Home
gpo.gov
govinfo.gov

e-CFR Navigation Aids

Browse

Simple Search

Advanced Search

 — Boolean

 — Proximity

 

Search History

Search Tips

Corrections

Latest Updates

User Info

FAQs

Agency List

Incorporation By Reference

eCFR logo

Related Resources

Electronic Code of Federal Regulations

We invite you to try out our new beta eCFR site at https://ecfr.federalregister.gov. We have made big changes to make the eCFR easier to use. Be sure to leave feedback using the Help button on the bottom right of each page!

e-CFR data is current as of September 17, 2020

Title 34Subtitle BChapter IIPart 222Subpart L → §222.195


Title 34: Education
PART 222—IMPACT AID PROGRAMS
Subpart L—Impact Aid Discretionary Construction Grant Program Under Section 8007(b) of the Act


§222.195   How does the Secretary make funds available to grantees?

The Secretary makes funds available to a grantee during a project period using the following procedure:

(a) Upon final approval of the grant proposal, the Secretary authorizes a project period of up to 60 months based upon the nature of the grant proposal and the time needed to complete the project.

(b) The Secretary then initially makes available to the grantee 10 percent of the total award amount.

(c) After the grantee submits a copy of the emergency or modernization contract approved by the grantee's governing board, the Secretary makes available 80 percent of the total award amount to a grantee.

(d) The Secretary makes available up to the remaining 10 percent of the total award amount to the grantee after the grantee submits a statement that—

(1) Details any earnings, savings, or interest;

(2) Certifies that—

(i) The project is fully completed; and

(ii) All the awarded funds have been spent for grant purposes; and

(3) Is signed by the—

(i) Chairperson of the governing board;

(ii) Superintendent of schools; and

(iii) Architect of the project.

(Authority: 20 U.S.C. 7707(b))