Home
gpo.gov
govinfo.gov

e-CFR Navigation Aids

Browse

Simple Search

Advanced Search

 — Boolean

 — Proximity

 

Search History

Search Tips

Corrections

Latest Updates

User Info

FAQs

Agency List

Incorporation By Reference

eCFR logo

Related Resources

Electronic Code of Federal Regulations

We invite you to try out our new beta eCFR site at https://ecfr.federalregister.gov. We have made big changes to make the eCFR easier to use. Be sure to leave feedback using the Feedback button on the bottom right of each page!

e-CFR data is current as of May 13, 2021

Title 18Chapter ISubchapter B → Part 32


Title 18: Conservation of Power and Water Resources


PART 32—INTERCONNECTION OF FACILITIES


Contents

Application for an Order Directing the Establishment of Physical Connection of Facilities

§32.1   Contents of the application.
§32.2   Required exhibits.
§32.3   Other information.
§32.4   Filing procedure.

Authority: 42 U.S.C. 7101-7352; E.O. No. 12,009, 3 CFR 1978 Comp., p. 142; 31 U.S.C. 9701; 16 U.S.C. 791a-825r; 16 U.S.C. 2601-2645 (1988).

Source: Order 141, 12 FR 8494, Dec. 19, 1947, unless otherwise noted.

return arrow Back to Top

Application for an Order Directing the Establishment of Physical Connection of Facilities

return arrow Back to Top

§32.1   Contents of the application.

Every application under section 202(b) of the Act shall set forth the following information:

(a) The exact legal name of the applicant and of all persons named as parties in the application.

(b) The name, title, and post office address of the person to whom correspondence in regard to the application shall be addressed.

(c) The person named in the application who is a public utility subject to the act.

(d) The State or States in which each electric utility named in the application operates, together with a brief description of the business of and territory, by counties and States, served by such utility.

(e) Description of the proposed interconnection, showing proposed location, capacity and type of construction.

(f) Reasons why the proposed connection, of facilities will be in the public interest.

(g) What steps, if any, have been taken to secure voluntary interconnection under the provisions of section 202(a) of the Act.

[Order 141, 12 FR 8494, Dec. 19, 1947, as amended by Order 427, 36 FR 5596, Mar. 25, 1971; Order 435, 50 FR 40357, Oct. 3, 1985; Order 737, 75 FR 43403, July 26, 2010]

return arrow Back to Top

§32.2   Required exhibits.

There shall be filed with the application and as a part thereof the following exhibits:

Exhibit A. Statement of the estimated capital cost of all facilities required to establish the connection, and the estimated annual cost of operating such facilities.

Exhibit B. A general or key map on a scale not greater than 20 miles to the inch showing, in separate colors, the territory served by each utility, and the location of the facilities used for the generation and transmission of electric energy, indicating on said map the points between which connection may be established most economically.

return arrow Back to Top

§32.3   Other information.

The Commission may require additional information when it appears to be pertinent in a particular case.

return arrow Back to Top

§32.4   Filing procedure.

All applications under Part 32 must be filed with the Secretary of the Commission in accordance with filing procedures posted on the Commission's Web site at http://www.ferc.gov.

[Order 737, 75 FR 43403, July 26, 2010]