e-CFR data is current as of January 19, 2021 |
Title 43 → Subtitle B → Chapter II → Subchapter C → Part 3836 → Subpart B → §3836.22 |
Title 43: Public Lands: Interior
PART 3836—ANNUAL ASSESSMENT WORK REQUIREMENTS FOR MINING CLAIMS
Subpart B—Deferring Assessment Work
Correspondence from NPS merely denying your Plan of Operations for incompleteness or inadequacy will not suffice for a deferment of assessment work. To qualify for a deferment of assessment work on claims situated on NPS lands—
(a) You must obtain a letter from NPS stating that—
(1) NPS received and found your proposed Plan of Operations to be complete;
(2) NPS cannot act on the plan until it conducts a validity exam; and
(3) NPS anticipates completing the validity exam after the assessment year ends.
(b) You must send NPS's letter to BLM, along with other documents and information that BLM requires (see §3836.23) to support your petition for deferment of assessment work.