Home
gpo.gov
govinfo.gov

e-CFR Navigation Aids

Browse

Simple Search

Advanced Search

 — Boolean

 — Proximity

 

Search History

Search Tips

Corrections

Latest Updates

User Info

FAQs

Agency List

Incorporation By Reference

eCFR logo

Related Resources

Electronic Code of Federal Regulations

We invite you to try out our new beta eCFR site at https://ecfr.federalregister.gov. We have made big changes to make the eCFR easier to use. Be sure to leave feedback using the Feedback button on the bottom right of each page!

e-CFR data is current as of January 15, 2021

Title 48Chapter 1Subchapter DPart 25Subpart 25.2 → §25.204


Title 48: Federal Acquisition Regulations System
PART 25—FOREIGN ACQUISITION
Subpart 25.2—Buy American—Construction Materials


25.204   Evaluating offers of foreign construction material.

(a) Offerors proposing to use foreign construction material other than that listed by the Government in the applicable clause at 52.225-9, paragraph (b)(2), or 52.225-11, paragraph (b)(3), or covered by the WTO GPA or a Free Trade Agreement (paragraph (b)(2) of 52.225-11), must provide the information required by paragraphs (c) and (d) of the respective clauses.

(b) Unless the head of the agency specifies a higher percentage, the contracting officer must add to the offered price 6 percent of the cost of any foreign construction material proposed for exception from the requirements of the Buy American statute based on the unreasonable cost of domestic construction materials. In the case of a tie, the contracting officer must give preference to an offer that does not include foreign construction material excepted at the request of the offeror on the basis of unreasonable cost.

(c) Offerors also may submit alternate offers based on use of equivalent domestic construction material to avoid possible rejection of the entire offer if the Government determines that an exception permitting use of a particular foreign construction material does not apply.

(d) If the contracting officer awards a contract to an offeror that proposed foreign construction material not listed in the applicable clause in the solicitation (paragraph (b)(2) of 52.225-9, or paragraph (b)(3) of 52.225-11), the contracting officer must add the excepted materials to the list in the contract clause.

[64 FR 72419, Dec. 27, 1999, as amended at 69 FR 1053, Jan. 7, 2004; 69 FR 77873, Dec. 28, 2004; 79 FR 24209, Apr. 29, 2014]