e-CFR data is current as of January 14, 2021 |
Title 40 → Chapter I → Subchapter C → Part 60 → Subpart FFFF → §60.3067 |
Title 40: Protection of Environment
PART 60—STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES (CONTINUED)
Subpart FFFF—Emission Guidelines and Compliance Times for Other Solid Waste Incineration Units That Commenced Construction On or Before December 9, 2004
(a) Use Method 9 of appendix A of this part to determine compliance with the opacity limitation.
(b) Conduct an initial test for opacity as specified in §60.8 within 180 days after the final compliance date in table 1 of this subpart.
(c) After the initial test for opacity, conduct annual tests no more than 12 months following the date of your previous test.
(d) If the air curtain incinerator has been out of operation for more than 12 months following the date of your previous test, then you must conduct a test for opacity upon startup of the unit.