e-CFR data is current as of March 5, 2021 |
Title 33 → Chapter I → Subchapter NN → Part 148 → Subpart C → Subject Group |
Title 33: Navigation and Navigable Waters
PART 148—DEEPWATER PORTS: GENERAL
Subpart C—Processing Applications
(a) In 33 U.S.C. 1504, the Act provides strict timelines for action on a license application, which, if closely observed, can lead to action in just under 1 year. The Coast Guard, in concurrence with MARAD, can suspend the process if an applicant fails to provide timely information or requests additional time to comply with a request.
(b) The Coast Guard must conduct public hearings in each Adjacent Coastal State within 240 days of publishing the notice of receipt of a deepwater port license application.
(c) MARAD issues a Record of Decision (ROD) approving or denying a license application within 90 days after the final public hearing. Actual issuance of a license may not take place until certain conditions imposed by the ROD have been met. Those conditions may include how the applicant must address design, construction, installation, testing, operations, and decommissioning of the deepwater port, or meet the requirements of other agencies.
[USCG-1998-3884, 71 FR 57651, Sept. 29, 2006, as amended by USCG-2013-0397, 78 FR 39177, July 1, 2013]
(a) Under §148.209 of this part, Federal agencies and Adjacent Coastal States are sent copies of the application. The agencies and States are encouraged to begin submitting their comments at that time.
(b) To be considered, comments from Federal agencies and Adjacent Coastal States must be received by the Commandant (CG-5P) within 45 days after the close of the public hearing period specified in §148.276(b) of this part. Separate comment periods will apply to the review of documents created during the National Environmental Policy Act process. Both the Commandant (CG-5P) and MARAD review the comments received.
(c) Comments should identify problems, if any, and suggest possible solutions.
[USCG-1998-3884, 71 FR 57651, Sept. 29, 2006, as amended by USCG-2013-0397, 78 FR 39177, July 1, 2013]
The criteria for approving or denying a license application appear in 33 U.S.C. 1503.
(a) When more than one application is submitted for a deepwater port in the same application area under 33 U.S.C. 1504(d), only one application is approved. Except as provided in paragraph (b) of this section, applicants receive priority in the following order:
(1) An Adjacent Coastal State or combination of States, political subdivision of the State, or an agency or instrumentality, including a wholly owned corporation of the State;
(2) A person that is:
(i) Not engaged in producing, refining, or marketing oil;
(ii) Not an affiliate of a person engaged in producing, refining, or marketing oil; or
(iii) Not an affiliate of a person engaged in producing, refining, or marketing oil; and then
(3) Any other applicant.
(b) MARAD may also approve one of the proposed deepwater ports if it determines that that deepwater port will best serve the national interest. In making this determination, MARAD considers:
(1) The degree to which each deepwater port will affect the environment, as determined under the review criteria in subpart G to this part;
(2) The differences between the anticipated completion dates of the deepwater ports; and
(3) The differences in costs for construction and operation of the deepwater ports that would be passed on to consumers of oil.
(c) This section does not apply to applications for natural gas deepwater ports.
[USCG-1998-3884, 71 FR 57651, Sept. 29, 2006, as amended by USCG-2013-0397, 78 FR 39177, July 1, 2013]
The Commandant (CG-5P) recommends to MARAD that the application process be suspended before the application is approved or denied if:
(a) All applications are withdrawn before MARAD approves one of them; or
(b) There is only one application; it is incomplete, and the applicant does not respond to a request by the Commandant (CG-5P) for further information, as per §148.107 of this part.
[USCG-1998-3884, 71 FR 57651, Sept. 29, 2006, as amended by USCG-2013-0397, 78 FR 39177, July 1, 2013]