwise. When a section in this part refers to a part of an incorporated document, you are responsible for complying with that part of the document as provided in that section.

(d) Under §§ 250.141 and 250.142, you may comply with a later edition of a specific document incorporated by reference, provided:

(1) You show that complying with the later edition provides a degree of protection, safety, or performance equal to or better than would be achieved by compliance with the listed edition; and

(2) You obtain prior written approval for alternative compliance from the authorized BSEE official.

[84 FR 21968, May 15, 2019]

§§ 250.116-250.117 [Reserved]
Gas Storage or Injection
§ 250.118 Will BSEE approve gas injection?

The Regional Supervisor may authorize you to inject gas on the OCS, on and off-lease, to promote conservation of natural resources and to prevent waste.

(a) To receive BSEE approval for injection, you must:

(1) Show that the injection will not result in undue interference with operations under existing leases; and

(2) Submit a written application to the Regional Supervisor for injection of gas.

(b) The Regional Supervisor will approve gas injection applications that:

(1) Enhance recovery;

(2) Prevent flaring of casinghead gas; or

(3) Implement other conservation measures approved by the Regional Supervisor.

§ 250.119 [Reserved]
§ 250.120 How does injecting, storing, or treating gas affect my royalty payments?

(a) If you produce gas from an OCS lease and inject it into a reservoir on the lease or unit for the purposes cited in § 250.118(b), you are not required to pay royalties until you remove or sell the gas from the reservoir.

(b) If you produce gas from an OCS lease and store it according to 30 CFR 550.119, you must pay royalty before injecting it into the storage reservoir.

(c) If you produce gas from an OCS lease and treat it at an off-lease or off-unit location, you must pay royalties when the gas is first produced.

§ 250.121 What happens when the reservoir contains both original gas in place and injected gas?

If the reservoir contains both original gas in place and injected gas, when you produce gas from the reservoir you must use a BSEE-approved formula to determine the amounts of injected or stored gas and gas original to the reservoir.

§ 250.122 What effect does subsurface storage have on the lease term?

If you use a lease area for subsurface storage of gas, it does not affect the continuance or expiration of the lease.

§ 250.123 [Reserved]
§ 250.124 Will BSEE approve gas injection into the cap rock containing a sulphur deposit?

To receive the Regional Supervisor's approval to inject gas into the cap rock of a salt dome containing a sulphur deposit, you must show that the injection:

(a) Is necessary to recover oil and gas contained in the cap rock; and

(b) Will not significantly increase potential hazards to present or future sulphur mining operations.

Fees
§ 250.125 Service fees.

(a) The table in this paragraph (a) shows the fees that you must pay to BSEE for the services listed. The fees will be adjusted periodically according to the Implicit Price Deflator for Gross Domestic Product by publication of a document in the Federal Register. If a significant adjustment is needed to arrive at the new actual cost for any reason other than inflation, then a proposed rule containing the new fees will be published in the Federal Register for comment.

Service - processing of the
following:
Fee amount 30 CFR citation
(1) Suspension of Operations/Suspension of Production (SOO/SOP) Request $2,123 § 250.171(e).
(2) Deepwater Operations Plan (DWOP) $3,599 § 250.292(q).
(3) Application for Permit to Drill (APD); Form BSEE-0123 $2,113 for initial applications only; no fee for revisions § 250.410(d); § 250.513(b); § 250.1617(a).
(4) Application for Permit to Modify (APM); Form BSEE-0124 $125 § 250.465(b); § 250.513(b); § 250.613(b); § 250.1618(a); § 250.1704(g).
(5) New Facility Production Safety System Application for facility with more than 125 components $5,426
$14,280 additional fee will be charged if BSEE conducts a pre-production inspection of a facility offshore, and $7,426 for an inspection of a facility while in a shipyard
A component is a piece of equipment or ancillary system that is protected by one or more of the safety devices required by API RP 14C (as incorporated by reference in § 250.198)
§ 250.842.
(6) New Facility Production Safety System Application for facility with 25-125 components $1,314
$8,967 additional fee will be charged if BSEE conducts a pre-production inspection of a facility offshore, and $5,141 for an inspection of a facility while in a shipyard
§ 250.842.
(7) New Facility Production Safety System Application for facility with fewer than 25 components $652 § 250.842.
(8) Production Safety System Application - Modification with more than 125 components reviewed $605 § 250.842.
(9) Production Safety System Application - Modification with 25-125 components reviewed $217 § 250.842.
(10) Production Safety System Application - Modification with fewer than 25 components reviewed $92 § 250.842.
(11) Platform Application - Installation - Under the Platform Verification Program $22,734 § 250.905(l).
(12) Platform Application - Installation - Fixed Structure Under the Platform Approval Program $3,256 § 250.905(l).
(13) Platform Application - Installation - Caisson/Well Protector $1,657 § 250.905(l)
(14) Platform Application - Modification/Repair $3,884 § 250.905(l).
(15) New Pipeline Application (Lease Term) $3,541 § 250.1000(b).
(16) Pipeline Application - Modification (Lease Term) $2,056 § 250.1000(b).
(17) Pipeline Application - Modification (ROW) $4,169 § 250.1000(b).
(18) Pipeline Repair Notification $388 § 250.1008(e).
(19) Pipeline Right-of-Way (ROW) Grant Application $2,771 § 250.1015(a).
(20) Pipeline Conversion of Lease Term to ROW $236 § 250.1015(a).
(21) Pipeline ROW Assignment $201 § 250.1018(b).
(22) 500 Feet From Lease/Unit Line Production Request $3,892 § 250.1156(a).
(23) Gas Cap Production Request $4,953 § 250.1157.
(24) Downhole Commingling Request $5,779 § 250.1158(a).
(25) Complex Surface Commingling and Measurement Application $4,056 § 250.1202(a); § 250.1203(b); § 250.1204(a).
(26) Simple Surface Commingling and Measurement Application $1,371 § 250.1202(a); § 250.1203(b); § 250.1204(a).
(27) Voluntary Unitization Proposal or Unit Expansion $12,619 § 250.1303(d).
(28) Unitization Revision $896 § 250.1303(d).
(29) Application to Remove a Platform or Other Facility $4,684 § 250.1727.
(30) Application to Decommission a Pipeline (Lease Term) $1,142 § 250.1751(a) or § 250.1752(a).
(31) Application to Decommission a Pipeline (ROW) $2,170 § 250.1751(a) or § 250.1752(a).

(b) Payment of the fees listed in paragraph (a) of this section must accompany the submission of the document for approval or be sent to an office identified by the Regional Director. Once a fee is paid, it is nonrefundable, even if an application or other request is withdrawn. If your application is returned to you as incomplete, you are not required to submit a new fee when you submit the amended application.

(c) Verbal approvals are occasionally given in special circumstances. Any action that will be considered a verbal permit approval requires either a paper permit application to follow the verbal approval or an electronic application submittal within 72 hours. Payment must be made with the completed paper or electronic application.

[76 FR 64462, Oct. 18, 2011, as amended at 77 FR 50891, Aug. 22, 2012; 78 FR 60213, Oct. 1, 2013; 81 FR 26014, Apr. 29, 2016; 81 FR 61916, Sept. 7, 2016]

§ 250.126 Electronic payment instructions.

(a) You must file all payments electronically through the Fees for Services page on the BSEE Web site at http://www.bsee.gov. This includes, but is not limited to, all OCS applications, permits, or any filing fees. You must include a copy of the Pay.gov confirmation receipt page with your application, permit, or filing fee.

(b) If you submitted an application or permit through eWell, you must use the interactive payment feature in that system, which directs you through Pay.gov to make a payment. It is recommended that you keep a copy of your payment confirmation receipt in the event that any questions arise regarding your transaction.

[81 FR 36149, June 6, 2016]

Inspections of Operations
§ 250.130 Why does BSEE conduct inspections?

BSEE will inspect OCS facilities and any vessels engaged in drilling or other downhole operations. These include facilities under jurisdiction of other Federal agencies that we inspect by agreement. We conduct these inspections:

(a) To verify that you are conducting operations according to the Act, the regulations, the lease, right-of-way, the BOEM-approved Exploration Plan or Development and Production Plans; or right-of-use and easement, and other applicable laws and regulations; and

(b) To determine whether equipment designed to prevent or ameliorate blowouts, fires, spillages, or other major accidents has been installed and is operating properly according to the requirements of this part.

§ 250.131 Will BSEE notify me before conducting an inspection?

BSEE conducts both scheduled and unscheduled inspections.

§ 250.132 What must I do when BSEE conducts an inspection?

(a) When BSEE conducts an inspection, you must provide:

(1) Access to all platforms, artificial islands, and other installations on your leases or associated with your lease, right-of-use and easement, or right-of-way; and

(2) Helicopter landing sites and refueling facilities for any helicopters we use to regulate offshore operations.

(b) You must make the following available for us to inspect:

(1) The area covered under a lease, right-of-use and easement, right-of-way, or permit;

(2) All improvements, structures, and fixtures on these areas; and

(3) All records of design, construction, operation, maintenance, repairs, or investigations on or related to the area.

§ 250.133 Will BSEE reimburse me for my expenses related to inspections?

Upon request, BSEE will reimburse you for food, quarters, and transportation that you provide for BSEE representatives while they inspect lease facilities and operations. You must send us your reimbursement request within 90 days of the inspection.

Disqualification
§ 250.135 What will BSEE do if my operating performance is unacceptable?

BSEE will determine if your operating performance is unacceptable. BSEE will refer a determination of unacceptable performance to BOEM, who may disapprove or revoke your designation as operator on a single facility or multiple facilities. We will give you adequate notice and opportunity for a review by BSEE officials before making a determination that your operating performance is unacceptable.

§ 250.136 How will BSEE determine if my operating performance is unacceptable?

In determining if your operating performance is unacceptable, BSEE will consider, individually or collectively:

(a) Accidents and their nature;

(b) Pollution events, environmental damages and their nature;

(c) Incidents of noncompliance;

(d) Civil penalties;

(e) Failure to adhere to OCS lease obligations; or

(f) Any other relevant factors.

Special Types of Approvals
§ 250.140 When will I receive an oral approval?

When you apply for BSEE approval of any activity, we normally give you a written decision. The following table shows circumstances under which we may give an oral approval.

When you . . . We may . . . And . . .
(a) Request approval orally Give you an oral approval, You must then confirm the oral request by sending us a written request within 72 hours.
(b) Request approval in writing, Give you an oral approval if quick action is needed, We will send you a written approval afterward. It will include any conditions that we place on the oral approval.
(c) Request approval orally for gas flaring, Give you an oral approval, You don't have to follow up with a written request unless the Regional Supervisor requires it. When you stop the approved flaring, you must promptly send a letter summarizing the location, dates and hours, and volumes of liquid hydrocarbons produced and gas flared by the approved flaring (see 30 CFR 250, subpart K).
§ 250.141 May I ever use alternate procedures or equipment?

You may use alternate procedures or equipment after receiving approval as described in this section.

(a) Any alternate procedures or equipment that you propose to use must provide a level of safety and environmental protection that equals or surpasses current BSEE requirements.

(b) You must receive the District Manager's or Regional Supervisor's written approval before you can use alternate procedures or equipment.

(c) To receive approval, you must either submit information or give an oral presentation to the appropriate Regional Supervisor. Your presentation must describe the site-specific application(s), performance characteristics, and safety features of the proposed procedure or equipment.

§ 250.142 How do I receive approval for departures?

We may approve departures to the operating requirements. You may apply for a departure by writing to the District Manager or Regional Supervisor.

§§ 250.143-250.144 [Reserved]
§ 250.145 How do I designate an agent or a local agent?

(a) You or your designated operator may designate for the Regional Supervisor's approval, or the Regional Director may require you to designate an agent empowered to fulfill your obligations under the Act, the lease, or the regulations in this part.

(b) You or your designated operator may designate for the Regional Supervisor's approval a local agent empowered to receive notices and submit requests, applications, notices, or supplemental information.

§ 250.146 Who is responsible for fulfilling leasehold obligations?

(a) When you are not the sole lessee, you and your co-lessee(s) are jointly and severally responsible for fulfilling your obligations under the provisions of 30 CFR parts 250 through 282 and 30 CFR parts 550 through 582 unless otherwise provided in these regulations.

(b) If your designated operator fails to fulfill any of your obligations under 30 CFR parts 250 through 282 and 30 CFR parts 550 through 582, the Regional Supervisor may require you or any or all of your co-lessees to fulfill those obligations or other operational obligations under the Act, the lease, or the regulations.

(c) Whenever the regulations in 30 CFR parts 250 through 282 and 30 CFR parts 550 through 582 require the lessee to meet a requirement or perform an action, the lessee, operator (if one has been designated), and the person actually performing the activity to which the requirement applies are jointly and severally responsible for complying with the regulation.

Naming and Identifying Facilities and Wells (Does Not Include MODUs)
§ 250.150 How do I name facilities and wells in the Gulf of Mexico Region?

(a) Assign each facility a letter designation except for those types of facilities identified in paragraph (c)(1) of this section. For example, A, B, CA, or CB.

(1) After a facility is installed, rename each predrilled well that was assigned only a number and was suspended temporarily at the mudline or at the surface. Use a letter and number designation. The letter used must be the same as that of the production facility, and the number used must correspond to the order in which the well was completed, not necessarily the number assigned when it was drilled. For example, the first well completed for production on Facility A would be renamed Well A-1, the second would be Well A-2, and so on; and

(2) When you have more than one facility on a block, each facility installed, and not bridge-connected to another facility, must be named using a different letter in sequential order. For example, EC 222A, EC 222B, EC 222C.

(3) When you have more than one facility on multiple blocks in a local area being co-developed, each facility installed and not connected with a walkway to another facility should be named using a different letter in sequential order with the block number corresponding to the block on which the platform is located. For example, EC 221A, EC 222B, and EC 223C.

(b) In naming multiple well caissons, you must assign a letter designation.

(c) In naming single well caissons, you must use certain criteria as follows:

(1) For single well caissons not attached to a facility with a walkway, use the well designation. For example, Well No. 1;

(2) For single well caissons attached to a facility with a walkway, use the same designation as the facility. For example, rename Well No.10 as A-10; and

(3) For single well caissons with production equipment, use a letter designation for the facility name and a letter plus number designation for the well. For example, the Well No. 1 caisson would be designated as Facility A, and the well would be Well A-1.

§ 250.151 How do I name facilities in the Pacific Region?

The operator assigns a name to the facility.

§ 250.152 How do I name facilities in the Alaska Region?

Facilities will be named and identified according to the Regional Director's directions.

§ 250.153 Do I have to rename an existing facility or well?

You do not have to rename facilities installed and wells drilled before January 27, 2000, unless the Regional Director requires it.

§ 250.154 What identification signs must I display?

(a) You must identify all facilities, artificial islands, and mobile offshore drilling units with a sign maintained in a legible condition.

(1) You must display an identification sign that can be viewed from the waterline on at least one side of the platform. The sign must use at least 3-inch letters and figures.

(2) When helicopter landing facilities are present, you must display an additional identification sign that is visible from the air. The sign must use at least 12-inch letters and figures and must also display the weight capacity of the helipad unless noted on the top of the helipad. If this sign is visible to both helicopter and boat traffic, then the sign in paragraph (a)(1) of this section is not required.

(3) Your identification sign must:

(i) List the name of the lessee or designated operator;

(ii) In the GOM OCS Region, list the area designation or abbreviation and the block number of the facility location as depicted on OCS Official Protraction Diagrams or leasing maps;

(iii) In the Pacific OCS Region, list the lease number on which the facility is located; and

(iv) List the name of the platform, structure, artificial island, or mobile offshore drilling unit.

(b) You must identify singly completed wells and multiple completions as follows:

(1) For each singly completed well, list the lease number and well number on the wellhead or on a sign affixed to the wellhead;

(2) For wells with multiple completions, downhole splitter wells, and multilateral wells, identify each completion in addition to the well name and lease number individually on the well flowline at the wellhead; and

(3) For subsea wells that flow individually into separate pipelines, affix the required sign on the pipeline or surface flowline dedicated to that subsea well at a convenient location on the receiving platform. For multiple subsea wells that flow into a common pipeline or pipelines, no sign is required.

§§ 250.160-250.167 [Reserved]
Suspensions
§ 250.168 May operations or production be suspended?

(a) You may request approval of a suspension, or the Regional Supervisor may direct a suspension (Directed Suspension), for all or any part of a lease or unit area.

(b) Depending on the nature of the suspended activity, suspensions are labeled either Suspensions of Operations (SOO) or Suspensions of Production (SOP).

§ 250.169 What effect does suspension have on my lease?

(a) A suspension may extend the term of a lease (see § 250.180(b), (d), and (e)). The extension is equal to the length of time the suspension is in effect, except as provided in paragraph (b) of this section.

(b) A Directed Suspension does not extend the term of a lease when the Regional Supervisor directs a suspension because of:

(1) Gross negligence; or

(2) A willful violation of a provision of the lease or governing statutes and regulations.

§ 250.170 How long does a suspension last?

(a) BSEE may issue suspensions for up to 5 years per suspension. The Regional Supervisor will set the length of the suspension based on the conditions of the individual case involved. BSEE may grant consecutive suspension periods.

(b) An SOO ends automatically when the suspended operation commences.

(c) An SOP ends automatically when production begins.

(d) A Directed Suspension normally ends as specified in the letter directing the suspension.

(e) BSEE may terminate any suspension when the Regional Supervisor determines the circumstances that justified the suspension no longer exist or that other lease conditions warrant termination. The Regional Supervisor will notify you of the reasons for termination and the effective date.

§ 250.171 How do I request a suspension?

You must submit your request for a suspension to the Regional Supervisor, and BSEE must receive the request before the end of the lease term (i.e., end of primary term, end of the 1-year period following the last leaseholding operation, and end of a current suspension). Your request must include:

(a) The justification for the suspension including the length of suspension requested;

(b) A reasonable schedule of work leading to the commencement or restoration of the suspended activity;

(c) A statement that a well has been drilled on the lease and determined to be producible according to § 250.1603 (SOP only), 30 CFR 550.115, or 30 CFR 550.116;

(d) A commitment to production (SOP only); and

(e) The service fee listed in § 250.125 of this subpart.

[76 FR 64462, Oct. 18, 2011, as amended at 82 FR 26744, June 9, 2017]

§ 250.172 When may the Regional Supervisor grant or direct an SOO or SOP?

The Regional Supervisor may grant or direct an SOO or SOP under any of the following circumstances:

(a) When necessary to comply with judicial decrees prohibiting any activities or the permitting of those activities. The effective date of the suspension will be the effective date required by the action of the court;

(b) When activities pose a threat of serious, irreparable, or immediate harm or damage. This would include a threat to life (including fish and other aquatic life), property, any mineral deposit, or the marine, coastal, or human environment. BSEE may require you to do a site-specific study (see § 250.177(a)).

(c) When necessary for the installation of safety or environmental protection equipment;

(d) When necessary to carry out the requirements of NEPA or to conduct an environmental analysis; or

(e) When necessary to allow for inordinate delays encountered in obtaining required permits or consents, including administrative or judicial challenges or appeals.

§ 250.173 When may the Regional Supervisor direct an SOO or SOP?

The Regional Supervisor may direct a suspension when:

(a) You failed to comply with an applicable law, regulation, order, or provision of a lease or permit; or

(b) The suspension is in the interest of National security or defense.

§ 250.174 When may the Regional Supervisor grant or direct an SOP?

The Regional Supervisor may grant or direct an SOP when the suspension is in the National interest, and it is necessary because the suspension will meet one of the following criteria:

(a) It will allow you to properly develop a lease, including time to construct and install production facilities;

(b) It will allow you time to obtain adequate transportation facilities;

(c) It will allow you time to enter a sales contract for oil, gas, or sulphur. You must show that you are making an effort to enter into the contract(s); or

(d) It will avoid continued operations that would result in premature abandonment of a producing well(s).

§ 250.175 When may the Regional Supervisor grant an SOO?

(a) The Regional Supervisor may grant an SOO when necessary to allow you time to begin drilling or other operations when you are prevented by reasons beyond your control, such as unexpected weather, unavoidable accidents, or drilling rig delays.

(b) The Regional Supervisor may grant an SOO when all of the following conditions are met:

(1) The lease was issued with a primary lease term of 5 years, or with a primary term of 8 years with a requirement to drill within 5 years;

(2) Before the end of the third year of the primary term, you or your predecessor in interest must have acquired and interpreted geophysical information that indicates:

(i) The presence of a salt sheet;

(ii) That all or a portion of a potential hydrocarbon-bearing formation may lie beneath or adjacent to the salt sheet; and

(iii) The salt sheet interferes with identification of the potential hydrocarbon-bearing formation.

(3) The interpreted geophysical information required under paragraph (b)(2) of this section must include full 3-D depth migration beneath the salt sheet and over the entire lease area.

(4) Before requesting the suspension, you have conducted or are conducting additional data processing or interpretation of the geophysical information with the objective of identifying a potential hydrocarbon-bearing formation.

(5) You demonstrate that additional time is necessary to:

(i) Complete current processing or interpretation of existing geophysical data or information;

(ii) Acquire, process, or interpret new geophysical data or information; or

(iii) Drill into the potential hydrocarbon-bearing formation identified as a result of the activities conducted in paragraphs (b)(2), (b)(4), and (b)(5) of this section.

(c) The Regional Supervisor may grant an SOO to conduct additional geological and geophysical data analysis that may lead to the drilling of a well below 25,000 feet true vertical depth below the datum at mean sea level (TVD SS) when all of the following conditions are met:

(1) The lease was issued with a primary lease term of:

(i) Five years; or

(ii) Eight years with a requirement to drill within 5 years.

(2) Before the end of the fifth year of the primary term, you or your predecessor in interest must have acquired and interpreted geophysical information that:

(i) Indicates that all or a portion of a potential hydrocarbon-bearing formation lies below 25,000 feet TVD SS; and

(ii) Includes full 3-D depth migration over the entire lease area.

(3) Before requesting the suspension, you have conducted or are conducting additional data processing or interpretation of the geophysical information with the objective of identifying a potential hydrocarbon-bearing geologic structure or stratigraphic trap lying below 25,000 feet TVD SS.

(4) You demonstrate that additional time is necessary to:

(i) Complete current processing or interpretation of existing geophysical data or information;

(ii) Acquire, process, or interpret new geophysical or geological data or information that would affect the decision to drill the same geologic structure or stratigraphic trap, as determined by the Regional Supervisor, identified in paragraphs (c)(2) and (c)(3) of this section; or

(iii) Drill a well below 25,000 feet TVD SS into the geologic structure or stratigraphic trap identified as a result of the activities conducted in paragraphs (c)(2), (c)(3), and (c)(4)(i) and (ii) of this section.

§ 250.176 Does a suspension affect my royalty payment?

A directed suspension may affect the payment of rental or royalties for the lease as provided in 30 CFR 1218.154.

§ 250.177 What additional requirements may the Regional Supervisor order for a suspension?

If BSEE grants or directs a suspension under paragraph § 250.172(b), the Regional Supervisor may require you to:

(a) Conduct a site-specific study.

(1) The Regional Supervisor must approve or prescribe the scope for any site-specific study that you perform.

(2) The study must evaluate the cause of the hazard, the potential damage, and the available mitigation measures.

(3) You must pay for the study unless you request, and the Regional Supervisor agrees to arrange, payment by another party.

(4) You must furnish copies and results of the study to the Regional Supervisor.

(5) BSEE will make the results available to other interested parties and to the public.

(6) The Regional Supervisor will use the results of the study and any other information that becomes available:

(i) To decide if the suspension can be lifted; and

(ii) To determine any actions that you must take to mitigate or avoid any damage to the environment, life, or property.

(b) Submit a revised Exploration Plan (including any required mitigating measures);

(c) Submit a revised Development and Production Plan (including any required mitigating measures); or

(d) Submit a revised Development Operations Coordination Document according to 30 CFR part 550, subpart B.

Primary Lease Requirements, Lease Term Extensions, and Lease Cancellations
§ 250.180 What am I required to do to keep my lease term in effect?

(a) If your lease is in its primary term:

(1) You must submit a report to the District Manager according to paragraphs (h) and (i) of this section whenever production begins initially, whenever production ceases during the last year of the primary term, and whenever production resumes during the last year of the primary term.

(2) Your lease expires at the end of its primary term unless you are conducting operations on your lease (see 30 CFR part 556). For purposes of this section, the term operations means, drilling, well-reworking, or production in paying quantities. The objective of the drilling or well-reworking must be to establish production in paying quantities on the lease.

(b) If you stop conducting operations during the last year of your primary lease term, your lease will expire unless you either resume operations or receive an SOO or an SOP from the Regional Supervisor under § 250.172, § 250.173, § 250.174, or § 250.175 before the end of the year after you stop operations.

(c) If you extend your lease term under paragraph (b) of this section, you must pay rental or minimum royalty, as appropriate, for each year or part of the year during which your lease continues in force beyond the end of the primary lease term.

(d) If you stop conducting operations on a lease that has continued beyond its primary term, your lease will expire unless you resume operations or receive an SOO or an SOP from the Regional Supervisor under § 250.172, § 250.173, § 250.174, or § 250.175 before the end of the year after you stop operations.

(e) You may ask the Regional Supervisor to allow you more than a year to resume operations on a lease continued beyond its primary term when operating conditions warrant. The request must be in writing and explain the operating conditions that warrant a longer period. In allowing additional time, the Regional Supervisor must determine that the longer period is in the National interest, and it conserves resources, prevents waste, or protects correlative rights.

(f) When you begin conducting operations on a lease that has continued beyond its primary term, you must immediately notify the District Manager either orally or by fax or e-mail and follow up with a written report according to paragraph (g) of this section.

(g) If your lease is continued beyond its primary term, you must submit a report to the District Manager under paragraphs (h) and (i) of this section whenever production begins initially, whenever production ceases, whenever production resumes before the end of the 1-year period after having ceased, or whenever drilling or well-reworking operations begin before the end of the 1-year period.

(h) The reports required by paragraphs (a) and (g) of this section must contain:

(1) Name of lessee or operator;

(2) The well number, lease number, area, and block;

(3) As appropriate, the unit agreement name and number; and

(4) A description of the operation and pertinent dates.

(i) You must submit the reports required by paragraphs (a) and (g) of this section within the following timeframes:

(1) Initialization of production - within 5 days of initial production.

(2) Cessation of production - within 15 days after the first full month of zero production.

(3) Resumption of production - within 5 days of resuming production after ceasing production under paragraph (i)(2) of this section.

(4) Drilling or well reworking operations - within 5 days of beginning and completing the leaseholding operations.

(j) For leases continued beyond the primary term, you must immediately report to the District Manager if operations do not begin before the end of the 1-year period.

[76 FR 64462, Oct. 18, 2011, as amended at 82 FR 26744, June 9, 2017]

§§ 250.181-250.185 [Reserved]
Information and Reporting Requirements
§ 250.186 What reporting information and report forms must I submit?

(a) You must submit information and reports as BSEE requires.

(1) You may obtain copies of forms from, and submit completed forms to, the District Manager or Regional Supervisor.

(2) Instead of paper copies of forms available from the District Manager or Regional Supervisor, you may use your own computer-generated forms that are equal in size to BSEE's forms. You must arrange the data on your form identical to the BSEE form. If you generate your own form and it omits terms and conditions contained on the official BSEE form, we will consider it to contain the omitted terms and conditions.

(3) You may submit digital data when the Region/District is equipped to accept it.

(b) When BSEE specifies, you must include, for public information, an additional copy of such reports.

(1) You must mark it Public Information

(2) You must include all required information, except information exempt from public disclosure under § 250.197 or otherwise exempt from public disclosure under law or regulation.

§ 250.187 What are BSEE's incident reporting requirements?

(a) You must report all incidents listed in § 250.188(a) and (b) to the District Manager. The specific reporting requirements for these incidents are contained in §§ 250.189 and 250.190.

(b) These reporting requirements apply to incidents that occur on the area covered by your lease, right-of-use and easement, pipeline right-of-way, or other permit issued by BOEM or BSEE, and that are related to operations resulting from the exercise of your rights under your lease, right-of-use and easement, pipeline right-of-way, or permit.

(c) Nothing in this subpart relieves you from making notifications and reports of incidents that may be required by other regulatory agencies.

(d) You must report all spills of oil or other liquid pollutants in accordance with 30 CFR 254.46.

§ 250.188 What incidents must I report to BSEE and when must I report them?

(a) You must report the following incidents to the District Manager immediately via oral communication, and provide a written follow-up report (hard copy or electronically transmitted) within 15 calendar days after the incident:

(1) All fatalities.

(2) All injuries that require the evacuation of the injured person(s) from the facility to shore or to another offshore facility.

(3) All losses of well control. “Loss of well control” means:

(i) Uncontrolled flow of formation or other fluids. The flow may be to an exposed formation (an underground blowout) or at the surface (a surface blowout);

(ii) Flow through a diverter; or

(iii) Uncontrolled flow resulting from a failure of surface equipment or procedures.

(4) All fires and explosions.

(5) All reportable releases of hydrogen sulfide (H2S) gas, as defined in § 250.490(l).

(6) All collisions that result in property or equipment damage greater than $25,000. “Collision” means the act of a moving vessel (including an aircraft) striking another vessel, or striking a stationary vessel or object (e.g., a boat striking a drilling rig or platform). “Property or equipment damage” means the cost of labor and material to restore all affected items to their condition before the damage, including, but not limited to, the OCS facility, a vessel, helicopter, or equipment. It does not include the cost of salvage, cleaning, gas-freeing, dry docking, or demurrage.

(7) All incidents involving structural damage to an OCS facility. “Structural damage” means damage severe enough so that operations on the facility cannot continue until repairs are made.

(8) All incidents involving crane or personnel/material handling operations.

(9) All incidents that damage or disable safety systems or equipment (including firefighting systems).

(b) You must provide a written report of the following incidents to the District Manager within 15 calendar days after the incident:

(1) Any injuries that result in one or more days away from work or one or more days on restricted work or job transfer. One or more days means the injured person was not able to return to work or to all of their normal duties the day after the injury occurred;

(2) All gas releases that initiate equipment or process shutdown;

(3) All incidents that require operations personnel on the facility to muster for evacuation for reasons not related to weather or drills;

(4) All other incidents, not listed in paragraph (a) of this section, resulting in property or equipment damage greater than $25,000.

(c) On the Arctic OCS, in addition to the requirements of paragraphs (a) and (b) of this section, you must provide to the BSEE inspector on location, if one is present, or to the Regional Supervisor, both of the following:

(1) An immediate oral report if any of the following occur:

(i) Any sea ice movement or condition that has the potential to affect your operation or trigger ice management activities;

(ii) The start and termination of ice management activities; or

(iii) Any “kicks” or operational issues that are unexpected and could result in the loss of well control.

(2) Within 24 hours after completing ice management activities, a written report of such activities that conforms to the content requirements in § 250.190.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 46560, July 15, 2016]

§ 250.189 Reporting requirements for incidents requiring immediate notification.

For an incident requiring immediate notification under § 250.188(a), you must notify the District Manager via oral communication immediately after aiding the injured and stabilizing the situation. Your oral communication must provide the following information:

(a) Date and time of occurrence;

(b) Operator, and operator representative's, name and telephone number;

(c) Contractor, and contractor representative's name and telephone number (if a contractor is involved in the incident or injury/fatality);

(d) Lease number, OCS area, and block;

(e) Platform/facility name and number, or pipeline segment number;

(f) Type of incident or injury/fatality;

(g) Operation or activity at time of incident (i.e., drilling, production, workover, completion, pipeline, crane, etc.); and

(h) Description of the incident, damage, or injury/fatality.

§ 250.190 Reporting requirements for incidents requiring written notification.

(a) For any incident covered under § 250.188, you must submit a written report within 15 calendar days after the incident to the District Manager. The report must contain the following information:

(1) Date and time of occurrence;

(2) Operator, and operator representative's name and telephone number;

(3) Contractor, and contractor representative's name and telephone number (if a contractor is involved in the incident or injury);

(4) Lease number, OCS area, and block;

(5) Platform/facility name and number, or pipeline segment number;

(6) Type of incident or injury;

(7) Operation or activity at time of incident (i.e., drilling, production, workover, completion, pipeline, crane etc.);

(8) Description of incident, damage, or injury (including days away from work, restricted work or job transfer), and any corrective action taken; and

(9) Property or equipment damage estimate (in U.S. dollars).

(b) You may submit a report or form prepared for another agency in lieu of the written report required by paragraph (a) of this section, provided the report or form contains all required information.

(c) The District Manager may require you to submit additional information about an incident on a case-by-case basis.

§ 250.191 How does BSEE conduct incident investigations?

Any investigation that BSEE conducts under the authority of sections 22(d)(1) and (2) of the Act (43 U.S.C. 1348(d)(1) and (2)) is a fact-finding proceeding with no adverse parties. The purpose of the investigation is to prepare a public report that determines the cause or causes of the incident. The investigation may involve panel meetings conducted by a chairperson appointed by BSEE. The following requirements apply to any panel meetings involving persons giving testimony:

(a) A person giving testimony may have legal or other representative(s) present to provide advice or counsel while the person is giving testimony. The chairperson may require a verbatim transcript to be made of all oral testimony. The chairperson also may accept a sworn written statement in lieu of oral testimony.

(b) Only panel members, and any experts the panel deems necessary, may address questions to any person giving testimony.

(c) The chairperson may issue subpoenas to persons to appear and provide testimony or documents at a panel meeting. A subpoena may not require a person to attend a panel meeting held at a location more than 100 miles from where a subpoena is served.

(d) Any person giving testimony may request compensation for mileage, and fees for services, within 90 days after the panel meeting. The compensated expenses must be similar to mileage and fees the U.S. District Courts allow.

§ 250.192 What reports and statistics must I submit relating to a hurricane, earthquake, or other natural occurrence?

(a) You must submit evacuation statistics to the Regional Supervisor for a natural occurrence, such as a hurricane, a tropical storm, or an earthquake. Statistics include facilities and rigs evacuated and the amount of production shut-in for gas and oil. You must:

(1) Submit the statistics by fax or e-mail (for activities in the BSEE GOM OCS Region, use Form BSEE-0132) as soon as possible when evacuation occurs. In lieu of submitting your statistics by fax or e-mail, you may submit them electronically in accordance with 30 CFR 250.186(a)(3);

(2) Submit the statistics on a daily basis by 11 a.m., as conditions allow, during the period of shut-in and evacuation;

(3) Inform BSEE when you resume production; and

(4) Submit the statistics either by BSEE district, or the total figures for your operations in a BSEE region.

(b) If your facility, production equipment, or pipeline is damaged by a natural occurrence, you must:

(1) Submit an initial damage report to the Regional Supervisor within 48 hours after you complete your initial evaluation of the damage. You must use Form BSEE-0143, Facility/Equipment Damage Report, to make this and all subsequent reports. In lieu of submitting Form BSEE-0143 by fax or e-mail, you may submit the damage report electronically in accordance with 30 CFR 250.186(a)(3). In the report, you must:

(i) Name the items damaged (e.g., platform or other structure, production equipment, pipeline);

(ii) Describe the damage and assess the extent of the damage (major, medium, minor); and

(iii) Estimate the time it will take to replace or repair each damaged structure and piece of equipment and return it to service. The initial estimate need not be provided on the form until availability of hardware and repair capability has been established (not to exceed 30 days from your initial report).

(2) Submit subsequent reports monthly and immediately whenever information submitted in previous reports changes until the damaged structure or equipment is returned to service. In the final report, you must provide the date the item was returned to service.

§ 250.193 Reports and investigations of possible violations.

(a) Any person may report to BSEE any hazardous or unsafe working condition on any facility engaged in OCS activities, and any possible violation or failure to comply with:

(1) Any provision of the Act,

(2) Any provision of a lease, approved plan, or permit issued under the Act,

(3) Any provision of any regulation or order issued under the Act, or

(4) Any other Federal law relating to safety of offshore oil and gas operations.

(b) To make a report under this section, a person is not required to know whether any legal requirement listed in paragraph (a) of this section has been violated.

(c) When BSEE receives a report of a possible violation, or when a BSEE employee detects a possible violation, BSEE will investigate according to BSEE procedures and notify any other Federal agency(ies) for further investigation, as appropriate.

(d) BSEE investigations of possible violations may include:

(1) Conducting interviews of personnel;

(2) Requiring the prompt production of documents, data, and other evidence;

(3) Requiring the preservation of all relevant evidence and access for BSEE investigators to such evidence; and

(4) Taking other actions and imposing other requirements as necessary to investigate possible violations and assure an orderly investigation.

(e)

(1) Reports should contain sufficient credible information to establish a reasonable basis for BSEE to investigate whether a violation or other hazardous or unsafe working condition exists.

(2) To report hazardous or unsafe working conditions or a possible violation:

(i) Contact BSEE by:

(A) Phone at 1-877-440-0173 (BSEE Toll-free Safety Hotline),

(B) Internet at www.bsee.gov, or

(C) Mail to: U.S. DOI/BSEE, 1849 C Street NW., Mail Stop 5438, Washington, DC 20240 Attention: IRU Hotline Operations.

(ii) Include the following items in the report:

(A) Name, address, and telephone number should be provided if you do not want to remain anonymous;

(B) The specific concern, provision or Federal law, if known, referenced in (a) that a person violated or with which a person failed to comply; and

(C) Any other facts, data, and applicable information.

(f) When a possible violation is reported, BSEE will protect a person's identity to the extent authorized by law.

[78 FR 20439, Apr. 5, 2013, as amended at 81 FR 36149, June 6, 2016]

§ 250.194 How must I protect archaeological resources?

(a-b) [Reserved]

(c) If you discover any archaeological resource while conducting operations in the lease or right-of-way area, you must immediately halt operations within the area of the discovery and report the discovery to the BSEE Regional Director. If investigations determine that the resource is significant, the Regional Director will tell you how to protect it.

§ 250.195 What notification does BSEE require on the production status of wells?

You must notify the appropriate BSEE District Manager when you successfully complete or recomplete a well for production. You must:

(a) Notify the District Manager within 5 working days of placing the well in a production status. You must confirm oral notification by telefax or e-mail within those 5 working days.

(b) Provide the following information in your notification:

(1) Lessee or operator name;

(2) Well number, lease number, and OCS area and block designations;

(3) Date you placed the well on production (indicate whether or not this is first production on the lease);

(4) Type of production; and

(5) Measured depth of the production interval.

§ 250.196 Reimbursements for reproduction and processing costs.

(a) BSEE will reimburse you for costs of reproducing data and information that the Regional Director requests if:

(1) You deliver geophysical and geological (G&G) data and information to BSEE for the Regional Director to inspect or select and retain;

(2) BSEE receives your request for reimbursement and the Regional Director determines that the requested reimbursement is proper; and

(3) The cost is at your lowest rate or at the lowest commercial rate established in the area, whichever is less.

(b) BSEE will reimburse you for the costs of processing geophysical information (that does not include cost of data acquisition):

(1) If, at the request of the Regional Director, you processed the geophysical data or information in a form or manner other than that used in the normal conduct of business; or

(2) If you collected the information under a permit that BSEE issued to you before October 1, 1985, and the Regional Director requests and retains the information.

(c) When you request reimbursement, you must identify reproduction and processing costs separately from acquisition costs.

(d) BSEE will not reimburse you for data acquisition costs or for the costs of analyzing or processing geological information or interpreting geological or geophysical information.

§ 250.197 Data and information to be made available to the public or for limited inspection.

BSEE will protect data and information that you submit under this part, and 30 CFR part 203, as described in this section. Paragraphs (a) and (b) of this section describe what data and information will be made available to the public without the consent of the lessee, under what circumstances, and in what time period. Paragraph (c) of this section describes what data and information will be made available for limited inspection without the consent of the lessee, and under what circumstances.

(a) All data and information you submit on BSEE forms will be made available to the public upon submission, except as specified in the following table:

On form . . . Data and information not immediately available are . . . Excepted data will be made available . . .
(1) BSEE-0123, Application for Permit to Drill, Items 15, 16, 22 through 25, When the well goes on production or according to the table in paragraph (b) of this section, whichever is earlier.
(2) BSEE-0123S, Supplemental APD Information Sheet, Items 3, 7, 8, 15 and 17, When the well goes on production or according to the table in paragraph (b) of this section, whichever is earlier.
(3) BSEE-0124, Application for Permit to Modify, Item 17, When the well goes on production or according to the table in paragraph (b) of this section, whichever is earlier.
(4) BSEE-0125, End of Operations Report, Items 12, 13, 17, 21, 22, 26 through 38, When the well goes on production or according to the table in paragraph (b) of this section, whichever is earlier. However, items 33 through 38 will not be released when the well goes on production unless the period of time in the table in paragraph (b) has expired.
(5) BSEE-0126, Well Potential Test Report, Item 101, 2 years after you submit it.
(6) [Reserved]
(7) BSEE-0133 Well Activity Report, Item 10 Fields [WELLBORE START DATE, TD DATE, OP STATUS, END DATE, MD, TVD, AND MW PPG]. Item 11 Fields [WELLBORE START DATE, TD DATE, PLUGBACK DATE, FINAL MD, AND FINAL TVD] and Items 12 through 15, When the well goes on production or according to the table in paragraph (b) of this section, whichever is earlier.
(8) BSEE-0133S Open Hole Data Report, Boxes 7 and 8, When the well goes on production or according to the table in paragraph (b) of this section, whichever is earlier.
(9) [Reserved]
(10) [Reserved]

(b) BSEE will release lease and permit data and information that you submit and BSEE retains, but that are not normally submitted on BSEE forms, according to the following table:

If . . . BSEE will release . . . At this time . . . Special provisions . . .
(1) The Director determines that data and information are needed for specific scientific or research purposes for the Government, Geophysical data, Geological data Interpreted G&G information, Processed G&G information, Analyzed geological information, At any time, BSEE will release data and information only if release would further the National interest without unduly damaging the competitive position of the lessee.
(2) Data or information is collected with high-resolution systems (e.g., bathymetry, side-scan sonar, subbottom profiler, and magnetometer) to comply with safety or environmental protection requirements, Geophysical data, Geological data, Interpreted G&G information, Processed geological information, Analyzed geological information, 60 days after BSEE receives the data or information, if the Regional Supervisor deems it necessary, BSEE will release the data and information earlier than 60 days if the Regional Supervisor determines it is needed by affected States to make decisions under 30 CFR 550, subpart B. The Regional Supervisor will reconsider earlier release if you satisfy him/her that it would unduly damage your competitive position.
(3) Your lease is no longer in effect, Geophysical data, Geological data, Processed G&G information Interpreted G&G information, Analyzed geological information, When your lease terminates, This release time applies only if the provisions in this table governing high-resolution systems and the provisions in 30 CFR 552.7 do not apply. The release time applies to the geophysical data and information only if acquired postlease for a lessee's exclusive use.
(4) Your lease is still in effect, Geophysical data, Processed geophysical information, Interpreted G&G information, 10 years after you submit the data and information, This release time applies only if the provisions in this table governing high-resolution systems and the provisions in 30 CFR 552.7 do not apply. This release time applies to the geophysical data and information only if acquired postlease for a lessee's exclusive use.
(5) Your lease is still in effect and within the primary term specified in the lease, Geological data, Analyzed geological information, 2 years after the required submittal date or 60 days after a lease sale if any portion of an offered lease is within 50 miles of a well, whichever is later, These release times apply only if the provisions in this table governing high-resolution systems and the provisions in 30 CFR 552.7 do not apply. If the primary term specified in the lease is extended under the heading of “Suspensions” in this subpart, the extension applies to this provision.
(6) Your lease is in effect and beyond the primary term specified in the lease, Geological data, Analyzed geological information, 2 years after the required submittal date, None.
(7) Data or information is submitted on well operations, Descriptions of downhole locations, operations, and equipment, When the well goes on production or when geological data is released according to §§ 250.197(b)(5) and (b)(6), whichever occurs earlier, Directional survey data may be released earlier to the owner of an adjacent lease according to Subpart D of this part.
(8) Data and information are obtained from beneath unleased land as a result of a well deviation that has not been approved by the District Manager or Regional Supervisor, Any data or information obtained, At any time, None.
(9) Except for high-resolution data and information released under paragraph (b)(2) of this section data and information acquired by a permit under 30 CFR part 551 are submitted by a lessee under 30 CFR part 203, 30 CFR part 250, or 30 CFR part 550, G&G data, analyzed geological information, processed and interpreted G&G information, Geological data and information: 10 years after BOEM issues the permit; Geophysical data: 50 years after BOEM issues the permit; Geophysical information: 25 years after BOEM issues the permit, None.

(c) BSEE may allow limited inspection, but only by persons with a direct interest in related BSEE decisions and issues in specific geographic areas, and who agree in writing to its confidentiality, of G&G data and information submitted under this part or 30 CFR part 203 that BSEE uses to:

(1) Make unitization determinations on two or more leases;

(2) Make competitive reservoir determinations;

(3) Ensure proper plans of development for competitive reservoirs;

(4) Promote operational safety;

(5) Protect the environment;

(6) [Reserved]; or

(7) Determine eligibility for royalty relief.

References
§ 250.198 Documents incorporated by reference.

Certain material is incorporated by reference into this part with the approval of the Director of the Federal Register under 5 U.S.C. 552(a) and 1 CFR part 51. All incorporated material is available for inspection at the Houston BSEE office at 1919 Smith Street Suite 14042, Houston, Texas 77002 and is available from the sources indicated in this section. It is also available for inspection at the National Archives and Records Administration (NARA). To make an appointment to inspect incorporated material at the Houston BSEE office, call 1-844-259-4779. For information on the availability of this material at NARA, call 202-741-6030 or go to http://www.archives.gov/federal-register/cfr/ibr-locations.html.

(a) American Concrete Institute (ACI), ACI Standards, 38800 Country Club Drive, Farmington Hills, MI 48331-3439: http://www.concrete.org; phone: 248-848-3700:

(1) ACI Standard 318-95, Building Code Requirements for Reinforced Concrete, 1995; incorporated by reference at § 250.901.

(2) ACI 318R-95, Commentary on Building Code Requirements for Reinforced Concrete, 1995; incorporated by reference at § 250.901.

(3) ACI 357R-84, Guide for the Design and Construction of Fixed Offshore Concrete Structures, 1984; reapproved 1997, incorporated by reference at § 250.901.

(b) American Gas Association (AGA Reports), 400 North Capitol Street NW, Suite 450, Washington, DC 20001, http://www.aga.org; phone: 202-824-7000;

(1) AGA Report No. 7 - Measurement of Natural Gas by Turbine Meters; Revised February 2006; incorporated by reference at § 250.1203(b);

(2) AGA Report No. 9 - Measurement of Gas by Multipath Ultrasonic Meters; Second Edition, April 2007; incorporated by reference at § 250.1203(b);

(3) AGA Report No. 10 - Speed of Sound in Natural Gas and Other Related Hydrocarbon Gases; Copyright 2003; incorporated by reference at § 250.1203(b).

(c) American Institute of Steel Construction, Inc. (AISC), AISC Standards, One East Wacker Drive, Suite 700, Chicago, IL 60601-1802; http://www.aisc.org; phone: 312-670-2400:

(1) ANSI/AISC 360-05, Specification for Structural Steel Buildings, incorporated by reference at § 250.901.

(2) [Reserved]

(d) American National Standards Institute (ANSI), http.www./webstore.ansi.org/; phone: 212-642-4900:

(1) ANSI/ASME B 16.5-2003, Pipe Flanges and Flanged Fittings, incorporated by reference at § 250.1002;

(2) ANSI/ASME B 31.8-2003, Gas Transmission and Distribution Piping Systems, incorporated by reference at § 250.1002;

(3) ANSI Z88.2-1992, American National Standard for Respiratory Protection, incorporated by reference at § 250.490.

(e) American Petroleum Institute (API), API Recommended Practices (RP), Specs, Standards, Manual of Petroleum Measurement Standards (MPMS) chapters, 1220 L Street, NW, Washington, DC 20005-4070; http://www.api.org; phone: 202-682-8000:

(1) API 510, Pressure Vessel Inspection Code: In-Service Inspection, Rating, Repair, and Alteration, Tenth Edition, May 2014; Addendum 1, May 2017; incorporated by reference at §§ 250.851(a) and 250.1629(b);

(2) API 570, Piping Inspection Code: In-service Inspection, Rating, Repair, and Alteration of Piping Systems, Fourth Edition, February 2016; Addendum 1, May 2017; incorporated by reference at § 250.841(b).

(3) API Bulletin 2INT-DG, Interim Guidance for Design of Offshore Structures for Hurricane Conditions, May 2007; incorporated by reference at § 250.901;

(4) API Bulletin 2INT-EX, Interim Guidance for Assessment of Existing Offshore Structures for Hurricane Conditions, May 2007; incorporated by reference at § 250.901;

(5) API Bulletin 2INT-MET, Interim Guidance on Hurricane Conditions in the Gulf of Mexico, May 2007; incorporated by reference at § 250.901;

(6) API Bulletin 92L, Drilling Ahead Safely with Lost Circulation in the Gulf of Mexico, First Edition, August 2015; incorporated by reference at § 250.427(b);

(7) API MPMS Chapter 1 - Vocabulary, Second Edition, July 1994; incorporated by reference at § 250.1201;

(8) API MPMS Chapter 2 - Tank Calibration, Section 2A - Measurement and Calibration of Upright Cylindrical Tanks by the Manual Tank Strapping Method, First Edition, February 1995; reaffirmed August 2017; incorporated by reference at § 250.1202;

(9) API MPMS Chapter 2 - Tank Calibration, Section 2B - Calibration of Upright Cylindrical Tanks Using the Optical Reference Line Method, First Edition, March 1989; reaffirmed April 2019 (including Addendum 1, October 2019); incorporated by reference at § 250.1202;

(10) API MPMS Chapter 3 - Tank Gauging, Section 1A - Standard Practice for the Manual Gauging of Petroleum and Petroleum Products, Second Edition, August 2005; incorporated by reference at § 250.1202;

(11) API MPMS Chapter 3 - Tank Gauging, Section 1B - Standard Practice for Level Measurement of Liquid Hydrocarbons in Stationary Tanks by Automatic Tank Gauging, Second Edition, June 2001; reaffirmed February 2016; incorporated by reference at § 250.1202;

(12) API MPMS Chapter 4 - Proving Systems, Section 1 - Introduction, Third Edition, February 2005; reaffirmed June 2014; incorporated by reference at § 250.1202;

(13) API MPMS Chapter 4 - Proving Systems, Section 2 - Displacement Provers, Third Edition, September 2003; incorporated by reference at § 250.1202;

(14) API MPMS Chapter 4 - Proving Systems, Section 4 - Tank Provers, Second Edition, May 1998, reaffirmed May 2015; incorporated by reference at § 250.1202;

(15) API MPMS Chapter 4 - Proving Systems, Section 5 - Master-Meter Provers, Second Edition, May 2000, reaffirmed, August 2005; incorporated by reference at § 250.1202;

(16) API MPMS Chapter 4 - Proving Systems, Section 6 - Pulse Interpolation, Second Edition, May 1999; Errata April 2007; reaffirmed October 2013; incorporated by reference at § 250.1202;

(17) API MPMS Chapter 4 - Proving Systems, Section 7 - Field Standard Test Measures, Second Edition, December 1998; reaffirmed 2003; incorporated by reference at § 250.1202;

(18) API MPMS Chapter 4 - Proving Systems, Section 8 - Operation of Proving Systems; First Edition, reaffirmed March 2007; incorporated by reference at § 250.1202(a), (f), and (g);

(19) API MPMS Chapter 5 - Metering, Section 1 - General Considerations for Measurement by Meters, Fourth Edition, September 2005; incorporated by reference at § 250.1202;

(20) API MPMS Chapter 5 - Metering, Section 2 - Measurement of Liquid Hydrocarbons by Displacement Meters, Third Edition, September 2005; reaffirmed July 2015; incorporated by reference at § 250.1202;

(21) API MPMS Chapter 5 - Metering, Section 3 - Measurement of Liquid Hydrocarbons by Turbine Meters, Fifth Edition, September 2005; reaffirmed August 1, 2014; incorporated by reference at § 250.1202;

(22) API MPMS Chapter 5 - Metering, Section 4 - Accessory Equipment for Liquid Meters, Fourth Edition, September 2005; reaffirmed August 2015; incorporated by reference at § 250.1202;

(23) API MPMS Chapter 5 - Metering, Section 5 - Fidelity and Security of Flow Measurement Pulsed-Data Transmission Systems, Second Edition, August 2005; reaffirmed August 2015; incorporated by reference at § 250.1202;

(24) API MPMS Chapter 5 - Metering, Section 6 - Measurement of Liquid Hydrocarbons by Coriolis Meters; First Edition, October 2002; reaffirmed November 2013; incorporated by reference at § 250.1202;

(25) API MPMS Chapter 5 - Metering, Section 8 - Measurement of Liquid Hydrocarbons by Ultrasonic Flow Meters Using Transit Time Technology; First Edition, February 2005; incorporated by reference at § 250.1202(a);

(26) API MPMS Chapter 6 - Metering Assemblies, Section 1 - Lease Automatic Custody Transfer (LACT) Systems, Second Edition, May 1991; reaffirmed May 2012; incorporated by reference at § 250.1202;

(27) API MPMS Chapter 6 - Metering Assemblies, Section 6 - Pipeline Metering Systems, Second Edition, May 1991; reaffirmed December 2017; incorporated by reference at § 250.1202;

(28) API MPMS Chapter 6 - Metering Assemblies, Section 7 - Metering Viscous Hydrocarbons, Second Edition, May 1991; reaffirmed March 2018; incorporated by reference at § 250.1202;

(29) API MPMS Chapter 7 - Temperature Determination, First Edition, June 2001; reaffirmed, March 2007; incorporated by reference at § 250.1202;

(30) API MPMS Chapter 8 - Sampling, Section 1 - Standard Practice for Manual Sampling of Petroleum and Petroleum Products, Third Edition, October 1995; reaffirmed, March 2006; incorporated by reference at § 250.1202;

(31) API MPMS Chapter 8 - Sampling, Section 2 - Standard Practice for Automatic Sampling of Liquid Petroleum and Petroleum Products, Second Edition, October 1995; reaffirmed, June 2005; incorporated by reference at § 250.1202;

(32) API MPMS Chapter 9 - Density Determination, Section 1 - Standard Test Method for Density, Relative Density (Specific Gravity), or API Gravity of Crude Petroleum and Liquid Petroleum Products by Hydrometer Method, Second Edition, December 2002; reaffirmed October 2005; incorporated by reference at § 250.1202(a) and (l);

(33) API MPMS Chapter 9 - Density Determination, Section 2 - Standard Test Method for Density or Relative Density of Light Hydrocarbons by Pressure Hydrometer, Second Edition, March 2003; incorporated by reference at § 250.1202;

(34) API MPMS Chapter 10 - Sediment and Water, Section 1 - Standard Test Method for Sediment in Crude Oils and Fuel Oils by the Extraction Method, Third Edition, November 2007; reaffirmed October 2012; incorporated by reference at § 250.1202;

(35) API MPMS Chapter 10 - Sediment and Water, Section 2 - Standard Test Method for Water in Crude Oil by Distillation, Second Edition, November 2007; incorporated by reference at § 250.1202;

(36) API MPMS Chapter 10 - Sediment and Water, Section 3 - Standard Test Method for Water and Sediment in Crude Oil by the Centrifuge Method (Laboratory Procedure), Third Edition, May 2008; incorporated by reference at § 250.1202;

(37) API MPMS Chapter 10 - Sediment and Water, Section 4 - Determination of Water and/or Sediment in Crude Oil by the Centrifuge Method (Field Procedure), Third Edition, December 1999; incorporated by reference at § 250.1202;

(38) API MPMS Chapter 10 - Sediment and Water, Section 9 - Standard Test Method for Water in Crude Oils by Coulometric Karl Fischer Titration, Second Edition, December 2002; reaffirmed 2005; incorporated by reference at § 250.1202;

(39) API MPMS Chapter 11.1 - Volume Correction Factors, Volume 1, Table 5A - Generalized Crude Oils and JP-4 Correction of Observed API Gravity to API Gravity at 60 °F, and Table 6A - Generalized Crude Oils and JP-4 Correction of Volume to 60 °F Against API Gravity at 60 °F, API Standard 2540, First Edition, August 1980; reaffirmed March 1997; incorporated by reference at § 250.1202;

(40) API MPMS Chapter 11.2.2 - Compressibility Factors for Hydrocarbons: 0.350-0.637 Relative Density (60 °F/60 °F) and −50 °F to 140 °F Metering Temperature, Second Edition, October 1986; reaffirmed: December 2007; incorporated by reference at § 250.1202;

(41) API MPMS Chapter 11 - Physical Properties Data, Section 1 - Temperature and Pressure Volume Correction Factors for Generalized Crude Oils, Refined Products, and Lubricating Oils; May 2004 (incorporating Addendum 1, September 2007); incorporated by reference at § 250.1202(a), (g), and (l);

(42) API MPMS Chapter 11 - Physical Properties Data, Addendum to Section 2, Part 2 - Compressibility Factors for Hydrocarbons, Correlation of Vapor Pressure for Commercial Natural Gas Liquids, First Edition, December 1994; reaffirmed, December 2002; incorporated by reference at § 250.1202;

(43) API MPMS, Chapter 12 - Calculation of Petroleum Quantities, Section 2 - Calculation of Petroleum Quantities Using Dynamic Measurement Methods and Volumetric Correction Factors, Part 1 - Introduction, Second Edition, May 1995; reaffirmed March 2014; incorporated by reference at § 250.1202;

(44) API MPMS, Chapter 12 - Calculation of Petroleum Quantities, Section 2 - Calculation of Petroleum Quantities Using Dynamic Measurement Methods and Volumetric Correction Factors, Part 2 - Measurement Tickets, Third Edition, June 2003; reaffirmed February 2016; incorporated by reference at § 250.1202;

(45) API MPMS Chapter 12 - Calculation of Petroleum Quantities, Section 2 - Calculation of Petroleum Quantities Using Dynamic Measurement Methods and Volumetric Correction Factors, Part 3 - Proving Reports; First Edition, October 1998, reaffirmed March 2014; incorporated by reference at § 250.1202(a) and (g);

(46) API MPMS Chapter 12 - Calculation of Petroleum Quantities, Section 2 - Calculation of Petroleum Quantities Using Dynamic Measurement Methods and Volumetric Correction Factors, Part 4 - Calculation of Base Prover Volumes by the Waterdraw Method, First Edition, December 1997; reaffirmed September 2014; incorporated by reference at § 250.1202(a), (f), and (g);

(47) API MPMS Chapter 14 - Natural Gas Fluids Measurement, Section 3 - Concentric, Square-Edged Orifice Meters, Part 1 - General Equations and Uncertainty Guidelines, Third Edition, September 1990; reaffirmed, January 2003; incorporated by reference at § 250.1203;

(48) API MPMS Chapter 14 - Natural Gas Fluids Measurement, Section 3 - Concentric, Square-Edged Orifice Meters, Part 2 - Specification and Installation Requirements, Fourth Edition, April 2000; reaffirmed March 2006; incorporated by reference at § 250.1203;

(49) API MPMS Chapter 14 - Natural Gas Fluids Measurement, Section 3 - Concentric, Square-Edged Orifice Meters; Part 3 - Natural Gas Applications; Third Edition, August 1992; Errata March 1994, reaffirmed, February 2009; incorporated by reference at § 250.1203;

(50) API MPMS, Chapter 14.5/GPA Standard 2172-09; Calculation of Gross Heating Value, Relative Density, Compressibility and Theoretical Hydrocarbon Liquid Content for Natural Gas Mixtures for Custody Transfer; Third Edition, January 2009; reaffirmed February 2014; incorporated by reference at § 250.1203;

(51) API MPMS Chapter 14 - Natural Gas Fluids Measurement, Section 6 - Continuous Density Measurement, Second Edition, April 1991; reaffirmed, February 2006; incorporated by reference at § 250.1203;

(52) API MPMS Chapter 14 - Natural Gas Fluids Measurement, Section 8 - Liquefied Petroleum Gas Measurement, Second Edition, July 1997; reaffirmed, March 2006; incorporated by reference at § 250.1203;

(53) API MPMS Chapter 20 - Section 1 - Allocation Measurement, First Edition, September 1993; reaffirmed October 2006; incorporated by reference at § 250.1202;

(54) API MPMS Chapter 21 - Flow Measurement Using Electronic Metering Systems, Section 1 - Electronic Gas Measurement, First Edition, August 1993; reaffirmed, July 2005; incorporated by reference at § 250.1203;

(55) API MPMS Chapter 21 - Flow Measurement Using Electronic Metering Systems, Section 2 - Electronic Liquid Volume Measurement Using Positive Displacement and Turbine Meters; First Edition, June 1998; reaffirmed October 2016; incorporated by reference at § 250.1202(a);

(56) API MPMS Chapter 21 - Flow Measurement Using Electronic Metering Systems, Addendum to Section 2 - Flow Measurement Using Electronic Metering Systems, Inferred Mass; First Edition, reaffirmed February 2006; incorporated by reference at § 250.1202(a);

(57) API RP 2A-WSD, Recommended Practice for Planning, Designing and Constructing Fixed Offshore Platforms - Working Stress Design, Twenty-first Edition, December 2000; Errata and Supplement 1, December 2002; Errata and Supplement 2, September 2005; Errata and Supplement 3, October 2007; incorporated by reference at §§ 250.901, 250.908, 250.919, and 250.920;

(58) API RP 2D, Operation and Maintenance of Offshore Cranes, Sixth Edition, May 2007; incorporated by reference at § 250.108;

(59) API RP 2FPS, RP for Planning, Designing, and Constructing Floating Production Systems; First Edition, March 2001; incorporated by reference at § 250.901;

(60) API RP 2I, In-Service Inspection of Mooring Hardware for Floating Structures; Third Edition, April 2008; incorporated by reference at § 250.901(a) and (d);

(61) ANSI/API RP 2N, Third Edition, “Recommended Practice for Planning, Designing, and Constructing Structures and Pipelines for Arctic Conditions”, Third Edition, April 2015; incorporated by reference at § 250.470(g);

(62) API RP 2RD, Recommended Practice for Design of Risers for Floating Production Systems (FPSs) and Tension-Leg Platforms (TLPs), First Edition, June 1998; reaffirmed, May 2006, Errata, June 2009; incorporated by reference at §§ 250.733, 250.800(c), 250.901(a), (d), and 250.1002(b);

(63) API RP 2SK, Design and Analysis of Stationkeeping Systems for Floating Structures, Third Edition, October 2005, Addendum, May 2008, reaffirmed June 2015; incorporated by reference at §§ 250.800(c) and 250.901(a) and (d);

(64) API RP 2SM, Recommended Practice for Design, Manufacture, Installation, and Maintenance of Synthetic Fiber Ropes for Offshore Mooring, First Edition, March 2001, Addendum, May 2007; incorporated by reference at §§ 250.800(c) and 250.901(a) and (d);

(65) API RP 2T, Recommended Practice for Planning, Designing, and Constructing Tension Leg Platforms, Second Edition, August 1997; incorporated by reference at § 250.901(a) and (d);

(66) ANSI/API RP 14B, Design, Installation, Operation, Test, and Redress of Subsurface Safety Valve Systems, Sixth Edition, September 2015; incorporated by reference at §§ 250.802(b), 250.803(a), 250.814(d), 250.828(c), and 250.880(c);

(67) API RP 14C, Recommended Practice for Analysis, Design, Installation, and Testing of Basic Surface Safety Systems for Offshore Production Platforms, Seventh Edition, March 2001, reaffirmed: March 2007; incorporated by reference at §§ 250.125(a), 250.292(j), 250.841(a), 250.842(a), 250.850, 250.852(a), 250.855, 250.856(a), 250.858(a), 250.862(e), 250.865(a), 250.867(a), 250.869(a) through (c), 250.872(a), 250.873(a), 250.874(a), 250.880(b) and (c), 250.1002(d), 250.1004(b), 250.1628(c) and (d), 250.1629(b), and 250.1630(a);

(68) API RP 14E, Recommended Practice for Design and Installation of Offshore Production Platform Piping Systems, Fifth Edition, October 1991; reaffirmed, January 2013; incorporated by reference at §§ 250.841(b), 250.842(a), and 250.1628(b) and (d);

(69) API RP 14F, Recommended Practice for Design, Installation, and Maintenance of Electrical Systems for Fixed and Floating Offshore Petroleum Facilities for Unclassified and Class 1, Division 1 and Division 2 Locations, Upstream Segment, Fifth Edition, July 2008, reaffirmed: April 2013; incorporated by reference at §§ 250.114(c), 250.842(c), 250.862(e), and 250.1629(b);

(70) API RP 14FZ, Recommended Practice for Design, Installation, and Maintenance of Electrical Systems for Fixed and Floating Offshore Petroleum Facilities for Unclassified and Class I, Zone 0, Zone 1 and Zone 2 Locations, Second Edition, May 2013; incorporated by reference at §§ 250.114(c), 250.842(c), 250.862(e), and 250.1629(b);

(71) API RP 14G, Recommended Practice for Fire Prevention and Control on Fixed Open-type Offshore Production Platforms, Fourth Edition, April 2007; Reaffirmed, January 2013; incorporated by reference at §§ 250.859(a), 250.862(e), 250.880(c), and 250.1629(b);

(72) API RP 14J, Recommended Practice for Design and Hazards Analysis for Offshore Production Facilities, Second Edition, May 2001; reaffirmed: January 2013; incorporated by reference at §§ 250.800(b) and (c), 250.842(c), and 250.901(a) and (d);

(73) API RP 17H, Remotely Operated Tools and Interfaces on Subsea Production Systems, Second Edition, June 2013; Errata, January 2014; incorporated by reference at § 250.734(a);

(74) API RP 65, Recommended Practice for Cementing Shallow Water Flow Zones in Deepwater Wells, First Edition, September 2002; incorporated by reference at § 250.415;

(75) API RP 75, Recommended Practice for Development of a Safety and Environmental Management Program for Offshore Operations and Facilities, Third Edition, May 2004, reaffirmed May 2008; incorporated by reference at §§ 250.1900, 250.1902, 250.1903, 250.1909, 250.1920;

(76) API RP 86, API Recommended Practice for Measurement of Multiphase Flow; First Edition, September 2005; incorporated by reference at §§ 250.1202(a) and 250.1203(b);

(77) API RP 90, Annular Casing Pressure Management for Offshore Wells, First Edition, August 2006; incorporated by reference at § 250.519;

(78) API RP 500, Recommended Practice for Classification of Locations for Electrical Installations at Petroleum Facilities Classified as Class I, Division 1 and Division 2, Third Edition, December 2012; Errata January 2014, incorporated by reference at §§ 250.114(a), 250.459, 250.842(a), 250.862(a) and (e), 250.872(a), 250.1628(b) and (d), and 250.1629(b);

(79) API RP 505, Recommended Practice for Classification of Locations for Electrical Installations at Petroleum Facilities Classified as Class I, Zone 0, Zone 1, and Zone 2, First Edition, November 1997; reaffirmed, August 2013; incorporated by reference at §§ 250.114(a), 250.459, 250.842(a), 250.862(a) and (e), 250.872(a), 250.1628(b) and (d), and 250.1629(b);

(80) API RP 2556, Recommended Practice for Correcting Gauge Tables for Incrustation, Second Edition, August 1993; reaffirmed November 2003; incorporated by reference at § 250.1202;

(81) API Spec. 2C, Specification for Offshore Pedestal Mounted Cranes, Sixth Edition, March 2004, Effective Date: September 2004; incorporated by reference at § 250.108;

(82) ANSI/API Spec. 6A, Specification for Wellhead and Christmas Tree Equipment, Twentieth Edition, October 2010; Addendum 1, November 2011; Errata 2, November 2011; Addendum 2, November 2012; Addendum 3, March 2013; Errata 3, June 2013; Errata 4, August 2013; Errata 5, November 2013; Errata 6, March 2014; Errata 7, December 2014; Errata 8, February 2016; Addendum 4, June 2016; Errata 9, June 2016; Errata 10, August 2016; incorporated by reference at §§ 250.730, 250.802(a), 250.803(a), 250.833, 250.873(b), 250.874(g), and 250.1002(b);

(83) API Spec. 6AV1, Specification for Verification Test of Wellhead Surface Safety Valves and Underwater Safety Valves for Offshore Service, Second Edition, February 2013; incorporated by reference at §§ 250.802(a), 250.833, 250.873(b), and 250.874(g);

(84) API STD 6AV2, Installation, Maintenance, and Repair of Surface Safety Valves and Underwater Safety Valves Offshore; First Edition, March 2014; Errata 1, August 2014; incorporated by reference at §§ 250.820, 250.834, 250.836, and 250.880(c)

(85) ANSI/API Spec. 6D, Specification for Pipeline Valves, Twenty-third Edition, April 2008; Effective Date: October 1, 2008, Errata 1, June 2008; Errata 2, November 2008; Errata 3, February 2009; Addendum 1, October 2009; Contains API Monogram Annex as Part of U.S. National Adoption; ISO 14313:2007 (Identical), Petroleum and natural gas industries - Pipeline transportation systems - Pipeline valves; incorporated by reference at § 250.1002(b);

(86) ANSI/API Spec. 11D1, Packers and Bridge Plugs, Second Edition, July 2009; incorporated by reference at §§ 250.518, 250.619, and 250.1703;

(87) ANSI/API Spec. 14A, Specification for Subsurface Safety Valve Equipment, Eleventh Edition, October 2005, reaffirmed, June 2012; incorporated by reference at §§ 250.802 and 250.803(a);

(88) ANSI/API Spec. 16A, Specification for Drill-through Equipment, Third Edition, June 2004, reaffirmed August 2010; incorporated by reference at § 250.730;

(89) ANSI/API Spec. 16C, Specification for Choke and Kill Systems, First Edition, January 1993, reaffirmed July 2010; incorporated by reference at § 250.730;

(90) API Spec. 16D, Specification for Control Systems for Drilling Well Control Equipment and Control Systems for Diverter Equipment, Second Edition, July 2004, reaffirmed August 2013; incorporated by reference at § 250.730;

(91) ANSI/API Spec. 17D, Design and Operation of Subsea Production Systems - Subsea Wellhead and Tree Equipment, Second Edition, May 2011; incorporated by reference at § 250.730;

(92) ANSI/API Spec. 17J, Specification for Unbonded Flexible Pipe, Third Edition, July 2008, incorporated by reference at §§ 250.852(e), 250.1002(b), and 250.1007(a).

(93) ANSI/API Spec. Q1, Specification for Quality Management System Requirements for Manufacturing Organizations for the Petroleum and Natural Gas Industry, Ninth Edition, June 2013; Errata, February 2014; Errata 2, March 2014; Addendum 1, June 2016; incorporated by reference at §§ 250.730 and 250.801(b) and (c);

(94) API Standard 53, Blowout Prevention Equipment Systems for Drilling Wells, Fourth Edition, November 2012, Addendum 1, July 2016, incorporated by reference at §§ 250.730, 250.734, 250.735, 250.736, 250.737, and 250.739;

(95) API Standard 65 - Part 2, Isolating Potential Flow Zones During Well Construction; Second Edition, December 2010; incorporated by reference at §§ 250.415(f) and 250.420(a);

(96) API Standard 2552, USA Standard Method for Measurement and Calibration of Spheres and Spheroids, First Edition, 1966; reaffirmed, October 2007; incorporated by reference at § 250.1202;

(97) API Standard 2555, Method for Liquid Calibration of Tanks, First Edition, September 1966; reaffirmed March 2002; incorporated by reference at § 250.1202;

(f) American Society of Mechanical Engineers (ASME), 22 Law Drive, P.O. Box 2900, Fairfield, NJ 07007-2900; http://www.asme.org; phone: 1-800-843-2763.

(1) 2017 ASME Boiler and Pressure Vessel Code (BPVC), Section I, Rules for Construction of Power Boilers, 2017 Edition, July 1, 2017, incorporated by reference at §§ 250.851(a) and 250.1629(b).

(2) 2017 ASME Boiler and Pressure Vessel Code, Section IV, Rules for Construction of Heating Boilers, 2017 Edition, July 1, 2017, incorporated by reference at §§ 250.851(a) and 250.1629(b).

(3) 2017 ASME Boiler and Pressure Vessel Code, Section VIII, Rules for Construction of Pressure Vessels; Division 1, 2017 Edition; July 1, 2017, incorporated by reference at §§ 250.851(a) and 250.1629(b).

(4) 2017 ASME Boiler and Pressure Vessel Code, Section VIII, Rules for Construction of Pressure Vessels; Division 2: Alternative Rules, 2017 Edition, July 1, 2017, incorporated by reference at §§ 250.851(a) and 250.1629(b).

(5) 2017 ASME Boiler and Pressure Vessel Code, Section VIII, Rules for Construction of Pressure Vessels; Division 3: Alternative Rules for Construction of High Pressure Vessels, 2017 Edition, July 1, 2017, incorporated by reference at §§ 250.851(a) and 250.1629(b).

(g) American Society for Testing and Materials (ASTM), ASTM Standards, 100 Bar Harbor Drive, P.O. Box C700, West Conshohocken, PA 19428-2959; http://www.astm.org; phone: 1-877-909-2786:

(1) ASTM Standard C 33-07, approved December 15, 2007, Standard Specification for Concrete Aggregates; incorporated by reference at § 250.901;

(2) ASTM Standard C 94/C 94M-07, approved January 1, 2007, Standard Specification for Ready-Mixed Concrete; incorporated by reference at § 250.901;

(3) ASTM Standard C 150-07, approved May 1, 2007, Standard Specification for Portland Cement; incorporated by reference at § 250.901;

(4) ASTM Standard C 330-05, approved December 15, 2005, Standard Specification for Lightweight Aggregates for Structural Concrete; incorporated by reference at § 250.901;

(5) ASTM Standard C 595-08, approved January 1, 2008, Standard Specification for Blended Hydraulic Cements; incorporated by reference at § 250.901;

(h) American Welding Society (AWS), AWS Codes, 8669 NW 36 Street, #130, Miami, FL 33126; http://www.aws.org;phone: 800-443-9353:

(1) AWS D1.1:2000, Structural Welding Code - Steel, 17th Edition, October 18, 1999; incorporated by reference at § 250.901;

(2) AWS D1.4-98, Structural Welding Code - Reinforcing Steel, 1998 Edition; incorporated by reference at § 250.901;

(3) AWS D3.6M:1999, Specification for Underwater Welding (1999); incorporated by reference at § 250.901.

(i) National Association of Corrosion Engineers (NACE) International, NACE Standards, Park Ten Place, Houston, TX 77084; http://www.nace.org; phone: 281-228-6200:

(1) NACE Standard MR0175-2003, Standard Material Requirements, Metals for Sulfide Stress Cracking and Stress Corrosion Cracking Resistance in Sour Oilfield Environments, Revised January 17, 2003; incorporated by reference at §§ 250.490 and 250.901;

(2) NACE Standard RP0176-2003, Standard Recommended Practice, Corrosion Control of Steel Fixed Offshore Structures Associated with Petroleum Production; incorporated by reference at § 250.901.

(j) International Organization for Standardization (ISO), 1, ch. de la Voie-Creuse, CP 56, CH-1211, Geneva 20, Switzerland; www.iso.org; phone: 41-22-749-01-11:

(1) ISO/IEC (International Electrotechnical Commission) 17011, Conformity assessment - General requirements for accreditation bodies accrediting conformity assessment bodies, First edition 2004-09-01; Corrected version 2005-02-15; incorporated by reference at §§ 250.1900, 250.1903, 250.1904, and 250.1922.

(2) ISO/IEC 17021-1, Conformity assessment - Requirements for bodies providing audit and certification of management systems - Part 1: Requirements, First Edition, June 2015, incorporated by reference at § 250.730(d).

(3) [Reserved]

(k) Center for Offshore Safety (COS), 1990 Post Oak Blvd., Suite 1370, Houston, TX 77056; www.centerforoffshoresafety.org; phone: 832-495-4925.

(1) COS Safety Publication COS-2-01, Qualification and Competence Requirements for Audit Teams and Auditors Performing Third-party SEMS Audits of Deepwater Operations, First Edition, Effective Date October 2012; incorporated by reference at §§ 250.1900, 250.1903, 250.1904, and 250.1921.

(2) COS Safety Publication COS-2-03, Requirements for Third-party SEMS Auditing and Certification of Deepwater Operations, First Edition, Effective Date October 2012; incorporated by reference at §§ 250.1900, 250.1903, 250.1904, and 250.1920.

(3) COS Safety Publication COS-2-04, Requirements for Accreditation of Audit Service Providers Performing SEMS Audits and Certification of Deepwater Operations, First Edition, Effective Date October 2012; incorporated by reference at §§ 250.1900, 250.1903, 250.1904, and 250.1922.

[84 FR 21969, May 15, 2019, as amended at 85 FR 84236, Dec. 30, 2020]

§ 250.199 Paperwork Reduction Act statements - information collection.

(a) OMB has approved the information collection requirements in part 250 under 44 U.S.C. 3501 et seq. The table in paragraph (e) of this section lists the subpart in the rule requiring the information and its title, provides the OMB control number, and summarizes the reasons for collecting the information and how BSEE uses the information. The associated BSEE forms required by this part are listed at the end of this table with the relevant information.

(b) Respondents are OCS oil, gas, and sulphur lessees and operators. The requirement to respond to the information collections in this part is mandated under the Act (43 U.S.C. 1331 et seq.) and the Act's Amendments of 1978 (43 U.S.C. 1801 et seq.). Some responses are also required to obtain or retain a benefit or may be voluntary. Proprietary information will be protected under § 250.197, Data and information to be made available to the public or for limited inspection; parts 30 CFR Parts 251, 252; and the Freedom of Information Act (5 U.S.C. 552) and its implementing regulations at 43 CFR part 2.

(c) The Paperwork Reduction Act of 1995 requires us to inform the public that an agency may not conduct or sponsor, and you are not required to respond to, a collection of information unless it displays a currently valid OMB control number.

(d) Send comments regarding any aspect of the collections of information under this part, including suggestions for reducing the burden, to the Information Collection Clearance Officer, Bureau of Safety and Environmental Enforcement, 45600 Woodland Road, Sterling, VA 20166.

(e) BSEE is collecting this information for the reasons given in the following table:

30 CFR Subpart, title and/or BSEE Form (OMB Control No.) BSEE collects this information and uses it to:
(1) Subpart A, General (1014-0022), including Forms BSEE-0011, iSEE; BSEE-0132, Evacuation Statistics; BSEE-0143, Facility/Equipment Damage Report; BSEE-1832, Notification of Incidents of Noncompliance (i) Determine that activities on the OCS comply with statutory and regulatory requirements; are safe and protect the environment; and result in diligent development and production on OCS leases.
(ii) Support the unproved and proved reserve estimation, resource assessment, and fair market value determinations.
(iii) Assess damage and project any disruption of oil and gas production from the OCS after a major natural occurrence.
(2) Subpart B, Plans and Information (1014-0024) Evaluate Deepwater Operations Plans for compliance with statutory and regulatory requirements
(3) Subpart C, Pollution Prevention and Control (1014-0023) (i) Evaluate measures to prevent unauthorized discharge of pollutants into the offshore waters.
(ii) Ensure action is taken to control pollution.
(4) Subpart D, Oil and Gas and Drilling Operations (1014-0018), including Forms BSEE-0125, End of Operations Report; BSEE-0133, Well Activity Report; and BSEE-0133S, Open Hole Data Report (i) Evaluate the equipment and procedures to be used in drilling operations on the OCS.
(ii) Ensure that drilling operations meet statutory and regulatory requirements.
(5) Subpart E, Oil and Gas Well-Completion Operations (1014-0004) (i) Evaluate the equipment and procedures to be used in well-completion operations on the OCS.
(ii) Ensure that well-completion operations meet statutory and regulatory requirements.
(6) Subpart F, Oil and Gas Well Workover Operations (1014-0001) (i) Evaluate the equipment and procedures to be used during well-workover operations on the OCS.
(ii) Ensure that well-workover operations meet statutory and regulatory requirements.
(7) Subpart G, Blowout Preventer Systems (1014-0028), including Form BSEE-0144, Rig Movement Notification Report (i) Evaluate the equipment and procedures to be used during well drilling, completion, workover, and abandonment operations on the OCS.
(ii) Ensure that well operations meet statutory and regulatory requirements.
(8) Subpart H, Oil and Gas Production Safety Systems (1014-0003) (i) Evaluate the equipment and procedures that will be used during production operations on the OCS.
(ii) Ensure that production operations meet statutory and regulatory requirements.
(9) Subpart I, Platforms and Structures (1014-0011) (i) Evaluate the design, fabrication, and installation of platforms on the OCS.
(ii) Ensure the structural integrity of platforms installed on the OCS.
(10) Subpart J, Pipelines and Pipeline Rights-of-Way (1014-0016), including Form BSEE-0149, Assignment of Federal OCS Pipeline Right-of-Way Grant (i) Evaluate the design, installation, and operation of pipelines on the OCS.
(ii) Ensure that pipeline operations meet statutory and regulatory requirements.
(11) Subpart K, Oil and Gas Production Rates (1014-0019), including Forms BSEE-0126, Well Potential Test Report and BSEE-0128, Semiannual Well Test Report (i) Evaluate production rates for hydrocarbons produced on the OCS.
(ii) Ensure economic maximization of ultimate hydrocarbon recovery.
(12) Subpart L, Oil and Gas Production Measurement, Surface Commingling, and Security (1014-0002) (i) Evaluate the measurement of production, commingling of hydrocarbons, and site security plans.
(ii) Ensure that produced hydrocarbons are measured and commingled to provide for accurate royalty payments and security.
(13) Subpart M, Unitization (1014-0015) (i) Evaluate the unitization of leases.
(ii) Ensure that unitization prevents waste, conserves natural resources, and protects correlative rights.
(14) Subpart N, Remedies and Penalties (The requirements in subpart N are exempt from the Paperwork Reduction Act of 1995 according to 5 CFR 1320.4).
(15) Subpart O, Well Control and Production Safety Training (1014-0008) (i) Evaluate training program curricula for OCS workers, course schedules, and attendance.
(ii) Ensure that training programs are technically accurate and sufficient to meet statutory and regulatory requirements, and that workers are properly trained.
(16) Subpart P, Sulfur Operations (1014-0006) (i) Evaluate sulfur exploration and development operations on the OCS.
(ii) Ensure that OCS sulfur operations meet statutory and regulatory requirements and will result in diligent development and production of sulfur leases.
(17) Subpart Q, Decommissioning Activities (1014-0010) Ensure that decommissioning activities, site clearance, and platform or pipeline removal are properly performed to meet statutory and regulatory requirements and do not conflict with other users of the OCS.
(18) Subpart S, Safety and Environmental Management Systems (1014-0017), including Form BSEE-0131, Performance Measures Data (i) Evaluate operators' policies and procedures to assure safety and environmental protection while conducting OCS operations (including those operations conducted by contractor and subcontractor personnel).
(ii) Evaluate Performance Measures Data relating to risk and number of accidents, injuries, and oil spills during OCS activities.
(19) Application for Permit to Drill (APD, Revised APD), Form BSEE-0123; and Supplemental APD Information Sheet, Form BSEE-0123S, and all supporting documentation (1014-0025) (i) Evaluate and approve the adequacy of the equipment, materials, and/or procedures that the lessee or operator plans to use during drilling.
(ii) Ensure that applicable OCS operations meet statutory and regulatory requirements.
(20) Application for Permit to Modify (APM), Form BSEE-0124, and supporting documentation (1014-0026) (i) Evaluate and approve the adequacy of the equipment, materials, and/or procedures that the lessee or operator plans to use during drilling and to evaluate well plan modifications and changes in major equipment.
(ii) Ensure that applicable OCS operations meet statutory and regulatory requirements.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 26015, Apr. 29, 2016; 81 FR 36149, June 6, 2016]

Subpart B - Plans and Information
General Information
§ 250.200 Definitions.

Acronyms and terms used in this subpart have the following meanings:

(a) Acronyms used frequently in this subpart are listed alphabetically below:

BOEM means Bureau of Ocean Energy Management of the Department of the Interior.

BSEE means Bureau of Safety and Environmental Enforcement of the Department of the Interior.

CID means Conservation Information Document.

CZMA means Coastal Zone Management Act.

DOCD means Development Operations Coordination Document.

DPP means Development and Production Plan.

DWOP means Deepwater Operations Plan.

EIA means Environmental Impact Analysis.

EP means Exploration Plan.

NPDES means National Pollutant Discharge Elimination System.

NTL means Notice to Lessees and Operators.

OCS means Outer Continental Shelf.

(b) Terms used in this subpart are listed alphabetically below:

Amendment means a change you make to an EP, DPP, or DOCD that is pending before BOEM for a decision (see 30 CFR 550.232(d) and 550.267(d)).

Modification means a change required by the Regional Supervisor to an EP, DPP, or DOCD (see 30 CFR 550.233(b)(2) and 550.270(b)(2)) that is pending before BOEM for a decision because the OCS plan is inconsistent with applicable requirements.

New or unusual technology means equipment or procedures that:

(1) Have not been used previously or extensively in a BSEE OCS Region;

(2) Have not been used previously under the anticipated operating conditions; or

(3) Have operating characteristics that are outside the performance parameters established by this part.

Non-conventional production or completion technology includes, but is not limited to, floating production systems, tension leg platforms, spars, floating production, storage, and offloading systems, guyed towers, compliant towers, subsea manifolds, and other subsea production components that rely on a remote site or host facility for utility and well control services.

Offshore vehicle means a vehicle that is capable of being driven on ice.

Resubmitted OCS plan means an EP, DPP, or DOCD that contains changes you make to an OCS plan that BOEM has disapproved (see 30 CFR 550.234(b), 550.272(a), and 550.273(b)).

Revised OCS plan means an EP, DPP, or DOCD that proposes changes to an approved OCS plan, such as those in the location of a well or platform, type of drilling unit, or location of the onshore support base (see 30 CFR 550.283(a)).

Supplemental OCS plan means an EP, DPP, or DOCD that proposes the addition to an approved OCS plan of an activity that requires approval of an application or permit (see 30 CFR 550.283(b)).

§ 250.201 What plans and information must I submit before I conduct any activities on my lease or unit?

(a) Plans and documents. Before you conduct the activities on your lease or unit listed in the following table, you must submit, and BSEE must approve, the listed plans and documents. Your plans and documents may cover one or more leases or units.

You must submit a(n) . . . Before you . . .
(1) [Reserved]
(2) [Reserved]
(3) [Reserved]
(4) Deepwater Operations Plan (DWOP), Conduct post-drilling installation activities in any water depth associated with a development project that will involve the use of a non-conventional production or completion technology.
(5) [Reserved]
(6) [Reserved]

(b) Submitting additional information. On a case-by-case basis, the Regional Supervisor may require you to submit additional information if the Regional Supervisor determines that it is necessary to evaluate your proposed plan or document.

(c) Limiting information. The Regional Director may limit the amount of information or analyses that you otherwise must provide in your proposed plan or document under this subpart when:

(1) Sufficient applicable information or analysis is readily available to BSEE;

(2) Other coastal or marine resources are not present or affected;

(3) Other factors such as technological advances affect information needs; or

(4) Information is not necessary or required for a State to determine consistency with their CZMA Plan.

(d) Referencing. In preparing your proposed plan or document, you may reference information and data discussed in other plans or documents you previously submitted or that are otherwise readily available to BSEE.

§§ 250.202-250.203 [Reserved]
§ 250.204 How must I protect the rights of the Federal government?

(a) To protect the rights of the Federal government, you must either:

(1) Drill and produce the wells that the Regional Supervisor determines are necessary to protect the Federal government from loss due to production on other leases or units or from adjacent lands under the jurisdiction of other entities (e.g., State and foreign governments); or

(2) Pay a sum that the Regional Supervisor determines as adequate to compensate the Federal government for your failure to drill and produce any well.

(b) Payment under paragraph (a)(2) of this section may constitute production in paying quantities for the purpose of extending the lease term.

(c) You must complete and produce any penetrated hydrocarbon-bearing zone that the Regional Supervisor determines is necessary to conform to sound conservation practices.

§ 250.205 Are there special requirements if my well affects an adjacent property?

For wells that could intersect or drain an adjacent property, the Regional Supervisor may require special measures to protect the rights of the Federal government and objecting lessees or operators of adjacent leases or units.

Post-Approval Requirements for the EP, DPP, and DOCD
§ 250.282 Do I have to conduct post-approval monitoring?

The Regional Supervisor may direct you to conduct monitoring programs. You must retain copies of all monitoring data obtained or derived from your monitoring programs and make them available to BSEE upon request. The Regional Supervisor may require you to:

(a) Monitoring plans. Submit monitoring plans for approval before you begin work; and

(b) Monitoring reports. Prepare and submit reports that summarize and analyze data and information obtained or derived from your monitoring programs. The Regional Supervisor will specify requirements for preparing and submitting these reports.

Deepwater Operations Plan (DWOP)
§ 250.286 What is a DWOP?

(a) A DWOP is a plan that provides sufficient information for BSEE to review a deepwater development project, and any other project that uses non-conventional production or completion technology, from a total system approach. The DWOP does not replace, but supplements other submittals required by the regulations such as BOEM Exploration Plans, Development and Production Plans, and Development Operations Coordination Documents. BSEE will use the information in your DWOP to determine whether the project will be developed in an acceptable manner, particularly with respect to operational safety and environmental protection issues involved with non-conventional production or completion technology.

(b) The DWOP process consists of two parts: a Conceptual Plan and the DWOP. Section 250.289 prescribes what the Conceptual Plan must contain, and § 250.292 prescribes what the DWOP must contain.

§ 250.287 For what development projects must I submit a DWOP?

You must submit a DWOP for each development project in which you will use non-conventional production or completion technology, regardless of water depth. If you are unsure whether BSEE considers the technology of your project non-conventional, you must contact the Regional Supervisor for guidance.

§ 250.288 When and how must I submit the Conceptual Plan?

You must submit four copies, or one hard copy and one electronic version, of the Conceptual Plan to the Regional Director after you have decided on the general concept(s) for development and before you begin engineering design of the well safety control system or subsea production systems to be used after well completion.

§ 250.289 What must the Conceptual Plan contain?

In the Conceptual Plan, you must explain the general design basis and philosophy that you will use to develop the field. You must include the following information:

(a) An overview of the development concept(s);

(b) A well location plat;

(c) The system control type (i.e., direct hydraulic or electro-hydraulic); and

(d) The distance from each of the wells to the host platform.

§ 250.290 What operations require approval of the Conceptual Plan?

You may not complete any production well or install the subsea wellhead and well safety control system (often called the tree) before BSEE has approved the Conceptual Plan.

§ 250.291 When and how must I submit the DWOP?

You must submit four copies, or one hard copy and one electronic version, of the DWOP to the Regional Director after you have substantially completed safety system design and before you begin to procure or fabricate the safety and operational systems (other than the tree), production platforms, pipelines, or other parts of the production system.

§ 250.292 What must the DWOP contain?

You must include the following information in your DWOP:

(a) A description and schematic of the typical wellbore, casing, and completion;

(b) Structural design, fabrication, and installation information for each surface system, including host facilities;

(c) Design, fabrication, and installation information on the mooring systems for each surface system;

(d) Information on any active stationkeeping system(s) involving thrusters or other means of propulsion used with a surface system;

(e) Information concerning the drilling and completion systems;

(f) Design and fabrication information for each riser system (e.g., drilling, workover, production, and injection);

(g) Pipeline information;

(h) Information about the design, fabrication, and operation of an offtake system for transferring produced hydrocarbons to a transport vessel;

(i) Information about subsea wells and associated systems that constitute all or part of a single project development covered by the DWOP;

(j) Flow schematics and Safety Analysis Function Evaluation (SAFE) charts (API RP 14C, subsection 4.3c, incorporated by reference in § 250.198) of the production system from the Surface Controlled Subsurface Safety Valve (SCSSV) downstream to the first item of separation equipment;

(k) A description of the surface/subsea safety system and emergency support systems to include a table that depicts what valves will close, at what times, and for what events or reasons;

(l) A general description of the operating procedures, including a table summarizing the curtailment of production and offloading based on operational considerations;

(m) A description of the facility installation and commissioning procedure;

(n) A discussion of any new technology that affects hydrocarbon recovery systems;

(o) A list of any alternate compliance procedures or departures for which you anticipate requesting approval;

(p) If you propose to use a pipeline free standing hybrid riser (FSHR) on a permanent installation that utilizes a buoyancy air can suspended from the top of the riser, you must provide the following information in your DWOP in the discussions required by paragraphs (f) and (g) of this section:

(1) A detailed description and drawings of the FSHR, buoy, and the associated connection system;

(2) Detailed information regarding the system used to connect the FSHR to the buoyancy air can, and associated redundancies; and

(3) Descriptions of your monitoring system and monitoring plan to monitor the pipeline FSHR and the associated connection system for fatigue, stress, and any other abnormal condition (e.g., corrosion) that may negatively impact the riser system's integrity.

(q) Payment of the service fee listed in § 250.125.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 26017, Apr. 29, 2016; 84 FR 21973, May 15, 2019]

§ 250.293 What operations require approval of the DWOP?

You may not begin production until BSEE approves your DWOP.

§ 250.294 May I combine the Conceptual Plan and the DWOP?

If your development project meets the following criteria, you may submit a combined Conceptual Plan/DWOP on or before the deadline for submitting the Conceptual Plan.

(a) The project is located in water depths of less than 400 meters (1,312 feet); and

(b) The project is similar to projects involving non-conventional production or completion technology for which you have obtained approval previously.

§ 250.295 When must I revise my DWOP?

You must revise either the Conceptual Plan or your DWOP to reflect changes in your development project that materially alter the facilities, equipment, and systems described in your plan. You must submit the revision within 60 days after any material change to the information required for that part of your plan.

Subpart C - Pollution Prevention and Control
§ 250.300 Pollution prevention.

(a) During the exploration, development, production, and transportation of oil and gas or sulphur, the lessee shall take measures to prevent unauthorized discharge of pollutants into the offshore waters. The lessee shall not create conditions that will pose unreasonable risk to public health, life, property, aquatic life, wildlife, recreation, navigation, commercial fishing, or other uses of the ocean.

(1) When pollution occurs as a result of operations conducted by or on behalf of the lessee and the pollution damages or threatens to damage life (including fish and other aquatic life), property, any mineral deposits (in areas leased or not leased), or the marine, coastal, or human environment, the control and removal of the pollution to the satisfaction of the District Manager shall be at the expense of the lessee. Immediate corrective action shall be taken in all cases where pollution has occurred. Corrective action shall be subject to modification when directed by the District Manager.

(2) If the lessee fails to control and remove the pollution, the Director, in cooperation with other appropriate Agencies of Federal, State, and local governments, or in cooperation with the lessee, or both, shall have the right to control and remove the pollution at the lessee's expense. Such action shall not relieve the lessee of any responsibility provided for by law.

(b)

(1) The District Manager may restrict the rate of drilling fluid discharges or prescribe alternative discharge methods. The District Manager may also restrict the use of components that could cause unreasonable degradation to the marine environment. No petroleum-based substances, including diesel fuel, may be added to the drilling mud system without prior approval of the District Manager. For Arctic OCS exploratory drilling, you must capture all petroleum-based mud to prevent its discharge into the marine environment. The Regional Supervisor may also require you to capture, during your Arctic OCS exploratory drilling operations, all water-based mud from operations after completion of the hole for the conductor casing to prevent its discharge into the marine environment, based on various factors including, but not limited to:

(i) The proximity of your exploratory drilling operation to subsistence hunting and fishing locations;

(ii) The extent to which discharged mud may cause marine mammals to alter their migratory patterns in a manner that impedes subsistence users' access to, or use of, those resources, or increases the risk of injury to subsistence users; or

(iii) The extent to which discharged mud may adversely affect marine mammals, fish, or their habitat.

(2) You must obtain approval from the District Manager of the method you plan to use to dispose of drill cuttings, sand, and other well solids. For Arctic OCS exploratory drilling, you must capture all cuttings from operations that utilize petroleum-based mud to prevent their discharge into the marine environment. The Regional Supervisor may also require you to capture, during your Arctic OCS exploratory drilling operations, all cuttings from operations that utilize water-based mud after completion of the hole for the conductor casing to prevent their discharge into the marine environment, based on various factors including, but not limited to:

(i) The proximity of your exploratory drilling operation to subsistence hunting and fishing locations;

(ii) The extent to which discharged cuttings may cause marine mammals to alter their migratory patterns in a manner that impedes subsistence users' access to, or use of, those resources, or increases the risk of injury to subsistence users; or

(iii) The extent to which discharged cuttings may adversely affect marine mammals, fish, or their habitat.

(3) All hydrocarbon-handling equipment for testing and production such as separators, tanks, and treaters shall be designed, installed, and operated to prevent pollution. Maintenance or repairs which are necessary to prevent pollution of offshore waters shall be undertaken immediately.

(4) Curbs, gutters, drip pans, and drains shall be installed in deck areas in a manner necessary to collect all contaminants not authorized for discharge. Oil drainage shall be piped to a properly designed, operated, and maintained sump system which will automatically maintain the oil at a level sufficient to prevent discharge of oil into offshore waters. All gravity drains shall be equipped with a water trap or other means to prevent gas in the sump system from escaping through the drains. Sump piles shall not be used as processing devices to treat or skim liquids but may be used to collect treated-produced water, treated-produced sand, or liquids from drip pans and deck drains and as a final trap for hydrocarbon liquids in the event of equipment upsets. Improperly designed, operated, or maintained sump piles which do not prevent the discharge of oil into offshore waters shall be replaced or repaired.

(5) On artificial islands, all vessels containing hydrocarbons shall be placed inside an impervious berm or otherwise protected to contain spills. Drainage shall be directed away from the drilling rig to a sump. Drains and sumps shall be constructed to prevent seepage.

(6) Disposal of equipment, cables, chains, containers, or other materials into offshore waters is prohibited.

(c) Materials, equipment, tools, containers, and other items used in the Outer Continental Shelf (OCS) which are of such shape or configuration that they are likely to snag or damage fishing devices shall be handled and marked as follows:

(1) All loose material, small tools, and other small objects shall be kept in a suitable storage area or a marked container when not in use and in a marked container before transport over offshore waters;

(2) All cable, chain, or wire segments shall be recovered after use and securely stored until suitable disposal is accomplished;

(3) Skid-mounted equipment, portable containers, spools or reels, and drums shall be marked with the owner's name prior to use or transport over offshore waters; and

(4) All markings must clearly identify the owner and must be durable enough to resist the effects of the environmental conditions to which they may be exposed.

(d) Any of the items described in paragraph (c) of this section that are lost overboard shall be recorded on the facility's daily operations report, as appropriate, and reported to the District Manager.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 46560, July 15, 2016]

§ 250.301 Inspection of facilities.

Drilling and production facilities shall be inspected daily or at intervals approved or prescribed by the District Manager to determine if pollution is occurring. Necessary maintenance or repairs shall be made immediately. Records of such inspections and repairs shall be maintained at the facility or at a nearby manned facility for 2 years.

Subpart D - Oil and Gas Drilling Operations
General Requirements
§ 250.400 General requirements.

Drilling operations must be conducted in a safe manner to protect against harm or damage to life (including fish and other aquatic life), property, natural resources of the Outer Continental Shelf (OCS), including any mineral deposits (in areas leased and not leased), the National security or defense, or the marine, coastal, or human environment. In addition to the requirements of this subpart, you must also follow the applicable requirements of subpart G of this part.

[81 FR 26017, Apr. 29, 2016]

§§ 250.401-250.403 [Reserved]
§ 250.404 What are the requirements for the crown block?

You must have a crown block safety device that prevents the traveling block from striking the crown block. You must check the device for proper operation at least once per week and after each drill-line slipping operation and record the results of this operational check in the driller's report.

§ 250.405 What are the safety requirements for diesel engines used on a drilling rig?

You must equip each diesel engine with an air intake device to shut down the diesel engine in the event of a runaway.

(a) For a diesel engine that is not continuously manned, you must equip the engine with an automatic shutdown device;

(b) For a diesel engine that is continuously manned, you may equip the engine with either an automatic or remote manual air intake shutdown device;

(c) You do not have to equip a diesel engine with an air intake device if it meets one of the following criteria:

(1) Starts a larger engine;

(2) Powers a firewater pump;

(3) Powers an emergency generator;

(4) Powers a BOP accumulator system;

(5) Provides air supply to divers or confined entry personnel;

(6) Powers temporary equipment on a nonproducing platform;

(7) Powers an escape capsule; or

(8) Powers a portable single-cylinder rig washer.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 36149, June 6, 2016]

§ 250.406 [Reserved]
§ 250.407 What tests must I conduct to determine reservoir characteristics?

You must determine the presence, quantity, quality, and reservoir characteristics of oil, gas, sulphur, and water in the formations penetrated by logging, formation sampling, or well testing.

§ 250.408 May I use alternative procedures or equipment during drilling operations?

You may use alternative procedures or equipment during drilling operations after receiving approval from the District Manager. You must identify and discuss your proposed alternative procedures or equipment in your Application for Permit to Drill (APD) (Form BSEE-0123) (see § 250.414(h)). Procedures for obtaining approval are described in § 250.141 of this part.

§ 250.409 May I obtain departures from these drilling requirements?

The District Manager may approve departures from the drilling requirements specified in this subpart. You may apply for a departure from drilling requirements by writing to the District Manager. You should identify and discuss the departure you are requesting in your APD (see § 250.414(h)).

Applying for a Permit To Drill
§ 250.410 How do I obtain approval to drill a well?

You must obtain written approval from the District Manager before you begin drilling any well or before you sidetrack, bypass, or deepen a well. To obtain approval, you must:

(a) Submit the information required by §§ 250.411 through 250.418;

(b) Include the well in your approved Exploration Plan (EP), Development and Production Plan (DPP), or Development Operations Coordination Document (DOCD);

(c) Meet the oil spill financial responsibility requirements for offshore facilities as required by 30 CFR part 553; and

(d) Submit the following to the District Manager:

(1) An original and two complete copies of Form BSEE-0123, Application for Permit to Drill (APD), and Form BSEE-0123S, Supplemental APD Information Sheet;

(2) A separate public information copy of forms BSEE-0123 and BSEE-0123S that meets the requirements of § 250.186; and

(3) Payment of the service fee listed in § 250.125.

§ 250.411 What information must I submit with my application?

In addition to forms BSEE-0123 and BSEE-0123S, you must include the information required in this subpart and subpart G of this part, including the following:

Information that you must include with an APD Where to find a description
(a) Plat that shows locations of the proposed well, § 250.412.
(b) Design criteria used for the proposed well, § 250.413.
(c) Drilling prognosis, § 250.414.
(d) Casing and cementing programs, § 250.415.
(e) Diverter systems descriptions, § 250.416.
(f) BOP system descriptions, § 250.731.
(g) Requirements for using a MODU, and § 250.713.
(h) Additional information. § 250.418.

[81 FR 26017, Apr. 29, 2016]

§ 250.412 What requirements must the location plat meet?

The location plat must:

(a) Have a scale of 1:24,000 (1 inch = 2,000 feet);

(b) Show the surface and subsurface locations of the proposed well and all the wells in the vicinity;

(c) Show the surface and subsurface locations of the proposed well in feet or meters from the block line;

(d) Contain the longitude and latitude coordinates, and either Universal Transverse Mercator grid-system coordinates or state plane coordinates in the Lambert or Transverse Mercator Projection system for the surface and subsurface locations of the proposed well; and

(e) State the units and geodetic datum (including whether the datum is North American Datum 27 or 83) for these coordinates. If the datum was converted, you must state the method used for this conversion, since the various methods may produce different values.

§ 250.413 What must my description of well drilling design criteria address?

Your description of well drilling design criteria must address:

(a) Pore pressures;

(b) Formation fracture gradients, adjusted for water depth;

(c) Potential lost circulation zones;

(d) Drilling fluid weights;

(e) Casing setting depths;

(f) Maximum anticipated surface pressures. For this section, maximum anticipated surface pressures are the pressures that you reasonably expect to be exerted upon a casing string and its related wellhead equipment. In calculating maximum anticipated surface pressures, you must consider: drilling, completion, and producing conditions; drilling fluid densities to be used below various casing strings; fracture gradients of the exposed formations; casing setting depths; total well depth; formation fluid types; safety margins; and other pertinent conditions. You must include the calculations used to determine the pressures for the drilling and the completion phases, including the anticipated surface pressure used for designing the production string;

(g) A single plot containing curves for estimated pore pressures, formation fracture gradients, proposed drilling fluid weights (surface and downhole), planned safe drilling margin, and casing setting depths in true vertical measurements;

(h) A summary report of the shallow hazards site survey that describes the geological and manmade conditions if not previously submitted; and

(i) Permafrost zones, if applicable.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 26017, Apr. 29, 2016; 84 FR 21973, May 15, 2019]

§ 250.414 What must my drilling prognosis include?

Your drilling prognosis must include a brief description of the procedures you will follow in drilling the well. This prognosis includes but is not limited to the following:

(a) Projected plans for coring at specified depths;

(b) Projected plans for logging;

(c) Planned safe drilling margin that is between the estimated pore pressure and the lesser of estimated fracture gradients or casing shoe pressure integrity test and that is based on a risk assessment consistent with expected well conditions and operations.

(1) Your safe drilling margin must also include use of equivalent downhole mud weight that is:

(i) Greater than the estimated pore pressure; and

(ii) Except as provided in paragraph (c)(2) of this section, a minimum of 0.5 pound per gallon below the lower of the casing shoe pressure integrity test or the lowest estimated fracture gradient.

(2) In lieu of meeting the criteria in paragraph (c)(1)(ii) of this section, you may use an equivalent downhole mud weight as specified in your APD, provided that you submit adequate documentation (such as risk modeling data, off-set well data, analog data, seismic data) to justify the alternative equivalent downhole mud weight. You may submit such justification in advance of your full APD, and BSEE may consider such justification for approval when submitted. Any such approval will be contingent upon your confirmation in the APD that your plans and the information underlying your approved justification have not changed.

(3) When determining the pore pressure and lowest estimated fracture gradient for a specific interval, you must consider related off-set and analogous well behavior observations, if available.

(d) Estimated depths to the top of significant marker formations;

(e) Estimated depths to significant porous and permeable zones containing fresh water, oil, gas, or abnormally pressured formation fluids;

(f) Estimated depths to major faults;

(g) Estimated depths of permafrost, if applicable;

(h) A list and description of all requests for using alternate procedures or departures from the requirements of this subpart in one place in the APD. You must explain how the alternate procedures afford an equal or greater degree of protection, safety, or performance, or why the departures are requested;

(i) Projected plans for well testing (refer to § 250.460);

(j) The type of wellhead system and liner hanger system to be installed and a descriptive schematic, which includes but is not limited to pressure ratings, dimensions, valves, load shoulders, and locking mechanisms, if applicable; and

(k) Any additional information required by the District Manager needed to clarify or evaluate your drilling prognosis.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 26017, Apr. 29, 2016; 84 FR 21973, May 15, 2019]

§ 250.415 What must my casing and cementing programs include?

Your casing and cementing programs must include:

(a) The following well design information:

(1) Hole sizes;

(2) Bit depths (including measured and true vertical depth (TVD));

(3) Casing information, including sizes, weights, grades, collapse and burst values, types of connection, and setting depths (measured and TVD) for all sections of each casing interval; and

(4) Locations of any installed rupture disks (indicate if burst or collapse and rating);

(b) Casing design safety factors for tension, collapse, and burst with the assumptions made to arrive at these values;

(c) Type and amount of cement (in cubic feet) planned for each casing string;

(d) In areas containing permafrost, setting depths for conductor and surface casing based on the anticipated depth of the permafrost. Your program must provide protection from thaw subsidence and freezeback effect, proper anchorage, and well control;

(e) A statement of how you evaluated the best practices included in API RP 65, Recommended Practice for Cementing Shallow Water Flow Zones in Deep Water Wells (as incorporated by reference in § 250.198), if you drill a well in water depths greater than 500 feet and are in either of the following two areas:

(1) An “area with an unknown shallow water flow potential” is a zone or geologic formation where neither the presence nor absence of potential for a shallow water flow has been confirmed.

(2) An “area known to contain a shallow water flow hazard” is a zone or geologic formation for which drilling has confirmed the presence of shallow water flow; and

(f) A written description of how you evaluated the best practices included in API Standard 65 - Part 2, Isolating Potential Flow Zones During Well Construction, Second Edition (as incorporated by reference in § 250.198). Your written description must identify the mechanical barriers and cementing practices you will use for each casing string (reference API Standard 65 - Part 2, Sections 4 and 5).

[76 FR 64462, Oct. 18, 2011, as amended at 77 FR 50891, Aug. 22, 2012; 81 FR 26018, Apr. 29, 2016]

§ 250.416 What must I include in the diverter description?

You must include in the diverter description:

(a) A description of the diverter system and its operating procedures;

(b) A schematic drawing of the diverter system (plan and elevation views) that shows:

(1) The size of the element installed in the diverter housing;

(2) Spool outlet internal diameter(s);

(3) Diverter-line lengths and diameters; burst strengths and radius of curvature at each turn; and

(4) Valve type, size, working pressure rating, and location.

[81 FR 26018, Apr. 29, 2016]

§ 250.417 [Reserved]
§ 250.418 What additional information must I submit with my APD?

You must include the following with the APD:

(a) Rated capacities of the drilling rig and major drilling equipment, if not already on file with the appropriate District office;

(b) A drilling fluids program that includes the minimum quantities of drilling fluids and drilling fluid materials, including weight materials, to be kept at the site;

(c) A proposed directional plot if the well is to be directionally drilled;

(d) A Hydrogen Sulfide Contingency Plan (see § 250.490), if applicable, and not previously submitted;

(e) A welding plan (see §§ 250.109 to 250.113) if not previously submitted;

(f) In areas subject to subfreezing conditions, evidence that the drilling equipment, BOP systems and components, diverter systems, and other associated equipment and materials are suitable for operating under such conditions;

(g) A request for approval, if you plan to wash out or displace cement to facilitate casing removal upon well abandonment. Your request must include a description of how far below the mudline you propose to displace cement and how you will visually monitor returns;

(h) Certification of your casing and cementing program as required in § 250.420(a)(7); and

(i) Such other information as the District Manager may require.

(j) For Arctic OCS exploratory drilling operations, you must provide the information required by § 250.470.

[76 FR 64462, Oct. 18, 2011, as amended at 77 FR 50892, Aug. 22, 2012; 81 FR 26018, Apr. 29, 2016; 81 FR 46561, July 15, 2016]

Casing and Cementing Requirements
§ 250.420 What well casing and cementing requirements must I meet?

You must case and cement all wells. Your casing and cementing programs must meet the applicable requirements of this subpart and of subpart G of this part.

(a) Casing and cementing program requirements. Your casing and cementing programs must:

(1) Properly control formation pressures and fluids;

(2) Prevent the direct or indirect release of fluids from any stratum through the wellbore into offshore waters;

(3) Prevent communication between separate hydrocarbon-bearing strata;

(4) Protect freshwater aquifers from contamination;

(5) Support unconsolidated sediments;

(6) Provide adequate centralization consistent with the guidelines of API Standard 65 - Part 2 (as incorporated by reference in § 250.198); and

(7)

(i) Include a certification signed by a registered professional engineer that the casing and cementing design is appropriate for the purpose for which it is intended under expected wellbore conditions, and is sufficient to satisfy the tests and requirements of this section and § 250.423. Submit this certification with your APD (Form BSEE-0123).

(ii) You must have the registered professional engineer involved in the casing and cementing design process.

(iii) The registered professional engineer must be registered in a state of the United States and have sufficient expertise and experience to perform the certification.

(b) Casing requirements.

(1) You must design casing (including liners) to withstand the anticipated stresses imposed by tensile, compressive, and buckling loads; burst and collapse pressures; thermal effects; and combinations thereof.

(2) The casing design must include safety measures that ensure well control during drilling and safe operations during the life of the well.

(3) On all wells that use subsea BOP stacks, you must include two independent barriers, including one mechanical barrier, in each annular flow path (examples of barriers include, but are not limited to, primary cement job and seal assembly). For the final casing string (or liner if it is your final string), you must install one mechanical barrier in addition to cement to prevent flow in the event of a failure in the cement. A dual float valve, by itself, is not considered a mechanical barrier. These barriers cannot be modified prior to or during completion or abandonment operations. The BSEE District Manager may approve alternative options under § 250.141. You must submit documentation of this installation to BSEE in the End-of-Operations Report (Form BSEE-0125).

(4) If you need to substitute a different size, grade, or weight of casing than what was approved in your APD, you must contact the District Manager for approval prior to installing the casing.

(c) Cementing requirements .

(1) You must design and conduct your cementing jobs so that cement composition, placement techniques, and waiting times ensure that the cement placed behind the bottom 500 feet of casing attains a minimum compressive strength of 500 psi before drilling out the casing or before commencing completion operations. (If a liner is used refer to § 250.421(f)).

(2) You must use a weighted fluid during displacement to maintain an overbalanced hydrostatic pressure during the cement setting time, except when cementing casings or liners in riserless hole sections.

[76 FR 64462, Oct. 18, 2011, as amended at 77 FR 50892, Aug. 22, 2012; 81 FR 26018, Apr. 29, 2016; 84 FR 21973, May 15, 2019]

§ 250.421 What are the casing and cementing requirements by type of casing string?

The table in this section identifies specific design, setting, and cementing requirements for casing strings and liners. For the purposes of subpart D, the casing strings in order of normal installation are as follows: drive or structural, conductor, surface, intermediate, and production casings (including liners). The District Manager may approve or prescribe other casing and cementing requirements where appropriate.

Casing type Casing requirements Cementing requirements
(a) Drive or Structural Set by driving, jetting, or drilling to the minimum depth as approved or prescribed by the District Manager If you drilled a portion of this hole, you must use enough cement to fill the annular space back to the mudline.
(b) Conductor Design casing and select setting depths based on relevant engineering and geologic factors. These factors include the presence or absence of hydrocarbons, potential hazards, and water depths
Set casing immediately before drilling into formations known to contain oil or gas. If you encounter oil or gas or unexpected formation pressure before the planned casing point, you must set casing immediately and set it above the encountered zone
Use enough cement to fill the calculated annular space back to the mudline.
Verify annular fill by observing cement returns. If you cannot observe cement returns, use additional cement to ensure fill-back to the mudline.
For drilling on an artificial island or when using a well cellar, you must discuss the cement fill level with the District Manager.
(c) Surface Design casing and select setting depths based on relevant engineering and geologic factors. These factors include the presence or absence of hydrocarbons, potential hazards, and water depths Use enough cement to fill the calculated annular space to at least 200 feet measured depth (MD) inside the conductor casing.
When geologic conditions such as near-surface fractures and faulting exist, you must use enough cement to fill the calculated annular space to the mudline.
(d) Intermediate Design casing and select setting depth based on anticipated or encountered geologic characteristics or wellbore conditions Use enough cement to cover and isolate all hydrocarbon-bearing zones and isolate abnormal pressure intervals from normal pressure intervals in the well.
As a minimum, you must cement the annular space 500 feet MD above the casing shoe and 500 feet MD above each zone to be isolated.
(e) Production Design casing and select setting depth based on anticipated or encountered geologic characteristics or wellbore conditions Use enough cement to cover or isolate all hydrocarbon-bearing zones above the shoe.
As a minimum, you must cement the annular space at least 500 feet MD above the casing shoe and 500 feet MD above the uppermost hydrocarbon-bearing zone.
(f) Liners If you use a liner as surface casing, you must set the top of the liner at least 200 feet MD above the previous casing/liner shoe.
If you use a liner as an intermediate string below a surface string or production casing below an intermediate string, you must set the top of the liner at least 100 feet MD above the previous casing shoe.
You may not use a liner as conductor casing.
A subsea well casing string whose top is above the mudline and that has been cemented back to the mudline will not be considered a liner.
Same as cementing requirements for specific casing types. For example, a liner used as intermediate casing must be cemented according to the cementing requirements for intermediate casing.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 26018, Apr. 29, 2016; 84 FR 21974, May 15, 2019]

§ 250.422 When may I resume drilling after cementing?

(a) After cementing surface, intermediate, or production casing (or liners), you may resume drilling after the cement has been held under pressure for 12 hours. For conductor casing, you may resume drilling after the cement has been held under pressure for 8 hours. One acceptable method of holding cement under pressure is to use float valves to hold the cement in place.

(b) If you plan to nipple down your diverter or BOP stack during the 8- or 12-hour waiting time, you must determine, before nippling down, when it will be safe to do so. You must base your determination on a knowledge of formation conditions, cement composition, effects of nippling down, presence of potential drilling hazards, well conditions during drilling, cementing, and post cementing, as well as past experience.

§ 250.423 What are the requirements for casing and liner installation?

You must ensure proper installation of casing in the subsea wellhead or liner in the liner hanger.

(a) You must ensure that the latching mechanisms or lock down mechanisms are engaged upon successfully installing the casing string.

(b) If you run a liner that has a latching mechanism or lock down mechanism, you must ensure that the latching mechanisms or lock down mechanisms are engaged upon successfully installing the liner.

(c) You must perform a pressure test on the casing seal assembly to ensure proper installation of casing or liner. You must perform this test for the intermediate and production casing strings or liners.

(1) You must submit for approval with your APD, test procedures and criteria for a successful test.

(2) You must document all your test results and make them available to BSEE upon request.

[81 FR 26019, Apr. 29, 2016, as amended at 84 FR 21974, May 15, 2019]

§§ 250.424-250.426 [Reserved]
§ 250.427 What are the requirements for pressure integrity tests?

You must conduct a pressure integrity test below the surface casing or liner and all intermediate casings or liners. The District Manager may require you to run a pressure-integrity test at the conductor casing shoe if warranted by local geologic conditions or the planned casing setting depth. You must conduct each pressure integrity test after drilling at least 10 feet but no more than 50 feet of new hole below the casing shoe. You must test to either the formation leak-off pressure or to an equivalent drilling fluid weight if identified in an approved APD.

(a) You must use the pressure integrity test and related hole-behavior observations, such as pore-pressure test results, gas-cut drilling fluid, and well kicks to adjust the drilling fluid program and the setting depth of the next casing string. You must record all test results and hole-behavior observations made during the course of drilling related to formation integrity and pore pressure in the driller's report.

(b) While drilling, you must maintain the safe drilling margin identified in § 250.414. When you cannot maintain the safe drilling margin, you must:

(1) Suspend drilling operations and submit proposed remedial actions to the District Manager. The District Manager must review and approve your proposed remedial actions, which may include limited drilling through a lost circulation zone; or

(2) Notify the District Manager and take further action in accordance with API Bulletin 92L (as incorporated by reference in § 250.198), if appropriate. You must submit a revised permit documenting any responsive actions taken.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 26019, Apr. 29, 2016; 84 FR 21974, May 15, 2019]

§ 250.428 What must I do in certain cementing and casing situations?

The table in this section describes actions that lessees must take when certain situations occur during casing and cementing activities.

If you encounter the following situation: Then you must . . .
(a) Have unexpected formation pressures or conditions that warrant revising your casing design, Submit a revised casing program to the District Manager for approval.
(b) Need to change casing setting depths or hole interval drilling depth (for a BHA with an under-reamer, this means bit depth) more than 100 feet true vertical depth (TVD) from the approved APD due to conditions encountered during drilling operations, Submit those changes to the District Manager for approval and include a certification by a professional engineer (PE) that he or she reviewed and approved the proposed changes.
(c) Have indication of inadequate cement job (such as unplanned lost returns, no cement returns to mudline or expected height, cement channeling, or failure of equipment), (1) Locate the top of cement by:
(i) Running a temperature survey;
(ii) Running a cement evaluation log;
(iii) Using tracers in the cement and logging them prior to drill out; or
(iv) Using a combination of these techniques.
(2) Determine if your cement job is inadequate. If your cement job is determined to be inadequate, refer to paragraph (d) of this section.
(3) If your cement job is determined to be adequate, report the results to the District Manager in your submitted WAR.
(d) Inadequate cement job, Comply with § 250.428(c)(1) and take remedial actions. The District Manager must review and approve all remedial actions either through a previously approved contingency plan within the permit or remedial actions included in a revised permit before you may take them, unless immediate actions must be taken to ensure the safety of the crew or to prevent a well-control event. If you complete any immediate action to ensure the safety of the crew or to prevent a well-control event, submit a description of the action to the District Manager when that action is complete. Any changes to the well program, that are not included in the approved permit, will require submittal of a certification by a professional engineer (PE) certifying that they have reviewed and approved the proposed changes. You must also meet any other requirements of the District Manager for remedial actions.
(e) Primary cement job that did not isolate abnormal pressure intervals, Isolate those intervals from normal pressures by squeeze cementing before you complete; suspend operations; or abandon the well, whichever occurs first.
(f) Decide to produce a well that was not originally contemplated for production, Have at least two cemented casing strings (does not include liners) in the well. Note: All producing wells must have at least two cemented casing strings.
(g) Want to drill a well without setting conductor casing, Submit geologic data and information to the District Manager that demonstrates the absence of shallow hydrocarbons or hazards. This information must include logging and drilling fluid-monitoring from wells previously drilled within 500 feet of the proposed well path down to the next casing point.
(h) Need to use less than required cement for the surface casing during floating drilling operations to provide protection from burst and collapse pressures, Submit information to the District Manager that demonstrates the use of less cement is necessary.
(i) Cement across a permafrost zone, Use cement that sets before it freezes and has a low heat of hydration.
(j) Leave the annulus opposite a permafrost zone uncemented, Fill the annulus with a liquid that has a freezing point below the minimum permafrost temperature and minimizes opposite a corrosion.
(k) Plan to use a valve(s) on the drive pipe during cementing operations for the conductor casing, surface casing, or liner, Include a description of the plan in your APD. Your description must include a schematic of the valve and height above the water line. The valve must be remotely operated and full opening with visual observation while taking returns. The person in charge of observing returns must be in communication with the drill floor. You must record in your daily report and in the WAR if cement returns were observed. If cement returns are not observed, you must contact the District Manager and obtain approval of proposed plans to locate the top of cement before continuing with operations.

[76 FR 64462, Oct. 18, 2011, as amended at 77 FR 50892, Aug. 22, 2012; 81 FR 26019, Apr. 29, 2016; 84 FR 21974, May 15, 2019]

Diverter System Requirements
§ 250.430 When must I install a diverter system?

You must install a diverter system before you drill a conductor or surface hole. The diverter system consists of a diverter sealing element, diverter lines, and control systems. You must design, install, use, maintain, and test the diverter system to ensure proper diversion of gases, water, drilling fluid, and other materials away from facilities and personnel.

§ 250.431 What are the diverter design and installation requirements?

You must design and install your diverter system to:

(a) Use diverter spool outlets and diverter lines that have a nominal diameter of at least 10 inches for surface wellhead configurations and at least 12 inches for floating drilling operations;

(b) Use dual diverter lines arranged to provide for downwind diversion capability;

(c) Use at least two diverter control stations. One station must be on the drilling floor. The other station must be in a readily accessible location away from the drilling floor;

(d) Use only remote-controlled valves in the diverter lines. All valves in the diverter system must be full-opening. You may not install manual or butterfly valves in any part of the diverter system;

(e) Minimize the number of turns (only one 90-degree turn allowed for each line for bottom-founded drilling units) in the diverter lines, maximize the radius of curvature of turns, and target all right angles and sharp turns;

(f) Anchor and support the entire diverter system to prevent whipping and vibration; and

(g) Protect all diverter-control instruments and lines from possible damage by thrown or falling objects.

§ 250.432 How do I obtain a departure to diverter design and installation requirements?

The table below describes possible departures from the diverter requirements and the conditions required for each departure. To obtain one of these departures, you must have discussed the departure in your APD and received approval from the District Manager.

If you want a departure to: Then you must . . .
(a) Use flexible hose for diverter lines instead of rigid pipe, Use flexible hose that has integral end couplings.
(b) Use only one spool outlet for your diverter system, (1) Have branch lines that meet the minimum internal diameter requirements; and (2) Provide downwind diversion capability.
(c) Use a spool with an outlet with an internal diameter of less than 10 inches on a surface wellhead, Use a spool that has dual outlets with an internal diameter of at least 8 inches.
(d) Use a single diverter line for floating drilling operations on a dynamically positioned drillship, Maintain an appropriate vessel heading to provide for downwind diversion.
§ 250.433 What are the diverter actuation and testing requirements?

When you install the diverter system, you must actuate the diverter sealing element, diverter valves, and diverter-control systems and control stations. You must also flow-test the vent lines.

(a) For drilling operations with a surface wellhead configuration, you must actuate the diverter system at least once every 24-hour period after the initial test. After you have nippled up on conductor casing, you must pressure-test the diverter-sealing element and diverter valves to a minimum of 200 psi. While the diverter is installed, you must conduct subsequent pressure tests within 7 days after the previous test.

(b) For floating drilling operations with a subsea BOP stack, you must actuate the diverter system within 7 days after the previous actuation. For subsequent testing, you may partially actuate the diverter element and a flow test is not required.

(c) You must alternate actuations and tests between control stations.

[76 FR 64462, Oct. 18, 2011, as amended at 84 FR 21975, May 15, 2019]

§ 250.434 What are the recordkeeping requirements for diverter actuations and tests?

You must record the time, date, and results of all diverter actuations and tests in the driller's report. In addition, you must:

(a) Record the diverter pressure test on a pressure chart;

(b) Require your onsite representative to sign and date the pressure test chart;

(c) Identify the control station used during the test or actuation;

(d) Identify problems or irregularities observed during the testing or actuations and record actions taken to remedy the problems or irregularities; and

(e) Retain all pressure charts and reports pertaining to the diverter tests and actuations at the facility for the duration of drilling the well.

§§ 250.440-250.451 [Reserved]
§ 250.452 What are the real-time monitoring requirements for Arctic OCS exploratory drilling operations?

(a) When conducting exploratory drilling operations on the Arctic OCS, you must gather and monitor real-time data using an independent, automatic, and continuous monitoring system capable of recording, storing, and transmitting data regarding the following:

(1) The BOP control system;

(2) The well's fluid handling systems on the rig; and

(3) The well's downhole conditions as monitored by a downhole sensing system, when such a system is installed.

(b) During well operations, you must transmit the data identified in paragraph (a) of this section as they are gathered, barring unforeseeable or unpreventable interruptions in transmission, and have the capability to monitor the data onshore, using qualified personnel. Onshore personnel who monitor real-time data must have the capability to contact rig personnel during operations. After well operations, you must store the data at a designated location for recordkeeping purposes as required in §§ 250.740 and 250.741. You must provide BSEE with access to your real-time monitoring data onshore upon request.

[81 FR 46561, July 15, 2016]

Drilling Fluid Requirements
§ 250.455 What are the general requirements for a drilling fluid program?

You must design and implement your drilling fluid program to prevent the loss of well control. This program must address drilling fluid safe practices, testing and monitoring equipment, drilling fluid quantities, and drilling fluid-handling areas.

§ 250.456 What safe practices must the drilling fluid program follow?

Your drilling fluid program must include the following safe practices:

(a) Before starting out of the hole with drill pipe, you must properly condition the drilling fluid. You must circulate a volume of drilling fluid equal to the annular volume with the drill pipe just off-bottom. You may omit this practice if documentation in the driller's report shows:

(1) No indication of formation fluid influx before starting to pull the drill pipe from the hole;

(2) The weight of returning drilling fluid is within 0.2 pounds per gallon (1.5 pounds per cubic foot) of the drilling fluid entering the hole; and

(3) Other drilling fluid properties are within the limits established by the program approved in the APD.

(b) Record each time you circulate drilling fluid in the hole in the driller's report;

(c) When coming out of the hole with drill pipe, you must fill the annulus with drilling fluid before the hydrostatic pressure decreases by 75 psi, or every five stands of drill pipe, whichever gives a lower decrease in hydrostatic pressure. You must calculate the number of stands of drill pipe and drill collars that you may pull before you must fill the hole. You must also calculate the equivalent drilling fluid volume needed to fill the hole. Both sets of numbers must be posted near the driller's station. You must use a mechanical, volumetric, or electronic device to measure the drilling fluid required to fill the hole;

(d) You must run and pull drill pipe and downhole tools at controlled rates so you do not swab or surge the well;

(e) When there is an indication of swabbing or influx of formation fluids, you must take appropriate measures to control the well. You must circulate and condition the well, on or near-bottom, unless well or drilling-fluid conditions prevent running the drill pipe back to the bottom;

(f) You must calculate and post near the driller's console the maximum pressures that you may safely contain under a shut-in BOP for each casing string. The pressures posted must consider the surface pressure at which the formation at the shoe would break down, the rated working pressure of the BOP stack, and 70 percent of casing burst (or casing test as approved by the District Manager). As a minimum, you must post the following two pressures:

(1) The surface pressure at which the shoe would break down. This calculation must consider the current drilling fluid weight in the hole; and

(2) The lesser of the BOP's rated working pressure or 70 percent of casing-burst pressure (or casing test otherwise approved by the District Manager);

(g) You must install an operable drilling fluid-gas separator and degasser before you begin drilling operations. You must maintain this equipment throughout the drilling of the well;

(h) Before pulling drill-stem test tools from the hole, you must circulate or reverse-circulate the test fluids in the hole. If circulating out test fluids is not feasible, you may bullhead test fluids out of the drill-stem test string and tools with an appropriate kill weight fluid;

(i) When circulating, you must test the drilling fluid at least once each tour, or more frequently if conditions warrant. Your tests must conform to industry-accepted practices and include density, viscosity, and gel strength; hydrogenion concentration; filtration; and any other tests the District Manager requires for monitoring and maintaining drilling fluid quality, prevention of downhole equipment problems and for kick detection. You must record the results of these tests in the drilling fluid report; and

(j) In areas where permafrost and/or hydrate zones are present or may be present, you must control drilling fluid temperatures to drill safely through those zones.

[76 FR 64462, Oct. 18, 2011, as amended at 77 FR 50894, Aug. 22, 2012; 81 FR 26020, Apr. 29, 2016]

§ 250.457 What equipment is required to monitor drilling fluids?

Once you establish drilling fluid returns, you must install and maintain the following drilling fluid-system monitoring equipment throughout subsequent drilling operations. This equipment must have the following indicators on the rig floor:

(a) Pit level indicator to determine drilling fluid-pit volume gains and losses. This indicator must include both a visual and an audible warning device;

(b) Volume measuring device to accurately determine drilling fluid volumes required to fill the hole on trips;

(c) Return indicator devices that indicate the relationship between drilling fluid-return flow rate and pump discharge rate. This indicator must include both a visual and an audible warning device; and

(d) Gas-detecting equipment to monitor the drilling fluid returns. The indicator may be located in the drilling fluid-logging compartment or on the rig floor. If the indicators are only in the logging compartment, you must continually man the equipment and have a means of immediate communication with the rig floor. If the indicators are on the rig floor only, you must install an audible alarm.

§ 250.458 What quantities of drilling fluids are required?

(a) You must use, maintain, and replenish quantities of drilling fluid and drilling fluid materials at the drill site as necessary to ensure well control. You must determine those quantities based on known or anticipated drilling conditions, rig storage capacity, weather conditions, and estimated time for delivery.

(b) You must record the daily inventories of drilling fluid and drilling fluid materials, including weight materials and additives in the drilling fluid report.

(c) If you do not have sufficient quantities of drilling fluid and drilling fluid material to maintain well control, you must suspend drilling operations.

§ 250.459 What are the safety requirements for drilling fluid-handling areas?

You must classify drilling fluid-handling areas according to API RP 500, Recommended Practice for Classification of Locations for Electrical Installations at Petroleum Facilities, Classified as Class I, Division 1 and Division 2 (as incorporated by reference in § 250.198); or API RP 505, Recommended Practice for Classification of Locations for Electrical Installations at Petroleum Facilities, Classified as Class 1, Zone 0, Zone 1, and Zone 2 (as incorporated by reference in § 250.198). In areas where dangerous concentrations of combustible gas may accumulate, you must install and maintain a ventilation system and gas monitors. Drilling fluid-handling areas must have the following safety equipment:

(a) A ventilation system capable of replacing the air once every 5 minutes or 1.0 cubic feet of air-volume flow per minute, per square foot of area, whichever is greater. In addition:

(1) If natural means provide adequate ventilation, then a mechanical ventilation system is not necessary;

(2) If a mechanical system does not run continuously, then it must activate when gas detectors indicate the presence of 1 percent or more of combustible gas by volume; and

(3) If discharges from a mechanical ventilation system may be hazardous, then you must maintain the drilling fluid-handling area at a negative pressure. You must protect the negative pressure area by using at least one of the following: a pressure-sensitive alarm, open-door alarms on each access to the area, automatic door-closing devices, air locks, or other devices approved by the District Manager;

(b) Gas detectors and alarms except in open areas where adequate ventilation is provided by natural means. You must test and recalibrate gas detectors quarterly. No more than 90 days may elapse between tests;

(c) Explosion-proof or pressurized electrical equipment to prevent the ignition of explosive gases. Where you use air for pressuring equipment, you must locate the air intake outside of and as far as practicable from hazardous areas; and

(d) Alarms that activate when the mechanical ventilation system fails.

Other Drilling Requirements
§ 250.460 What are the requirements for conducting a well test?

(a) If you intend to conduct a well test, you must include your projected plans for the test with your APD (form BSEE-0123) or in an Application for Permit to Modify (APM) (form BSEE-0124). Your plans must include at least the following information:

(1) Estimated flowing and shut-in tubing pressures;

(2) Estimated flow rates and cumulative volumes;

(3) Time duration of flow, buildup, and drawdown periods;

(4) Description and rating of surface and subsurface test equipment;

(5) Schematic drawing, showing the layout of test equipment;

(6) Description of safety equipment, including gas detectors and fire-fighting equipment;

(7) Proposed methods to handle or transport produced fluids; and

(8) Description of the test procedures.

(b) You must give the District Manager at least 24-hours notice before starting a well test.

§ 250.461 What are the requirements for directional and inclination surveys?

For this subpart, BSEE classifies a well as vertical if the calculated average of inclination readings does not exceed 3 degrees from the vertical.

(a) Survey requirements for a vertical well.

(1) You must conduct inclination surveys on each vertical well and record the results. Survey intervals may not exceed 1,000 feet during the normal course of drilling;

(2) You must also conduct a directional survey that provides both inclination and azimuth, and digitally record the results in electronic format:

(i) Within 500 feet of setting surface or intermediate casing;

(ii) Within 500 feet of setting any liner; and

(iii) When you reach total depth.

(b) Survey requirements for a directional well. You must conduct directional surveys on each directional well and digitally record the results. Surveys must give both inclination and azimuth at intervals not to exceed 500 feet during the normal course of drilling. Intervals during angle-changing portions of the hole may not exceed 180 feet.

(c) Measurement while drilling. You may use measurement-while-drilling technology if it meets the requirements of this section.

(d) Composite survey requirements.

(1) Your composite directional survey must show the interval from the bottom of the conductor casing to total depth. In the absence of conductor casing, the survey must show the interval from the bottom of the drive or structural casing to total depth; and

(2) You must correct all surveys to Universal-Transverse-Mercator-Grid-north or Lambert-Grid-north after making the magnetic-to-true-north correction. Surveys must show the magnetic and grid corrections used and include a listing of the directionally computed inclinations and azimuths.

(e) If you drill within 500 feet of an adjacent lease, the Regional Supervisor may require you to furnish a copy of the well's directional survey to the affected leaseholder. This could occur when the adjoining leaseholder requests a copy of the survey for the protection of correlative rights.

[76 FR 64462, Oct. 18, 2011, as amended at 84 FR 21975, May 15, 2019]

§ 250.462 What are the source control, containment, and collocated equipment requirements?

For drilling operations using a subsea BOP or surface BOP on a floating facility, you must have the ability to control or contain a blowout event at the sea floor.

(a) To determine your required source control and containment capabilities you must do the following:

(1) Consider a scenario of the wellbore fully evacuated to reservoir fluids, with no restrictions in the well.

(2) Evaluate the performance of the well as designed to determine if a full shut-in can be achieved without having reservoir fluids broach to the sea floor. If your evaluation indicates that the well can only be partially shut-in, then you must determine your ability to flow and capture the residual fluids to a surface production and storage system.

(b) You must have access to and the ability to deploy Source Control and Containment Equipment (SCCE) and all other necessary supporting and collocated equipment to regain control of the well. SCCE means the capping stack, cap-and-flow system, containment dome, and/or other subsea and surface devices, equipment, and vessels, which have the collective purpose to control a spill source and stop the flow of fluids into the environment or to contain fluids escaping into the environment based on the determinations outlined in paragraph (a) of this section. This SCCE, supporting equipment, and collocated equipment may include, but is not limited to, the following:

(1) Subsea containment and capture equipment, including containment domes and capping stacks;

(2) Subsea utility equipment including hydraulic power sources and hydrate control equipment;

(3) Collocated equipment including dispersant injection equipment;

(4) Riser systems;

(5) Remotely operated vehicles (ROVs);

(6) Capture vessels;

(7) Support vessels; and

(8) Storage facilities.

(c) You must submit a description of your source control and containment capabilities to the Regional Supervisor and receive approval before BSEE will approve your APD, Form BSEE-0123. The description of your containment capabilities must contain the following:

(1) Your source control and containment capabilities for controlling and containing a blowout event at the seafloor;

(2) A discussion of the determination required in paragraph (a) of this section; and

(3) Information showing that you have access to and the ability to deploy all equipment required by paragraph (b) of this section.

(d) You must contact the District Manager and Regional Supervisor for reevaluation of your source control and containment capabilities if your:

(1) Well design changes; or

(2) Approved source control and containment equipment is out of service.

(e) You must maintain, test, and inspect the source control, containment, and collocated equipment identified in the following table according to these requirements:

Equipment Requirements, you must: Additional information
(1) Capping stacks, (i) Function test all pressure containing critical components on a quarterly frequency (not to exceed 104 days between tests), Pressure containing critical components are those components that will experience wellbore pressure during a shut-in after being functioned.
(ii) Pressure test pressure containing critical components on a bi-annual basis, but not later than 210 days from the last pressure test. All pressure testing must be witnessed by BSEE (if available) and an independent third party. Pressure containing critical components are those components that will experience wellbore pressure during a shut-in. These components include, but are not limited to: All blind rams, wellhead connectors, and outlet valves.
(iii) Notify BSEE at least 21 days prior to commencing any pressure testing
(2) Production safety systems used for flow and capture operations, (i) Meet or exceed the requirements set forth in Subpart H, excluding required equipment that would be installed below the wellhead or that is not applicable to the cap and flow system.
(ii) Have all equipment unique to containment operations available for inspection at all times
(3) Subsea utility equipment, Have all equipment utilized solely for containment operations available for inspection at all times Subsea utility equipment includes, but is not limited to: Hydraulic power sources, debris removal, and hydrate control equipment.
(4) Collocated equipment designated by the operator in the Regional Containment Demonstration (RCD) or Well Containment Plan (WCP), Have equipment available for inspection at all times Collocated equipment includes, but is not limited to, dispersant injection equipment and other subsea control equipment.

[81 FR 26020, Apr. 29, 2016, as amended at 84 FR 21975, May 15, 2019]

§ 250.463 Who establishes field drilling rules?

(a) The District Manager may establish field drilling rules different from the requirements of this subpart when geological and engineering information shows that specific operating requirements are appropriate. You must comply with field drilling rules and nonconflicting requirements of this subpart. The District Manager may amend or cancel field drilling rules at any time.

(b) You may request the District Manager to establish, amend, or cancel field drilling rules.

Applying for a Permit To Modify and Well Records
§ 250.465 When must I submit an Application for Permit to Modify (APM) or an End of Operations Report to BSEE?

(a) You must submit an APM (form BSEE-0124) or an End of Operations Report (form BSEE-0125) and other materials to the Regional Supervisor as shown in the following table. You must also submit a public information copy of each form.

When you . . . Then you must . . . And . . .
(1) Intend to revise your drilling plan, change major drilling equipment, or plugback, Submit form BSEE-0124 or request oral approval, Receive written or oral approval from the District Manager before you begin the intended operation. If you get an approval, you must submit form BSEE-0124 no later than the end of the 3rd business day following the oral approval. In all cases, or you must meet the additional requirements in paragraph (b) of this section.
(2) Determine a well's final surface location, water depth, and the rotary kelly bushing elevation, Immediately Submit a form BSEE-0124, Submit a plat certified by a registered land surveyor that meets the requirements of § 250.412.
(3) Move a drilling unit from a wellbore before completing a well, Submit forms BSEE-0124 and BSEE-0125 within 30 days after the suspension of wellbore operations, Submit appropriate copies of the well records.

(b) If you intend to perform any of the actions specified in paragraph (a)(1) of this section, you must meet the following additional requirements:

(1) Your APM (Form BSEE-0124) must contain a detailed statement of the proposed work that would materially change from the approved APD. The submission of your APM must be accompanied by payment of the service fee listed in § 250.125;

(2) Your form BSEE-0124 must include the present status of the well, depth of all casing strings set to date, well depth, present production zones and productive capability, and all other information specified; and

(3) Within 30 days after completing this work, you must submit an End of Operations Report (EOR), Form BSEE-0125, as required under § 250.744.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 26021, Apr. 29, 2016]

§§ 250.466-250.469 [Reserved]
Additional Arctic OCS Requirements
Source:

81 FR 46561, July 15, 2016, unless otherwise noted.

§ 250.470 What additional information must I submit with my APD for Arctic OCS exploratory drilling operations?

In addition to complying with all other applicable requirements included in this part, you must provide with your APD all of the following information pertaining to your proposed Arctic OCS exploratory drilling:

(a) A detailed description of:

(1) The environmental, meteorological, and oceanic conditions you expect to encounter at the well site(s);

(2) How you will prepare your equipment, materials, and drilling unit for service in the conditions identified in paragraph (a)(1) of this section, and how your drilling unit will be in compliance with the requirements of § 250.713.

(b) A detailed description of all operations necessary in Arctic OCS conditions to transition the rig from being under way to conducting drilling operations and from ending drilling operations to being under way, as well as any anticipated repair and maintenance plans for the drilling unit and equipment. You should include, among other things, a description of how you plan to:

(1) Recover the subsea equipment, including the marine riser and the lower marine riser package;

(2) Recover the BOP;

(3) Recover the auxiliary sub-sea controls and template;

(4) Lay down the drill pipe and secure the drill pipe and marine riser;

(5) Secure the drilling equipment;

(6) Transfer the fluids for transport or disposal;

(7) Secure ancillary equipment like the draw works and lines;

(8) Refuel or transfer fuel;

(9) Offload waste;

(10) Recover the Remotely Operated Vehicles;

(11) Pick up the oil spill prevention booms and equipment; and

(12) Offload the drilling crew.

(c) A description of well-specific drilling objectives, timelines, and updated contingency plans for temporary abandonment of the well, including but not limited to the following:

(1) When you will spud the particular well (i.e., begin drilling operations at the well site) identified in the APD;

(2) How long you will take to drill the well;

(3) Anticipated depths and geologic targets, with timelines;

(4) When you expect to set and cement each string of casing;

(5) When and how you would log the well;

(6) Your plans to test the well;

(7) When and how you intend to abandon the well, including specifically addressing your plans for how to move the rig off location and how you will meet the requirements of § 250.720(c);

(8) A description of what equipment and vessels will be involved in the process of temporarily abandoning the well due to ice; and

(9) An explanation of how you will integrate these elements into your overall program.

(d) A detailed description of your weather and ice forecasting capability for all phases of the drilling operation, including:

(1) How you will ensure your continuous awareness of potential weather and ice hazards at, and during transition between, wells;

(2) Your plans for managing ice hazards and responding to weather events; and

(3) Verification that you have the capabilities described in your BOEM-approved EP.

(e) A detailed description of how you will comply with the requirements of § 250.472.

(f) A statement that you own, or have a contract with a provider for, source control and containment equipment (SCCE), which is capable of controlling and/or containing a worst case discharge, as described in your BOEM-approved EP, when proposing to use a MODU to conduct exploratory drilling operations on the Arctic OCS. The following information must be included in your SCCE submittal:

(1) A detailed description of your or your contractor's SCCE capability to stop or contain flow from an out-of-control well, including your operating assumptions and limitations; your access to and ability to deploy, in accordance with § 250.471, all necessary SCCE; and your ability to evaluate the performance of the well design to determine how you can achieve a full shut-in without having reservoir fluids discharged into the environment;

(2) An inventory of the local and regional SCCE, supplies, and services that you own or for which you have a contract with a provider. You must identify each supplier of such equipment and services and provide their locations and telephone numbers;

(3) Where applicable, proof of contracts or membership agreements with cooperatives, service providers, or other contractors who will provide you with the necessary SCCE or related supplies and services if you do not possess them. The contract or membership agreement must include provisions for ensuring the availability of the personnel and/or equipment on a 24-hour per day basis while you are drilling below or working below the surface casing;

(4) A detailed description of the procedures you plan to use to inspect, test, and maintain your SCCE; and

(5) A detailed description of your plan to ensure that all members of your operating team, who are responsible for operating the SCCE, have received the necessary training to deploy and operate such equipment in Arctic OCS conditions and demonstrate ongoing proficiency in source control operations. You must also identify and include the dates of prior and planned training.

(g) Where it does not conflict with other requirements of this subpart, and except as provided in paragraphs (g)(1) through (11) of this section, you must comply with the requirements of API RP 2N, Third Edition “Planning, Designing, and Constructing Structures and Pipelines for Arctic Conditions” (incorporated by reference as specified in § 250.198), and provide a detailed description of how you will utilize the best practices included in API RP 2N during your exploratory drilling operations. You are not required to incorporate the following sections of API RP 2N into your drilling operations:

(1) Sections 6.6.3 through 6.6.4;

(2) The foundation recommendations in Section 8.4;

(4) The recommendations for permanently moored systems in Section 9.7;

(5) The recommendations for pile foundations in Section 9.10;

(6) Section 12;

(8) Sections 13.8.1.1, 13.8.2.1, 13.8.2.2, 13.8.2.4 through 13.8.2.7;

(9) Sections 13.9.1, 13.9.2, 13.9.4 through 13.9.8;

(10) Sections 14 through 16; and

(11) Section 18.

§ 250.471 What are the requirements for Arctic OCS source control and containment?

You must meet the following requirements for all exploration wells drilled on the Arctic OCS:

(a) If you use a MODU when drilling below or working below the surface casing, you must have access to the following SCCE capable of stopping or capturing the flow of an out-of-control well:

(1) A capping stack, positioned to ensure that it will arrive at the well location within 24 hours after a loss of well control and can be deployed as directed by the Regional Supervisor pursuant to paragraph (h) of this section;

(2) A cap and flow system, positioned to ensure that it will arrive at the well location within 7 days after a loss of well control and can be deployed as directed by the Regional Supervisor pursuant to paragraph (h) of this section. The cap and flow system must be designed to capture at least the amount of hydrocarbons equivalent to the calculated worst case discharge rate referenced in your BOEM-approved EP; and

(3) A containment dome, positioned to ensure that it will arrive at the well location within 7 days after a loss of well control and can be deployed as directed by the Regional Supervisor pursuant to paragraph (h) of this section. The containment dome must have the capacity to pump fluids without relying on buoyancy.

(b) You must conduct a monthly stump test of dry-stored capping stacks. If you use a pre-positioned capping stack, you must conduct a stump test prior to each installation on each well.

(c) As required by § 250.465(a), if you propose to change your well design, you must submit an APM. For Arctic OCS operations, your APM must include a reevaluation of your SCCE capabilities for any new Worst Case Discharge (WCD) rate, and a demonstration that your SCCE capabilities will meet the criteria in § 250.470(f) under the changed well design.

(d) You must conduct tests or exercises of your SCCE, including deployment of your SCCE, when directed by the Regional Supervisor.

(e) You must maintain records pertaining to testing, inspection, and maintenance of your SCCE for at least 10 years and make the records available to any authorized BSEE representative upon request.

(f) You must maintain records pertaining to the use of your SCCE during testing, training, and deployment activities for at least 3 years and make the records available to any authorized BSEE representative upon request.

(g) Upon a loss of well control, you must initiate transit of all SCCE identified in paragraph (a) of this section to the well.

(h) You must deploy and use SCCE when directed by the Regional Supervisor.

(i) Operators may request approval of alternate procedures or equipment to the SCCE requirements of subparagraph (a) of this section in accordance with § 250.141. The operator must show and document that the alternate procedures or equipment will provide a level of safety and environmental protection that will meet or exceed the level of safety and environmental protection required by BSEE regulations, including demonstrating that the alternate procedures or equipment will be capable of stopping or capturing the flow of an out-of-control well.

§ 250.472 What are the relief rig requirements for the Arctic OCS?

(a) In the event of a loss of well control, the Regional Supervisor may direct you to drill a relief well using the relief rig able to kill and permanently plug an out-of-control well as described in your APD. Your relief rig must comply with all other requirements of this part pertaining to drill rig characteristics and capabilities, and it must be able to drill a relief well under anticipated Arctic OCS conditions.

(b) When you are drilling below or working below the surface casing during Arctic OCS exploratory drilling operations, you must have access to a relief rig, different from your primary drilling rig, staged in a location such that it can arrive on site, drill a relief well, kill and abandon the original well, and abandon the relief well prior to expected seasonal ice encroachment at the drill site, but no later than 45 days after the loss of well control.

(c) Operators may request approval of alternative compliance measures to the relief rig requirement in accordance with § 250.141. The operator must show and document that the alternate compliance measure will meet or exceed the level of safety and environmental protection required by BSEE regulations, including demonstrating that the alternate compliance measure will be able to kill and permanently plug an out-of-control well.

§ 250.473 What must I do to protect health, safety, property, and the environment while operating on the Arctic OCS?

In addition to the requirements set forth in § 250.107, when conducting exploratory drilling operations on the Arctic OCS, you must protect health, safety, property, and the environment by using the following:

(a) Equipment and materials that are rated or de-rated for service under conditions that can be reasonably expected during your operations; and

(b) Measures to address human factors associated with weather conditions that can be reasonably expected during your operations including, but not limited to, provision of proper attire and equipment, construction of protected work spaces, and management of shifts.

Hydrogen Sulfide
§ 250.490 Hydrogen sulfide.

(a) What precautions must I take when operating in an H2S area? You must:

(1) Take all necessary and feasible precautions and measures to protect personnel from the toxic effects of H2S and to mitigate damage to property and the environment caused by H2S. You must follow the requirements of this section when conducting drilling, well-completion/well-workover, and production operations in zones with H2S present and when conducting operations in zones where the presence of H2S is unknown. You do not need to follow these requirements when operating in zones where the absence of H2S has been confirmed; and

(2) Follow your approved contingency plan.

(b) Definitions. Terms used in this section have the following meanings:

Facility means a vessel, a structure, or an artificial island used for drilling, well-completion, well-workover, and/or production operations.

H2S absent means:

(1) Drilling, logging, coring, testing, or producing operations have confirmed the absence of H2S in concentrations that could potentially result in atmospheric concentrations of 20 ppm or more of H2S; or

(2) Drilling in the surrounding areas and correlation of geological and seismic data with equivalent stratigraphic units have confirmed an absence of H2S throughout the area to be drilled.

H2S present means that drilling, logging, coring, testing, or producing operations have confirmed the presence of H2S in concentrations and volumes that could potentially result in atmospheric concentrations of 20 ppm or more of H2S.

H2S unknown means the designation of a zone or geologic formation where neither the presence nor absence of H2S has been confirmed.

Well-control fluid means drilling mud and completion or workover fluid as appropriate to the particular operation being conducted.

(c) Classifying an area for the presence of H2S. You must:

(1) Request and obtain an approved classification for the area from the Regional Supervisor before you begin operations. Classifications are “H2S absent,” H2S present,” or “H2S unknown”;

(2) Submit your request with your application for permit to drill;

(3) Support your request with available information such as geologic and geophysical data and correlations, well logs, formation tests, cores and analysis of formation fluids; and

(4) Submit a request for reclassification of a zone when additional data indicate a different classification is needed.

(d) What do I do if conditions change? If you encounter H2S that could potentially result in atmospheric concentrations of 20 ppm or more in areas not previously classified as having H2S present, you must immediately notify BSEE and begin to follow requirements for areas with H2S present.

(e) What are the requirements for conducting simultaneous operations? When conducting any combination of drilling, well-completion, well-workover, and production operations simultaneously, you must follow the requirements in the section applicable to each individual operation.

(f) Requirements for submitting an H2S Contingency Plan. Before you begin operations, you must submit an H2S Contingency Plan to the District Manager for approval. Do not begin operations before the District Manager approves your plan. You must keep a copy of the approved plan in the field, and you must follow the plan at all times. Your plan must include:

(1) Safety procedures and rules that you will follow concerning equipment, drills, and smoking;

(2) Training you provide for employees, contractors, and visitors;

(3) Job position and title of the person responsible for the overall safety of personnel;

(4) Other key positions, how these positions fit into your organization, and what the functions, duties, and responsibilities of those job positions are;

(5) Actions that you will take when the concentration of H2S in the atmosphere reaches 20 ppm, who will be responsible for those actions, and a description of the audible and visual alarms to be activated;

(6) Briefing areas where personnel will assemble during an H2S alert. You must have at least two briefing areas on each facility and use the briefing area that is upwind of the H2S source at any given time;

(7) Criteria you will use to decide when to evacuate the facility and procedures you will use to safely evacuate all personnel from the facility by vessel, capsule, or lifeboat. If you use helicopters during H2S alerts, describe the types of H2S emergencies during which you consider the risk of helicopter activity to be acceptable and the precautions you will take during the flights;

(8) Procedures you will use to safely position all vessels attendant to the facility. Indicate where you will locate the vessels with respect to wind direction. Include the distance from the facility and what procedures you will use to safely relocate the vessels in an emergency;

(9) How you will provide protective-breathing equipment for all personnel, including contractors and visitors;

(10) The agencies and facilities you will notify in case of a release of H2S (that constitutes an emergency), how you will notify them, and their telephone numbers. Include all facilities that might be exposed to atmospheric concentrations of 20 ppm or more of H2S;

(11) The medical personnel and facilities you will use if needed, their addresses, and telephone numbers;

(12) H2S detector locations in production facilities producing gas containing 20 ppm or more of H2S. Include an “H2S Detector Location Drawing” showing:

(i) All vessels, flare outlets, wellheads, and other equipment handling production containing H2S;

(ii) Approximate maximum concentration of H2S in the gas stream; and

(iii) Location of all H2S sensors included in your contingency plan;

(13) Operational conditions when you expect to flare gas containing H2S including the estimated maximum gas flow rate, H2S concentration, and duration of flaring;

(14) Your assessment of the risks to personnel during flaring and what precautionary measures you will take;

(15) Primary and alternate methods to ignite the flare and procedures for sustaining ignition and monitoring the status of the flare (i.e., ignited or extinguished);

(16) Procedures to shut off the gas to the flare in the event the flare is extinguished;

(17) Portable or fixed sulphur dioxide (SO2)-detection system(s) you will use to determine SO2 concentration and exposure hazard when H2S is burned;

(18) Increased monitoring and warning procedures you will take when the SO2 concentration in the atmosphere reaches 2 ppm;

(19) Personnel protection measures or evacuation procedures you will initiate when the SO2 concentration in the atmosphere reaches 5 ppm;

(20) Engineering controls to protect personnel from SO2; and

(21) Any special equipment, procedures, or precautions you will use if you conduct any combination of drilling, well-completion, well-workover, and production operations simultaneously.

(g) Training program:

(1) When and how often do employees need to be trained? All operators and contract personnel must complete an H2S training program to meet the requirements of this section:

(i) Before beginning work at the facility; and

(ii) Each year, within 1 year after completion of the previous class.

(2) What training documentation do I need? For each individual working on the platform, either:

(i) You must have documentation of this training at the facility where the individual is employed; or

(ii) The employee must carry a training completion card.

(3) What training do I need to give to visitors and employees previously trained on another facility?

(i) Trained employees or contractors transferred from another facility must attend a supplemental briefing on your H2S equipment and procedures before beginning duty at your facility;

(ii) Visitors who will remain on your facility more than 24 hours must receive the training required for employees by paragraph (g)(4) of this section; and

(iii) Visitors who will depart before spending 24 hours on the facility are exempt from the training required for employees, but they must, upon arrival, complete a briefing that includes:

(A) Information on the location and use of an assigned respirator; practice in donning and adjusting the assigned respirator; information on the safe briefing areas, alarm system, and hazards of H2S and SO2; and

(B) Instructions on their responsibilities in the event of an H2S release.

(4) What training must I provide to all other employees? You must train all individuals on your facility on the:

(i) Hazards of H2S and of SO2 and the provisions for personnel safety contained in the H2S Contingency Plan;

(ii) Proper use of safety equipment which the employee may be required to use;

(iii) Location of protective breathing equipment, H2S detectors and alarms, ventilation equipment, briefing areas, warning systems, evacuation procedures, and the direction of prevailing winds;

(iv) Restrictions and corrective measures concerning beards, spectacles, and contact lenses in conformance with ANSI Z88.2, American National Standard for Respiratory Protection (as specified in § 250.198);

(v) Basic first-aid procedures applicable to victims of H2S exposure. During all drills and training sessions, you must address procedures for rescue and first aid for H2S victims;

(vi) Location of:

(A) The first-aid kit on the facility;

(B) Resuscitators; and

(C) Litter or other device on the facility.

(vii) Meaning of all warning signals.

(5) Do I need to post safety information? You must prominently post safety information on the facility and on vessels serving the facility (i.e., basic first-aid, escape routes, instructions for use of life boats, etc.).

(h) Drills.

(1) When and how often do I need to conduct drills on H2S safety discussions on the facility? You must:

(i) Conduct a drill for each person at the facility during normal duty hours at least once every 7-day period. The drills must consist of a dry-run performance of personnel activities related to assigned jobs.

(ii) At a safety meeting or other meetings of all personnel, discuss drill performance, new H2S considerations at the facility, and other updated H2S information at least monthly.

(2) What documentation do I need? You must keep records of attendance for:

(i) Drilling, well-completion, and well-workover operations at the facility until operations are completed; and

(ii) Production operations at the facility or at the nearest field office for 1 year.

(i) Visual and audible warning systems:

(1) How must I install wind direction equipment? You must install wind-direction equipment in a location visible at all times to individuals on or in the immediate vicinity of the facility.

(2) When do I need to display operational danger signs, display flags, or activate visual or audible alarms?

(i) You must display warning signs at all times on facilities with wells capable of producing H2S and on facilities that process gas containing H2S in concentrations of 20 ppm or more.

(ii) In addition to the signs, you must activate audible alarms and display flags or activate flashing red lights when atmospheric concentration of H2S reaches 20 ppm.

(3) What are the requirements for signs? Each sign must be a high-visibility yellow color with black lettering as follows:

Letter height Wording
12 inches Danger.
Poisonous Gas.
Hydrogen Sulfide.
7 inches Do not approach if red flag is flying.
(Use appropriate wording at right) Do not approach if red lights are flashing.

(4) May I use existing signs? You may use existing signs containing the words “Danger-Hydrogen Sulfide-H2S,” provided the words “Poisonous Gas. Do Not Approach if Red Flag is Flying” or “Red Lights are Flashing” in lettering of a minimum of 7 inches in height are displayed on a sign immediately adjacent to the existing sign.

(5) What are the requirements for flashing lights or flags? You must activate a sufficient number of lights or hoist a sufficient number of flags to be visible to vessels and aircraft. Each light must be of sufficient intensity to be seen by approaching vessels or aircraft any time it is activated (day or night). Each flag must be red, rectangular, a minimum width of 3 feet, and a minimum height of 2 feet.

(6) What is an audible warning system? An audible warning system is a public address system or siren, horn, or other similar warning device with a unique sound used only for H2S.

(7) Are there any other requirements for visual or audible warning devices? Yes, you must:

(i) Illuminate all signs and flags at night and under conditions of poor visibility; and

(ii) Use warning devices that are suitable for the electrical classification of the area.

(8) What actions must I take when the alarms are activated? When the warning devices are activated, the designated responsible persons must inform personnel of the level of danger and issue instructions on the initiation of appropriate protective measures.

(j) H2S-detection and H2S monitoring equipment:

(1) What are the requirements for an H2S detection system? An H2S detection system must:

(i) Be capable of sensing a minimum of 10 ppm of H2S in the atmosphere; and

(ii) Activate audible and visual alarms when the concentration of H2S in the atmosphere reaches 20 ppm.

(2) Where must I have sensors for drilling, well-completion, and well-workover operations? You must locate sensors at the:

(i) Bell nipple;

(ii) Mud-return line receiver tank (possum belly);

(iii) Pipe-trip tank;

(iv) Shale shaker;

(v) Well-control fluid pit area;

(vi) Driller's station;

(vii) Living quarters; and

(viii) All other areas where H2S may accumulate.

(3) Do I need mud sensors? The District Manager may require mud sensors in the possum belly in cases where the ambient air sensors in the mud-return system do not consistently detect the presence of H2S.

(4) How often must I observe the sensors? During drilling, well-completion and well-workover operations, you must continuously observe the H2S levels indicated by the monitors in the work areas during the following operations:

(i) When you pull a wet string of drill pipe or workover string;

(ii) When circulating bottoms-up after a drilling break;

(iii) During cementing operations;

(iv) During logging operations; and

(v) When circulating to condition mud or other well-control fluid.

(5) Where must I have sensors for production operations? On a platform where gas containing H2S of 20 ppm or greater is produced, processed, or otherwise handled:

(i) You must have a sensor in rooms, buildings, deck areas, or low-laying deck areas not otherwise covered by paragraph (j)(2) of this section, where atmospheric concentrations of H2S could reach 20 ppm or more. You must have at least one sensor per 400 square feet of deck area or fractional part of 400 square feet;

(ii) You must have a sensor in buildings where personnel have their living quarters;

(iii) You must have a sensor within 10 feet of each vessel, compressor, wellhead, manifold, or pump, which could release enough H2S to result in atmospheric concentrations of 20 ppm at a distance of 10 feet from the component;

(iv) You may use one sensor to detect H2S around multiple pieces of equipment, provided the sensor is located no more than 10 feet from each piece, except that you need to use at least two sensors to monitor compressors exceeding 50 horsepower;

(v) You do not need to have sensors near wells that are shut in at the master valve and sealed closed;

(vi) When you determine where to place sensors, you must consider:

(A) The location of system fittings, flanges, valves, and other devices subject to leaks to the atmosphere; and

(B) Design factors, such as the type of decking and the location of fire walls; and

(vii) The District Manager may require additional sensors or other monitoring capabilities, if warranted by site specific conditions.

(6) How must I functionally test the H2S Detectors?

(i) Personnel trained to calibrate the particular H2S detector equipment being used must test detectors by exposing them to a known concentration in the range of 10 to 30 ppm of H2S.

(ii) If the results of any functional test are not within 2 ppm or 10 percent, whichever is greater, of the applied concentration, recalibrate the instrument.

(7) How often must I test my detectors?

(i) When conducting drilling, drill stem testing, well-completion, or well-workover operations in areas classified as H2S present or H2S unknown, test all detectors at least once every 24 hours. When drilling, begin functional testing before the bit is 1,500 feet (vertically) above the potential H2S zone.

(ii) When conducting production operations, test all detectors at least every 14 days between tests.

(iii) If equipment requires calibration as a result of two consecutive functional tests, the District Manager may require that H2S-detection and H2S-monitoring equipment be functionally tested and calibrated more frequently.

(8) What documentation must I keep?

(i) You must maintain records of testing and calibrations (in the drilling or production operations report, as applicable) at the facility to show the present status and history of each device, including dates and details concerning:

(A) Installation;

(B) Removal;

(C) Inspection;

(D) Repairs;

(E) Adjustments; and

(F) Reinstallation.

(ii) Records must be available for inspection by BSEE personnel.

(9) What are the requirements for nearby vessels? If vessels are stationed overnight alongside facilities in areas of H2S present or H2S unknown, you must equip vessels with an H2S-detection system that activates audible and visual alarms when the concentration of H2S in the atmosphere reaches 20 ppm. This requirement does not apply to vessels positioned upwind and at a safe distance from the facility in accordance with the positioning procedure described in the approved H2S Contingency Plan.

(10) What are the requirements for nearby facilities? The District Manager may require you to equip nearby facilities with portable or fixed H2S detector(s) and to test and calibrate those detectors. To invoke this requirement, the District Manager will consider dispersion modeling results from a possible release to determine if 20 ppm H2S concentration levels could be exceeded at nearby facilities.

(11) What must I do to protect against SO2 if I burn gas containing H2S? You must:

(i) Monitor the SO2concentration in the air with portable or strategically placed fixed devices capable of detecting a minimum of 2 ppm of SO2;

(ii) Take readings at least hourly and at any time personnel detect SO2 odor or nasal irritation;

(iii) Implement the personnel protective measures specified in the H2S Contingency Plan if the SO2 concentration in the work area reaches 2 ppm; and

(iv) Calibrate devices every 3 months if you use fixed or portable electronic sensing devices to detect SO2.

(12) May I use alternative measures? You may follow alternative measures instead of those in paragraph (j)(11) of this section if you propose and the Regional Supervisor approves the alternative measures.

(13) What are the requirements for protective-breathing equipment? In an area classified as H2S present or H2S unknown, you must:

(i) Provide all personnel, including contractors and visitors on a facility, with immediate access to self-contained pressure-demand-type respirators with hoseline capability and breathing time of at least 15 minutes.

(ii) Design, select, use, and maintain respirators in conformance with ANSI Z88.2 (as specified in § 250.198).

(iii) Make available at least two voice-transmission devices, which can be used while wearing a respirator, for use by designated personnel.

(iv) Make spectacle kits available as needed.

(v) Store protective-breathing equipment in a location that is quickly and easily accessible to all personnel.

(vi) Label all breathing-air bottles as containing breathing-quality air for human use.

(vii) Ensure that vessels attendant to facilities carry appropriate protective-breathing equipment for each crew member. The District Manager may require additional protective-breathing equipment on certain vessels attendant to the facility.

(viii) During H2S alerts, limit helicopter flights to and from facilities to the conditions specified in the H2S Contingency Plan. During authorized flights, the flight crew and passengers must use pressure-demand-type respirators. You must train all members of flight crews in the use of the particular type(s) of respirator equipment made available.

(ix) As appropriate to the particular operation(s), (production, drilling, well-completion or well-workover operations, or any combination of them), provide a system of breathing-air manifolds, hoses, and masks at the facility and the briefing areas. You must provide a cascade air-bottle system for the breathing-air manifolds to refill individual protective-breathing apparatus bottles. The cascade air-bottle system may be recharged by a high-pressure compressor suitable for providing breathing-quality air, provided the compressor suction is located in an uncontaminated atmosphere.

(k) Personnel safety equipment:

(1) What additional personnel-safety equipment do I need? You must ensure that your facility has:

(i) Portable H2S detectors capable of detecting a 10 ppm concentration of H2S in the air available for use by all personnel;

(ii) Retrieval ropes with safety harnesses to retrieve incapacitated personnel from contaminated areas;

(iii) Chalkboards and/or note pads for communication purposes located on the rig floor, shale-shaker area, the cement-pump rooms, well-bay areas, production processing equipment area, gas compressor area, and pipeline-pump area;

(iv) Bull horns and flashing lights; and

(v) At least three resuscitators on manned facilities, and a number equal to the personnel on board, not to exceed three, on normally unmanned facilities, complete with face masks, oxygen bottles, and spare oxygen bottles.

(2) What are the requirements for ventilation equipment? You must:

(i) Use only explosion-proof ventilation devices;

(ii) Install ventilation devices in areas where H2S or SO2 may accumulate; and

(iii) Provide movable ventilation devices in work areas. The movable ventilation devices must be multidirectional and capable of dispersing H2S or SO2 vapors away from working personnel.

(3) What other personnel safety equipment do I need? You must have the following equipment readily available on each facility:

(i) A first-aid kit of appropriate size and content for the number of personnel on the facility; and

(ii) At least one litter or an equivalent device.

(l) Do I need to notify BSEE in the event of an H2S release? You must notify BSEE without delay in the event of a gas release which results in a 15-minute time-weighted average atmospheric concentration of H2S of 20 ppm or more anywhere on the OCS facility. You must report these gas releases to the District Manager immediately by oral communication, with a written follow-up report within 15 days, pursuant to §§ 250.188 through 250.190.

(m) Do I need to use special drilling, completion and workover fluids or procedures? When working in an area classified as H2S present or H2S unknown:

(1) You may use either water- or oil-base muds in accordance with § 250.300(b)(1).

(2) If you use water-base well-control fluids, and if ambient air sensors detect H2S, you must immediately conduct either the Garrett-Gas-Train test or a comparable test for soluble sulfides to confirm the presence of H2S.

(3) If the concentration detected by air sensors in over 20 ppm, personnel conducting the tests must don protective-breathing equipment conforming to paragraph (j)(13) of this section.

(4) You must maintain on the facility sufficient quantities of additives for the control of H2S, well-control fluid pH, and corrosion equipment.

(i) Scavengers. You must have scavengers for control of H2S available on the facility. When H2S is detected, you must add scavengers as needed. You must suspend drilling until the scavenger is circulated throughout the system.

(ii) Control pH. You must add additives for the control of pH to water-base well-control fluids in sufficient quantities to maintain pH of at least 10.0.

(iii) Corrosion inhibitors. You must add additives to the well-control fluid system as needed for the control of corrosion.

(5) You must degas well-control fluids containing H2S at the optimum location for the particular facility. You must collect the gases removed and burn them in a closed flare system conforming to paragraph (q)(6) of this section.

(n) What must I do in the event of a kick? In the event of a kick, you must use one of the following alternatives to dispose of the well-influx fluids giving consideration to personnel safety, possible environmental damage, and possible facility well-equipment damage:

(1) Contain the well-fluid influx by shutting in the well and pumping the fluids back into the formation.

(2) Control the kick by using appropriate well-control techniques to prevent formation fracturing in an open hole within the pressure limits of the well equipment (drill pipe, work string, casing, wellhead, BOP system, and related equipment). The disposal of H2S and other gases must be through pressurized or atmospheric mud-separator equipment depending on volume, pressure and concentration of H2S. The equipment must be designed to recover well-control fluids and burn the gases separated from the well-control fluid. The well-control fluid must be treated to neutralize H2S and restore and maintain the proper quality.

(o) Well testing in a zone known to contain H2S. When testing a well in a zone with H2S present, you must do all of the following:

(1) Before starting a well test, conduct safety meetings for all personnel who will be on the facility during the test. At the meetings, emphasize the use of protective-breathing equipment, first-aid procedures, and the Contingency Plan. Only competent personnel who are trained and are knowledgeable of the hazardous effects of H2S must be engaged in these tests.

(2) Perform well testing with the minimum number of personnel in the immediate vicinity of the rig floor and with the appropriate test equipment to safely and adequately perform the test. During the test, you must continuously monitor H2S levels.

(3) Not burn produced gases except through a flare which meets the requirements of paragraph (q)(6) of this section. Before flaring gas containing H2S, you must activate SO2 monitoring equipment in accordance with paragraph (j)(11) of this section. If you detect SO2 in excess of 2 ppm, you must implement the personnel protective measures in your H2S Contingency Plan, required by paragraph (f) of this section. You must also follow the requirements of § 250.1164. You must pipe gases from stored test fluids into the flare outlet and burn them.

(4) Use downhole test tools and wellhead equipment suitable for H2S service.

(5) Use tubulars suitable for H2S service. You must not use drill pipe for well testing without the prior approval of the District Manager. Water cushions must be thoroughly inhibited in order to prevent H2S attack on metals. You must flush the test string fluid treated for this purpose after completion of the test.

(6) Use surface test units and related equipment that is designed for H2S service.

(p) Metallurgical properties of equipment. When operating in a zone with H2S present, you must use equipment that is constructed of materials with metallurgical properties that resist or prevent sulfide stress cracking (also known as hydrogen embrittlement, stress corrosion cracking, or H2S embrittlement), chloride-stress cracking, hydrogen-induced cracking, and other failure modes. You must do all of the following:

(1) Use tubulars and other equipment, casing, tubing, drill pipe, couplings, flanges, and related equipment that is designed for H2S service.

(2) Use BOP system components, wellhead, pressure-control equipment, and related equipment exposed to H2S-bearing fluids in conformance with NACE Standard MR0175-03 (as specified in § 250.198).

(3) Use temporary downhole well-security devices such as retrievable packers and bridge plugs that are designed for H2S service.

(4) When producing in zones bearing H2S, use equipment constructed of materials capable of resisting or preventing sulfide stress cracking.

(5) Keep the use of welding to a minimum during the installation or modification of a production facility. Welding must be done in a manner that ensures resistance to sulfide stress cracking.

(q) General requirements when operating in an H2S zone:

(1) Coring operations. When you conduct coring operations in H2S-bearing zones, all personnel in the working area must wear protective-breathing equipment at least 10 stands in advance of retrieving the core barrel. Cores to be transported must be sealed and marked for the presence of H2S.

(2) Logging operations. You must treat and condition well-control fluid in use for logging operations to minimize the effects of H2S on the logging equipment.

(3) Stripping operations. Personnel must monitor displaced well-control fluid returns and wear protective-breathing equipment in the working area when the atmospheric concentration of H2S reaches 20 ppm or if the well is under pressure.

(4) Gas-cut well-control fluid or well kick from H2S-bearing zone. If you decide to circulate out a kick, personnel in the working area during bottoms-up and extended-kill operations must wear protective-breathing equipment.

(5) Drill- and workover-string design and precautions. Drill- and workover-strings must be designed consistent with the anticipated depth, conditions of the hole, and reservoir environment to be encountered. You must minimize exposure of the drill- or workover-string to high stresses as much as practical and consistent with well conditions. Proper handling techniques must be taken to minimize notching and stress concentrations. Precautions must be taken to minimize stresses caused by doglegs, improper stiffness ratios, improper torque, whip, abrasive wear on tool joints, and joint imbalance.

(6) Flare system. The flare outlet must be of a diameter that allows easy nonrestricted flow of gas. You must locate flare line outlets on the downside of the facility and as far from the facility as is feasible, taking into account the prevailing wind directions, the wake effects caused by the facility and adjacent structure(s), and the height of all such facilities and structures. You must equip the flare outlet with an automatic ignition system including a pilot-light gas source or an equivalent system. You must have alternate methods for igniting the flare. You must pipe to the flare system used for H2S all vents from production process equipment, tanks, relief valves, burst plates, and similar devices.

(7) Corrosion mitigation. You must use effective means of monitoring and controlling corrosion caused by acid gases (H2S and CO2) in both the downhole and surface portions of a production system. You must take specific corrosion monitoring and mitigating measures in areas of unusually severe corrosion where accumulation of water and/or higher concentration of H2S exists.

(8) Wireline lubricators. Lubricators which may be exposed to fluids containing H2S must be of H2S-resistant materials.

(9) Fuel and/or instrument gas. You must not use gas containing H2S for instrument gas. You must not use gas containing H2S for fuel gas without the prior approval of the District Manager.

(10) Sensing lines and devices. Metals used for sensing line and safety-control devices which are necessarily exposed to H2S-bearing fluids must be constructed of H2S-corrosion resistant materials or coated so as to resist H2S corrosion.

(11) Elastomer seals. You must use H2S-resistant materials for all seals which may be exposed to fluids containing H2S.

(12) Water disposal. If you dispose of produced water by means other than subsurface injection, you must submit to the District Manager an analysis of the anticipated H2S content of the water at the final treatment vessel and at the discharge point. The District Manager may require that the water be treated for removal of H2S. The District Manager may require the submittal of an updated analysis if the water disposal rate or the potential H2S content increases.

(13) Deck drains. You must equip open deck drains with traps or similar devices to prevent the escape of H2S gas into the atmosphere.

(14) Sealed voids. You must take precautions to eliminate sealed spaces in piping designs (e.g., slip-on flanges, reinforcing pads) which can be invaded by atomic hydrogen when H2S is present.

Subpart E - Oil and Gas Well-Completion Operations
§ 250.500 General requirements.

Well-completion operations must be conducted in a manner to protect against harm or damage to life (including fish and other aquatic life), property, natural resources of the OCS, including any mineral deposits (in areas leased and not leased), the National security or defense, or the marine, coastal, or human environment. In addition to the requirements of this subpart, you must also follow the applicable requirements of subpart G of this part.

[81 FR 26021, Apr. 29, 2016]

§ 250.501 Definition.

When used in this subpart, the following term shall have the meaning given below:

Well-completion operations means the work conducted to establish the production of a well after the production-casing string has been set, cemented, and pressure-tested.

§ 250.502 [Reserved]
§ 250.503 Emergency shutdown system.

When well-completion operations are conducted on a platform where there are other hydrocarbon-producing wells or other hydrocarbon flow, an emergency shutdown system (ESD) manually controlled station shall be installed near the driller's console or well-servicing unit operator's work station.

§ 250.504 Hydrogen sulfide.

When a well-completion operation is conducted in zones known to contain hydrogen sulfide (H2S) or in zones where the presence of H2S is unknown (as defined in § 250.490 of this part), the lessee shall take appropriate precautions to protect life and property on the platform or completion unit, including, but not limited to operations such as blowing the well down, dismantling wellhead equipment and flow lines, circulating the well, swabbing, and pulling tubing, pumps, and packers. The lessee shall comply with the requirements in § 250.490 of this part as well as the appropriate requirements of this subpart.

§ 250.505 Subsea completions.

No subsea well completion shall be commenced until the lessee obtains written approval from the District Manager in accordance with § 250.513 of this part. That approval shall be based upon a case-by-case determination that the proposed equipment and procedures will adequately control the well and permit safe production operations.

§§ 250.506-250.508 [Reserved]
§ 250.509 Well-completion structures on fixed platforms.

Derricks, masts, substructures, and related equipment shall be selected, designed, installed, used, and maintained so as to be adequate for the potential loads and conditions of loading that may be encountered during the proposed operations. Prior to moving a well-completion rig or equipment onto a platform, the lessee shall determine the structural capability of the platform to safely support the equipment and proposed operations, taking into consideration the corrosion protection, age of platform, and previous stresses to the platform.

§ 250.510 Diesel engine air intakes.

Diesel engine air intakes must be equipped with a device to shut down the diesel engine in the event of runaway. Diesel engines that are continuously attended must be equipped with either remote operated manual or automatic-shutdown devices. Diesel engines that are not continuously attended must be equipped with automatic-shutdown devices.

§ 250.511 Traveling-block safety device.

All units being used for well-completion operations that have both a traveling block and a crown block must be equipped with a safety device that is designed to prevent the traveling block from striking the crown block. The device must be checked for proper operation weekly and after each drill-line slipping operation. The results of the operational check must be entered in the operations log.

§ 250.512 Field well-completion rules.

When geological and engineering information available in a field enables the District Manager to determine specific operating requirements, field well-completion rules may be established on the District Manager's initiative or in response to a request from a lessee. Such rules may modify the specific requirements of this subpart. After field well-completion rules have been established, well-completion operations in the field shall be conducted in accordance with such rules and other requirements of this subpart. Field well-completion rules may be amended or canceled for cause at any time upon the initiative of the District Manager or upon the request of a lessee.

§ 250.513 Approval and reporting of well-completion operations.

(a) No well-completion operation may begin until the lessee receives written approval from the District Manager. If completion is planned and the data are available at the time you submit the Application for Permit to Drill and Supplemental APD Information Sheet (Forms BSEE-0123 and BSEE-0123S), you may request approval for a well-completion on those forms (see §§ 250.410 through 250.418 of this part). If the District Manager has not approved the completion or if the completion objective or plans have significantly changed, you must submit an Application for Permit to Modify (Form BSEE-0124) for approval of such operations.

(b) You must submit the following with Form BSEE-0124 (or with Form BSEE-0123; Form BSEE-0123S):

(1) A brief description of the well-completion procedures to be followed, a statement of the expected surface pressure, and type and weight of completion fluids;

(2) A schematic drawing of the well showing the proposed producing zone(s) and the subsurface well-completion equipment to be used;

(3) For multiple completions, a partial electric log showing the zones proposed for completion, if logs have not been previously submitted;

(4) All applicable information required in § 250.731.

(5) When the well-completion is in a zone known to contain H2S or a zone where the presence of H2S is unknown, information pursuant to § 250.490 of this part; and

(6) Payment of the service fee listed in § 250.125.

(c) Within 30 days after completion, you must submit to the District Manager an End of Operations Report (Form BSEE-0125), including a schematic of the tubing and subsurface equipment.

(d) You must submit public information copies of Form BSEE-0125 according to § 250.186.

[76 FR 64462, Oct. 18, 2011, as amended at 77 FR 50894, Aug. 22, 2012; 81 FR 26021, Apr. 29, 2016]

§ 250.514 Well-control fluids, equipment, and operations.

(a) Well-control fluids, equipment, and operations shall be designed, utilized, maintained, and/or tested as necessary to control the well in foreseeable conditions and circumstances, including subfreezing conditions. The well shall be continuously monitored during well-completion operations and shall not be left unattended at any time unless the well is shut in and secured.

(b) The following well-control-fluid equipment shall be installed, maintained, and utilized:

(1) A fill-up line above the uppermost BOP;

(2) A well-control, fluid-volume measuring device for determining fluid volumes when filling the hole on trips; and

(3) A recording mud-pit-level indicator to determine mud-pit-volume gains and losses. This indicator shall include both a visual and an audible warning device.

(c) When coming out of the hole with drill pipe, the annulus shall be filled with well-control fluid before the change in such fluid level decreases the hydrostatic pressure 75 pounds per square inch (psi) or every five stands of drill pipe, whichever gives a lower decrease in hydrostatic pressure. The number of stands of drill pipe and drill collars that may be pulled prior to filling the hole and the equivalent well-control fluid volume shall be calculated and posted near the operator's station. A mechanical, volumetric, or electronic device for measuring the amount of well-control fluid required to fill the hole shall be utilized.

[76 FR 64462, Oct. 18, 2011, as amended at 77 FR 50894, Aug. 22, 2012; 81 FR 26021, Apr. 29, 2016]

§§ 250.515-250.517 [Reserved]
§ 250.518 Tubing and wellhead equipment.

(a) No tubing string shall be placed in service or continue to be used unless such tubing string has the necessary strength and pressure integrity and is otherwise suitable for its intended use.

(b) When the tree is installed, you must equip wells to monitor for casing pressure according to the following chart:

If you . . . you must equip . . . so you can monitor . . .
(1) fixed platform wells, the wellhead, all annuli (A, B, C, D, etc., annuli).
(2) subsea wells, the tubing head, the production casing annulus (A annulus).
(3) hybrid * wells, the surface wellhead, all annuli at the surface (A and B riser annuli). If the production casing below the mudline and the production casing riser above the mudline are pressure isolated from each other, provisions must be made to monitor the production casing below the mudline for casing pressure.

(c) Wellhead, tree, and related equipment shall have a pressure rating greater than the shut-in tubing pressure and shall be designed, installed, used, maintained, and tested so as to achieve and maintain pressure control. New wells completed as flowing or gas-lift wells shall be equipped with a minimum of one master valve and one surface safety valve, installed above the master valve, in the vertical run of the tree.

(d) Subsurface safety equipment must be installed, maintained, and tested in compliance with the applicable sections in §§ 250.810 through 250.839.

(e) When installed, packers and bridge plugs must meet the following:

(1) The uppermost permanently installed packer and all permanently installed bridge plugs qualified as mechanical barriers must comply with ANSI/API Spec. 11D1 (as incorporated by reference in § 250.198);

(2) The production packer must be set at a depth that will allow for a column of weighted fluids to be placed above the packer that will exert a hydrostatic force greater than or equal to the force created by the reservoir pressure below the packer;

(3) The production packer must be set as close as practically possible to the perforated interval; and

(4) The production packer must be set at a depth that is within the cemented interval of the selected casing section.

(f) Your APM must include a description and calculations for how you determined the production packer setting depth.

(g) You must have two independent barriers, one being mechanical, in the exposed center wellbore prior to removing the tree and/or well control equipment.

[76 FR 64462, Oct. 18, 2011. Redesignated at 77 FR 50894, Aug. 22, 2012, as amended at 81 FR 26021, Apr. 29, 2016; 81 FR 61918, Sept. 7, 2016; 84 FR 21976, May 15, 2019]

Casing Pressure Management
§ 250.519 What are the requirements for casing pressure management?

Once you install your wellhead, you must meet the casing pressure management requirements of API RP 90 (as incorporated by reference in § 250.198) and the requirements of §§ 250.519 through 250.531. If there is a conflict between API RP 90 and the casing pressure requirements of this subpart, you must follow the requirements of this subpart.

[84 FR 21976, May 15, 2019]

§ 250.520 How often do I have to monitor for casing pressure?

You must monitor for casing pressure in your well according to the following table:

If you have . . . you must monitor . . . with a minimum one pressure data point recorded per . . .
(a) fixed platform wells, monthly, month for each casing.
(b) subsea wells, continuously, day for the production casing.
(c) hybrid wells, continuously, day for each riser and/or the production casing.
(d) wells operating under a casing pressure request on a manned fixed platform, daily, day for each casing.
(e) wells operating under a casing pressure request on an unmanned fixed platform, weekly, week for each casing.

[76 FR 64462, Oct. 18, 2011. Redesignated at 77 FR 50894, Aug. 22, 2012]

§ 250.521 When do I have to perform a casing diagnostic test?

(a) You must perform a casing diagnostic test within 30 days after first observing or imposing casing pressure according to the following table:

If you have a . . . you must perform a casing diagnostic test if . . .
(1) fixed platform well, the casing pressure is greater than 100 psig.
(2) subsea well, the measurable casing pressure is greater than the external hydrostatic pressure plus 100 psig measured at the subsea wellhead.
(3) hybrid well, a riser or the production casing pressure is greater than 100 psig measured at the surface.

(b) You are exempt from performing a diagnostic pressure test for the production casing on a well operating under active gas lift.

[76 FR 64462, Oct. 18, 2011. Redesignated at 77 FR 50894, Aug. 22, 2012]

§ 250.522 How do I manage the thermal effects caused by initial production on a newly completed or recompleted well?

A newly completed or recompleted well often has thermal casing pressure during initial startup. Bleeding casing pressure during the startup process is considered a normal and necessary operation to manage thermal casing pressure; therefore, you do not need to evaluate these operations as a casing diagnostic test. After 30 days of continuous production, the initial production startup operation is complete and you must perform casing diagnostic testing as required in §§ 250.521 and 250.523.

[84 FR 21976, May 15, 2019]

§ 250.523 When do I have to repeat casing diagnostic testing?

Casing diagnostic testing must be repeated according to the following table:

When . . . you must repeat diagnostic testing . . .
(a) your casing pressure request approved term has expired, immediately.
(b) your well, previously on gas lift, has been shut-in or returned to flowing status without gas lift for more than 180 days, immediately on the production casing (A annulus). The production casing (A annulus) of wells on active gas lift are exempt from diagnostic testing.
(c) your casing pressure request becomes invalid, within 30 days.
(d) a casing or riser has an increase in pressure greater than 200 psig over the previous casing diagnostic test, within 30 days.
(e) after any corrective action has been taken to remediate undesirable casing pressure, either as a result of a casing pressure request denial or any other action, within 30 days.
(f) your fixed platform well production casing (A annulus) has pressure exceeding 10 percent of its minimum internal yield pressure (MIYP), except for production casings on active gas lift, once per year, not to exceed 12 months between tests.
(g) your fixed platform well's outer casing (B, C, D, etc., annuli) has a pressure exceeding 20 percent of its MIYP, once every 5 years, at a minimum.

[76 FR 64462, Oct. 18, 2011. Redesignated at 77 FR 50894, Aug. 22, 2012]

§ 250.524 How long do I keep records of casing pressure and diagnostic tests?

Records of casing pressure and diagnostic tests must be kept at the field office nearest the well for a minimum of 2 years. The last casing diagnostic test for each casing or riser must be retained at the field office nearest the well until the well is abandoned.

[76 FR 64462, Oct. 18, 2011. Redesignated at 77 FR 50894, Aug. 22, 2012]

§ 250.525 When am I required to take action from my casing diagnostic test?

You must take action if you have any of the following conditions:

(a) Any fixed platform well with a casing pressure exceeding its maximum allowable wellhead operating pressure (MAWOP);

(b) Any fixed platform well with a casing pressure that is greater than 100 psig and that cannot bleed to 0 psig through a1/2-inch needle valve within 24 hours, or is not bled to 0 psig during a casing diagnostic test;

(c) Any well that has demonstrated tubing/casing, tubing/riser, casing/casing, riser/casing, or riser/riser communication;

(d) Any well that has sustained casing pressure (SCP) and is bled down to prevent it from exceeding its MAWOP, except during initial startup operations described in § 250.522;

(e) Any hybrid well with casing or riser pressure exceeding 100 psig; or

(f) Any subsea well with a casing pressure 100 psig greater than the external hydrostatic pressure at the subsea wellhead.

[76 FR 64462, Oct. 18, 2011. Redesignated at 77 FR 50894, Aug. 22, 2012; 84 FR 21976, May 15, 2019]

§ 250.526 What do I submit if my casing diagnostic test requires action?

Within 14 days after you perform a casing diagnostic test requiring action under § 250.525:

You must submit either . . . to the appropriate . . . and it must include . . . You must also . . .
(a) a notification of corrective action; or, District Manager and copy the Regional Supervisor, Field Operations, requirements under § 250.527, submit an Application for Permit to Modify or Corrective Action Plan within 30 days of the diagnostic test.
(b) a casing pressure request, Regional Supervisor, Field Operations, requirements under § 250.528.

[84 FR 21976, May 15, 2019]

§ 250.527 What must I include in my notification of corrective action?

The following information must be included in the notification of corrective action:

(a) Lessee or Operator name;

(b) Area name and OCS block number;

(c) Well name and API number; and

(d) Casing diagnostic test data.

[76 FR 64462, Oct. 18, 2011. Redesignated at 77 FR 50894, Aug. 22, 2012]

§ 250.528 What must I include in my casing pressure request?

The following information must be included in the casing pressure request:

(a) API number;

(b) Lease number;

(c) Area name and OCS block number;

(d) Well number;

(e) Company name and mailing address;

(f) All casing, riser, and tubing sizes, weights, grades, and MIYP;

(g) All casing/riser calculated MAWOPs;

(h) All casing/riser pre-bleed down pressures;

(i) Shut-in tubing pressure;

(j) Flowing tubing pressure;

(k) Date and the calculated daily production rate during last well test (oil, gas, basic sediment, and water);

(l) Well status (shut-in, temporarily abandoned, producing, injecting, or gas lift);

(m) Well type (dry tree, hybrid, or subsea);

(n) Date of diagnostic test;

(o) Well schematic;

(p) Water depth;

(q) Volumes and types of fluid bled from each casing or riser evaluated;

(r) Type of diagnostic test performed:

(1) Bleed down/buildup test;

(2) Shut-in the well and monitor the pressure drop test;

(3) Constant production rate and decrease the annular pressure test;

(4) Constant production rate and increase the annular pressure test;

(5) Change the production rate and monitor the casing pressure test; and

(6) Casing pressure and tubing pressure history plot;

(s) The casing diagnostic test data for all casing exceeding 100 psig;

(t) Associated shoe strengths for casing shoes exposed to annular fluids;

(u) Concentration of any H2S that may be present;

(v) Whether the structure on which the well is located is manned or unmanned;

(w) Additional comments; and

(x) Request date.

[76 FR 64462, Oct. 18, 2011. Redesignated at 77 FR 50894, Aug. 22, 2012]

§ 250.529 What are the terms of my casing pressure request?

Casing pressure requests are approved by the Regional Supervisor, Field Operations, for a term to be determined by the Regional Supervisor on a case-by-case basis. The Regional Supervisor may impose additional restrictions or requirements to allow continued operation of the well.

[76 FR 64462, Oct. 18, 2011. Redesignated at 77 FR 50894, Aug. 22, 2012]

§ 250.530 What if my casing pressure request is denied?