Home
gpo.gov
govinfo.gov

e-CFR Navigation Aids

Browse

Simple Search

Advanced Search

 — Boolean

 — Proximity

 

Search History

Search Tips

Corrections

Latest Updates

User Info

FAQs

Agency List

Incorporation By Reference

eCFR logo

Related Resources

Electronic Code of Federal Regulations

We invite you to try out our new beta eCFR site at https://ecfr.federalregister.gov. We have made big changes to make the eCFR easier to use. Be sure to leave feedback using the Feedback button on the bottom right of each page!

e-CFR data is current as of November 24, 2020

Title 40Chapter ISubchapter CPart 62Subpart FFF → Appendix


Title 40: Protection of Environment
PART 62—APPROVAL AND PROMULGATION OF STATE PLANS FOR DESIGNATED FACILITIES AND POLLUTANTS
Subpart FFF—Federal Plan Requirements for Large Municipal Waste Combustors Constructed on or Before September 20, 1994


Table 6 to Subpart FFF of Part 62—Site-Specific Compliance Schedules and Increments of Progressa

Affected facilities at the following MWC sites City, State Increment 1
Submit final control plan
Increment 2
Award contracts
Increment 3
Begin on-site construction
Increment 4
Complete on-site construction
Increment 5
Final compliancec
Stanislaus Resource Recovery FacilityCrows Landing, CaliforniaJanuary 11, 199901/19/0005/19/0011/19/0012/19/00
Southeast Resource Recovery FacilityLong Beach, CaliforniaJanuary 11, 199904/30/9910/31/9904/30/0012/19/00
All large MWC unitsMaineJanuary 11, 199901/01/9907/01/9909/01/0012/19/00
Baltimore RescoBaltimore, MarylandJanuary 11, 1999January 11, 1999January 11, 199909/01/0012/19/00
All large MWC unitsNew JerseybJanuary 11, 199905/18/9911/14/9911/19/0012/19/00
American Ref-FuelDelaware County, Pennsylvania11/01/9805/18/9911/14/9911/19/0012/19/00
Montenay Energy ResourceMontgomery County, Pennsylvania11/01/9805/18/9911/14/9911/19/0012/19/00
I-95 Energy/Resource Recovery FacilityLorton, VirginiaJanuary 11, 199910/15/9903/01/0011/19/0012/19/00
New Hanover County, Unit 3AWilmington, North Carolina09/15/9903/01/0007/01/0011/19/0012/19/00

aThese schedules have been reviewed and determined to be acceptable by EPA.

bThis schedule applies to HC1 SO2, PM, Pb, Cd, CO, and NOX. However, owners and operators of large MWC units in New Jersey have the option of reserving the portion of their control plan that addresses NOX. Owners and operators must submit the reserved portion to EPA by December 15, 1999.

cThe owner or operator of an affected facility that began construction, modification, or reconstruction after June 26, 1987 must achieve final compliance with the mercury and dioxins/furans limits within 1 year after promulgation of subpart FFF (i.e., by 11/12/99) or 1 year after permit issuance. Permit issuance is issuance of a revised construction permit or revised operating permit if a permit modification is required to retrofit controls. Final compliance must be achieved no later than December 19, 2000, even if the date “1 year after permit issuance” exceeds December 19, 2000.

[63 FR 63202, Nov. 12, 1998; 64 FR 17219, Apr. 8, 1999, as amended at 65 FR 33469, May 24, 2000]