Home
gpo.gov
govinfo.gov

e-CFR Navigation Aids

Browse

Simple Search

Advanced Search

 — Boolean

 — Proximity

 

Search History

Search Tips

Corrections

Latest Updates

User Info

FAQs

Agency List

Incorporation By Reference

eCFR logo

Related Resources

Electronic Code of Federal Regulations

We invite you to try out our new beta eCFR site at https://ecfr.federalregister.gov. We have made big changes to make the eCFR easier to use. Be sure to leave feedback using the Help button on the bottom right of each page!

e-CFR data is current as of October 21, 2020

Title 36Chapter IIPart 228Subpart C → §228.53


Title 36: Parks, Forests, and Public Property
PART 228—MINERALS
Subpart C—Disposal of Mineral Materials


§228.53   Term.

(a) Time allowed. Except as provided in §228.61(f), §228.62(b), and elsewhere in this paragraph, a contract or permit may not exceed 1 year from the effective date of the contract or permit unless a written extension is obtained. For those mineral materials sold under a duration of production contract or under a contract for the sale of all mineral material within a specified area, or under a construction contract where removal cannot reasonably take place before completion of other work under the same contract, the authorized officer will establish a reasonable time period for removal.

(b) Extension of time. If it is shown that a delay in removal was due to causes beyond the control of the purchaser or permittee, the authorized officer may grant an extension, not to exceed 1 year, upon written request. Written requests for extensions of contracts must be received between 30 and 90 days before the expiration date of the contract. Written requests for extensions of permits must be received between 15 and 90 days before the permit expiration date. The authorized officer may grant a total of two extensions for contracts and permits.