Home
gpo.gov
govinfo.gov

e-CFR Navigation Aids

Browse

Simple Search

Advanced Search

 — Boolean

 — Proximity

 

Search History

Search Tips

Corrections

Latest Updates

User Info

FAQs

Agency List

Incorporation By Reference

eCFR logo

Related Resources

Electronic Code of Federal Regulations

We invite you to try out our new beta eCFR site at https://ecfr.federalregister.gov. We???ve made big changes to make the eCFR easier to use. Be sure to leave feedback using the Help button on the bottom right of each page!

e-CFR data is current as of August 6, 2020

Title 30Chapter IISubchapter BPart 250Subpart S → §250.1917


Title 30: Mineral Resources
PART 250—OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF
Subpart S—Safety and Environmental Management Systems (SEMS)


§250.1917   What criteria for pre-startup review must be in my SEMS program?

Your SEMS program must require that the commissioning process include a pre-startup safety and environmental review for new and significantly modified facilities that are subject to this subpart to confirm that the following criteria are met:

(a) Construction and equipment are in accordance with applicable specifications.

(b) Safety, environmental, operating, maintenance, and emergency procedures are in place and are adequate.

(c) Safety and environmental information is current.

(d) Hazards analysis recommendations have been implemented as appropriate.

(e) Training of operating personnel has been completed.

(f) Programs to address management of change and other elements of this subpart are in place.

(g) Safe work practices are in place.