Home
gpo.gov
govinfo.gov

e-CFR Navigation Aids

Browse

Simple Search

Advanced Search

 — Boolean

 — Proximity

 

Search History

Search Tips

Corrections

Latest Updates

User Info

FAQs

Agency List

Incorporation By Reference

eCFR logo

Related Resources

Electronic Code of Federal Regulations

We invite you to try out our new beta eCFR site at https://ecfr.federalregister.gov. We???ve made big changes to make the eCFR easier to use. Be sure to leave feedback using the Help button on the bottom right of each page!

e-CFR data is current as of August 5, 2020

Title 30Chapter IISubchapter BPart 250Subpart H → Subject Group


Title 30: Mineral Resources
PART 250—OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF
Subpart H—Oil and Gas Production Safety Systems


General Requirements

§250.800   General.

(a) You must design, install, use, maintain, and test production safety equipment in a manner to ensure the safety and protection of the human, marine, and coastal environments. For production safety systems operated in subfreezing climates, you must use equipment and procedures that account for floating ice, icing, and other extreme environmental conditions that may occur in the area. Before you commence production on a new production facility:

(1) BSEE must approve your production safety system application, as required in §250.842.

(2) You must request a preproduction inspection by notifying the District Manager at least 72 hours before you plan to commence initial production, as required under §250.880(a)(1).

(b) For all new production systems on fixed leg platforms, you must comply with API RP 14J (incorporated by reference as specified in §250.198);

(c) For all new floating production systems (FPSs) (e.g., column-stabilized-units (CSUs); floating production, storage and offloading facilities (FPSOs); tension-leg platforms (TLPs); and spars), you must:

(1) Comply with API RP 14J;

(2) Meet the production riser standards of API RP 2RD (incorporated by reference as specified in §250.198), provided that you may not install single bore production risers from floating production facilities;

(3) Design all stationkeeping (i.e., anchoring and mooring) systems for floating production facilities to meet the standards of API RP 2SK and API RP 2SM (both incorporated by reference as specified in §250.198); and

(4) Design stationkeeping (i.e., anchoring and mooring) systems for floating facilities to meet the structural requirements of §§250.900 through 250.921.

(d) If there are any conflicts between the documents incorporated by reference and the requirements of this subpart, you must follow the requirements of this subpart.

(e) You may use alternate procedures or equipment during operations after receiving approval from the District Manager. You must present your proposed alternate procedures or equipment as required by §250.141.

(f) You may apply for a departure from the operating requirements of this subpart as provided by §250.142. Your written request must include a justification showing why the departure is necessary and appropriate.

[81 FR 60918, Sept. 7, 2016, as amended at 83 FR 49256, Sept. 28, 2018]

§250.801   Safety and pollution prevention equipment (SPPE) certification.

(a) SPPE equipment. You must install only safety and pollution prevention equipment (SPPE) considered certified under paragraph (b) of this section or accepted under paragraph (c) of this section. BSEE considers the following equipment to be types of SPPE:

(1) Surface safety valves (SSV) and actuators, including those installed on injection wells capable of natural flow;

(2) Boarding shutdown valves (BSDV) and their actuators. For subsea wells, the BSDV is the surface equivalent of an SSV on a surface well;

(3) Underwater safety valves (USV) and actuators;

(4) Subsurface safety valves (SSSV) and associated safety valve locks and landing nipples; and

(5) Gas lift shutdown valves (GLSDV) and their actuators associated with subsea systems.

(b) Certification of SPPE. SPPE that is manufactured and marked pursuant to ANSI/API Spec. Q1 (incorporated by reference as specified in §250.198), is considered as certified SPPE under this part. All other SPPE is considered as not certified, unless approved in accordance with paragraph (c) of this section.

(c) Accepting SPPE manufactured under other quality assurance programs. BSEE may exercise its discretion to accept SPPE manufactured under a quality assurance program other than ANSI/API Spec. Q1, provided that the alternative quality assurance program is verified as equivalent to API Spec. Q1 by an appropriately qualified entity and that the operator submits a request to BSEE containing relevant information about the alternative program and receives BSEE approval. In addition, an operator may request that BSEE accept SPPE that is marked with a third-party certification mark other than the API monogram. All requests under this paragraph should be submitted to the Chief, Office of Offshore Regulatory Programs; Bureau of Safety and Environmental Enforcement; VAE-ORP; 45600 Woodland Road, Sterling, VA 20166.

[81 FR 60918, Sept. 7, 2016, as amended at 83 FR 49256, Sept. 28, 2018]

§250.802   Requirements for SPPE.

(a) All SSVs, BSDVs, USVs, and GLSDVs and their actuators must meet all of the specifications contained in ANSI/API Spec. 6A and API Spec. 6AV1 (both incorporated by reference in §250.198).

(b) All SSSVs and their actuators must meet all of the specifications and recommended practices of ANSI/API Spec. 14A and ANSI/API RP 14B, including all annexes (both incorporated by reference as specified in §250.198). Subsurface-controlled SSSVs are not allowed on subsea wells.

(c) Requirements derived from the documents incorporated in this section for SSVs, BSDVs, SSSVs, USVs, GLSDVs, and their actuators, include, but are not limited to, the following:

(1) You must ensure that each device is designed to function in the conditions to which it may be exposed; including temperature, pressure, flow rates, and environmental conditions.

(i) The device design must be tested by an independent test agency according to the test requirements in the appropriate standard for that device (API Spec. 6AV1 or ANSI/API Spec. 14A), as identified in paragraphs (a) and (b) of this section.

(ii) You must maintain a description of the process you used to ensure the device is designed to function as required in paragraphs (a) and (c)(1) of this section and provide that description to BSEE upon request.

(iii) If you remove any SPPE from service and install the device at a different location, you must have a qualified third party review and certify that each device will function as designed under the conditions to which it may be exposed.

(2) All materials and parts must meet the original equipment manufacturer specifications and acceptance criteria.

(3) The device must pass applicable validation tests and functional tests performed by an API-licensed test agency.

(4) You must have requalification testing performed following manufacture design changes.

(5) You must comply with and document all manufacturing, traceability, quality control, and inspection requirements.

(6) You must follow specified installation, testing, and repair protocols.

(7) You must use only qualified parts, procedures, and personnel to repair or redress equipment.

(d) You must install and use SPPE according to the following table.

If .  .  .Then .  .  .
(1) You need to install any SPPEYou must install SPPE that conforms to §250.801.
(2) A non-certified SPPE is already in serviceIt may remain in service.
(3) A non-certified SPPE requires offsite repair, re-manufacturing, or any hot work such as weldingYou must replace it with SPPE that conforms to §250.801.

(e) You must retain all documentation related to the manufacture, installation, testing, repair, redress, and performance of the SPPE until 1 year after the date of decommissioning of the equipment.

[81 FR 60918, Sept. 7, 2016, as amended at 83 FR 49256, Sept. 28, 2018]

§250.803   What SPPE failure reporting procedures must I follow?

(a) You must follow the failure reporting requirements contained in section 10.20.7.4 of ANSI/API Spec. 6A for SSVs, BSDVs, GLSDVs and USVs. You must follow the failure reporting requirements contained in section 7.10 of ANSI/API Spec. 14A and Annex F of ANSI/API RP 14B for SSSVs (all incorporated by reference in §250.198). Within 30 days after the discovery and identification of the failure, you must provide a written notice of equipment failure to the manufacturer of such equipment and to BSEE through the Chief, Office of Offshore Regulatory Programs, unless BSEE has designated a third party as provided in paragraph (d) of this section. A failure is any condition that prevents the equipment from meeting the functional specification or purpose.

(b) You must ensure that an investigation and a failure analysis are performed within 120 days of the failure to determine the cause of the failure. If the investigation and analyses are performed by an entity other than the manufacturer, you must ensure that the analysis report is submitted to the manufacturer and to BSEE through the Chief, Office of Offshore Regulatory Programs, unless BSEE has designated a third party as provided in paragraph (d) of this section. You must also ensure that the results of the investigation and any corrective action are documented in the analysis report.

(c) If the equipment manufacturer notifies you that it has changed the design of the equipment that failed or if you have changed operating or repair procedures as a result of a failure, then you must, within 30 days of such changes, report the design change or modified procedures in writing to BSEE through the Chief, Office of Offshore Regulatory Programs, unless BSEE has designated a third party as provided in paragraph (d) of this section.

(d) BSEE may designate a third party to receive the data required by paragraphs (a) through (c) of this section on behalf of BSEE. If BSEE designates a third party, you must submit the information required in this section to the designated third party, as directed by BSEE.

[83 FR 49256, Sept. 28, 2018]

§250.804   Additional requirements for subsurface safety valves (SSSVs) and related equipment installed in high pressure high temperature (HPHT) environments.

(a) If you plan to install SSSVs and related equipment in an HPHT environment, you must submit detailed information with your Application for Permit to Drill (APD) or Application for Permit to Modify (APM), and Deepwater Operations Plan (DWOP) that demonstrates the SSSVs and related equipment are capable of performing in the applicable HPHT environment. Your detailed information must include the following:

(1) A discussion of the SSSVs' and related equipment's design verification analyses;

(2) A discussion of the SSSVs' and related equipment's design validation and functional testing processes and procedures used; and

(3) An explanation of why the analyses, processes, and procedures ensure that the SSSVs and related equipment are fit-for-service in the applicable HPHT environment.

(b) For this section, HPHT environment means when one or more of the following well conditions exist:

(1) The completion of the well requires completion equipment or well control equipment assigned a pressure rating greater than 15,000 psia or a temperature rating greater than 350 degrees Fahrenheit;

(2) The maximum anticipated surface pressure or shut-in tubing pressure is greater than 15,000 psia on the seafloor for a well with a subsea wellhead or at the surface for a well with a surface wellhead; or

(3) The flowing temperature is equal to or greater than 350 degrees Fahrenheit on the seafloor for a well with a subsea wellhead or at the surface for a well with a surface wellhead.

(c) For this section, related equipment includes wellheads, tubing heads, tubulars, packers, threaded connections, seals, seal assemblies, production trees, chokes, well control equipment, and any other equipment that will be exposed to the HPHT environment.

§250.805   Hydrogen sulfide.

(a) In zones known to contain hydrogen sulfide (H2S) or in zones where the presence of H2S is unknown, as defined in §250.490, you must conduct production operations in accordance with that section and other relevant requirements of this subpart.

(b) You must receive approval through the DWOP process (§§250.286 through 250.295) for production operations in HPHT environments known to contain H2S or in HPHT environments where the presence of H2S is unknown.

§§250.806-250.809   [Reserved]2