Home
gpo.gov
govinfo.gov

e-CFR Navigation Aids

Browse

Simple Search

Advanced Search

 — Boolean

 — Proximity

 

Search History

Search Tips

Corrections

Latest Updates

User Info

FAQs

Agency List

Incorporation By Reference

eCFR logo

Related Resources

Electronic Code of Federal Regulations

We invite you to try out our new beta eCFR site at https://ecfr.federalregister.gov. We???ve made big changes to make the eCFR easier to use. Be sure to leave feedback using the Help button on the bottom right of each page!

e-CFR data is current as of August 6, 2020

Title 30Chapter IISubchapter BPart 250Subpart K → Subject Group


Title 30: Mineral Resources
PART 250—OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF
Subpart K—Oil and Gas Production Requirements


Well Tests and Surveys

§250.1151   How often must I conduct well production tests?

(a) You must conduct well production tests as shown in the following table:

You must conduct:And you must submit to the Regional Supervisor:
(1) A well-flow potential test on all new, recompleted, or reworked well completions within 30 days of the date of first continuous production,Form BSEE-0126, Well Potential Test Report, along with the supporting data as listed in the table in §250.1167, within 15 days after the end of the test period.
(2) At least one well test during a calendar half-year for each producing completion,Results on Form BSEE-0128, Semiannual Well Test Report, of the most recent well test obtained. This must be submitted within 45 days after the end of the calendar half-year.

(b) You may request an extension from the Regional Supervisor if you cannot submit the results of a semiannual well test within the specified time.

(c) You must submit to the Regional Supervisor an original and two copies of the appropriate form required by paragraph (a) of this section; one of the copies of the form must be a public information copy in accordance with §§250.186 and 250.197, and marked “Public Information.” You must submit two copies of the supporting information as listed in the table in §250.1167 with form BSEE-0126.

§250.1152   How do I conduct well tests?

(a) When you conduct well tests you must:

(1) Recover fluid from the well completion equivalent to the amount of fluid introduced into the formation during completion, recompletion, reworking, or treatment operations before you start a well test;

(2) Produce the well completion under stabilized rate conditions for at least 6 consecutive hours before beginning the test period;

(3) Conduct the test for at least 4 consecutive hours;

(4) Adjust measured gas volumes to the standard conditions of 14.73 pounds per square inch absolute (psia) and 60 °F for all tests; and

(5) Use measured specific gravity values to calculate gas volumes.

(b) You may request approval from the Regional Supervisor to conduct a well test using alternative procedures if you can demonstrate test reliability under those procedures.

(c) The Regional Supervisor may also require you to conduct the following tests and complete them within a specified time period:

(1) A retest or a prolonged test of a well completion if it is determined to be necessary for the proper establishment of a Maximum Production Rate (MPR) or a Maximum Efficient Rate (MER); and

(2) A multipoint back-pressure test to determine the theoretical open-flow potential of a gas well.

(d) A BSEE representative may witness any well test. Upon request, you must provide advance notice to the Regional Supervisor of the times and dates of well tests.

§§250.1153-250.1155   [Reserved]