About GPO   |   Newsroom/Media   |   Congressional Relations   |   Inspector General   |   Careers   |   Contact   |   askGPO   |   Help  
 
Home   |   Customers   |   Vendors   |   Libraries  

The Electronic Code of Federal Regulations (e-CFR) is a regularly updated, unofficial editorial compilation of CFR material and Federal Register amendments produced by the National Archives and Records Administration's Office of the Federal Register (OFR) and the Government Printing Office.

Parallel Table of Authorities and Rules for the Code of Federal Regulations and the United States Code
Text | PDF

Find, review, and submit comments on Federal rules that are open for comment and published in the Federal Register using Regulations.gov.

Purchase individual CFR titles from the U.S. Government Online Bookstore.

Find issues of the CFR (including issues prior to 1996) at a local Federal depository library.

[1]
 
 

Electronic Code of Federal Regulations

e-CFR Data is current as of August 28, 2014

Title 10Chapter IISubchapter HPart 603Subpart E → §603.570


Title 10: Energy
PART 603—TECHNOLOGY INVESTMENT AGREEMENTS
Subpart E—Pre-Award Business Evaluation


§603.570   Determining milestone payment amounts.

(a) If the contracting officer selects the milestone payment method (see §603.805), the contracting officer must assess the reasonableness of the estimated amount for reaching each milestone. This assessment enables the contracting officer to set the amount of each milestone payment to approximate the Federal share of the anticipated resource needs for carrying out that phase of the RD&D effort.

(b) The Federal share at each milestone need not be the same as the Federal share of the total project. For example, the contracting officer might deliberately set payment amounts with a larger Federal share for early milestones if a project involves a start-up company with limited resources.

(c) For an expenditure-based TIA, if the contracting officer establishes minimum cost sharing percentages for each milestone, those percentages should be indicated in the agreement.

(d) For a fixed-support TIA, the milestone payments should be associated with the well-defined, observable, and verifiable technical outcomes (e.g., demonstrations, tests, or data analysis) that are established for the project in accordance with §§603.305(a) and 603.560(a).