The Code of Federal Regulations (CFR) is the official legal print publication containing the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government. The Electronic Code of Federal Regulations (eCFR) is a continuously updated online version of the CFR. It is not an official legal edition of the CFR.

Learn more about the eCFR, its status, and the editorial process.

§ 830.207 DOE approval of safety basis.

(a) With respect to a new Hazard Category 1, 2, or 3 DOE nuclear facility or a major modification to an existing Hazard Category 1, 2, or 3 DOE nuclear facility, a contractor may not begin operation of the facility or modification prior to the issuance of a safety evaluation report in which DOE approves the safety basis for the facility or modification.

(b) Pending issuance of a safety evaluation report in which DOE approves an updated or amended safety basis for an existing Hazard Category 1, 2, or 3 DOE nuclear facility, the contractor responsible for the facility must continue to perform work in accordance with the DOE-approved safety basis for the facility and maintain the existing safety basis consistent with the requirements of this Subpart.