The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

§ 157.22 Schedule for final decisions on a request for a Federal authorization.

(a) For an application under section 3 or 7 of the Natural Gas Act that requires a Federal authorization—i.e., a permit, special use authorization, certification, opinion, or other approval—from a Federal agency or officer, or State agency or officer acting pursuant to delegated Federal authority, a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law.

(b) For requests for a water quality certification submitted pursuant to section 401(a)(1) of the Federal Water Pollution Control Act (Clean Water Act) in connection with a project for which authorization is sought from the Commission under section 3 or 7 of the Natural Gas Act, the reasonable period of time during which the certifying agency may act on the water quality certification request is one year from the certifying agency's receipt of the request. A certifying agency is deemed to have waived the certification requirements of section 401(a)(1) of the Clean Water Act if the certifying agency has not denied or granted certification by one year after the date the certifying agency received a written request for certification.

[86 FR 16302, Mar. 29, 2021]