Home
gpo.gov
govinfo.gov

e-CFR Navigation Aids

Browse

Simple Search

Advanced Search

 — Boolean

 — Proximity

 

Search History

Search Tips

Corrections

Latest Updates

User Info

FAQs

Agency List

Incorporation By Reference

eCFR logo

Related Resources

Electronic Code of Federal Regulations

We invite you to try out our new beta eCFR site at https://ecfr.federalregister.gov. We have made big changes to make the eCFR easier to use. Be sure to leave feedback using the Feedback button on the bottom right of each page!

e-CFR data is current as of November 20, 2020

Title 49Subtitle BChapter VIPart 611Subpart A → §611.103


Title 49: Transportation
PART 611—MAJOR CAPITAL INVESTMENT PROJECTS
Subpart A—General Provisions


§611.103   Applicability.

(a) This part applies to all proposals for Federal major capital investment funds under 49 U.S.C. 5309 for new fixed guideways, extensions to fixed guideways, and corridor-based bus rapid transit systems.

(b) This part does not apply to projects for which an FFGA or PCGA has already been executed, or to projects that have been approved into final design or project development unless the project sponsor requests to be covered by this part. The regulations in existence prior to the effective date of this rule will continue to apply to projects for which an FFGA or PCGA has already been executed and to projects approved into final design or project development unless a project sponsor requests to be covered by this part. New Starts projects approved for entry into final design shall be considered to be in the engineering phase of the New Starts process.

(c) A New Starts project which has been approved for entry into preliminary engineering under the regulations in existence prior to the effective date of this rule shall be considered to be in the engineering phase of the New Starts process. For the purpose of completing engineering, the regulations in existence prior to the effective date of this rule will continue to apply to a New Starts project approved into preliminary engineering until such time as the sponsor requests an FFGA unless the project sponsor requests to be covered by this part prior to an FFGA.