About GPO   |   Newsroom/Media   |   Congressional Relations   |   Inspector General   |   Careers   |   Contact   |   askGPO   |   Help  
 
Home   |   Customers   |   Vendors   |   Libraries  
The Code of Federal Regulations (CFR) annual edition is the codification of the general and permanent rules published in the Federal Register by the departments and agencies of the Federal Government produced by the Office of the Federal Register (OFR) and the Government Publishing Office.


Parallel Table of Authorities and Rules for the Code of Federal Regulations and the United States Code
Text | PDF

Find, review, and submit comments on Federal rules that are open for comment and published in the Federal Register using Regulations.gov.

Purchase individual CFR titles from the U.S. Government Online Bookstore.

Find issues of the CFR (including issues prior to 1996) at a local Federal depository library.

[1]
 
 

Electronic Code of Federal Regulations

e-CFR data is current as of April 23, 2015

Title 10Chapter IISubchapter HPart 603Subpart E → §603.520


Title 10: Energy
PART 603—TECHNOLOGY INVESTMENT AGREEMENTS
Subpart E—Pre-Award Business Evaluation


§603.520   Reasonableness of total project funding.

In cooperation with the program official, the contracting officer must assess the reasonableness of the total estimated budget to perform the RD&D that will be supported by the agreement.

(a) Labor. Much of the budget likely will involve direct labor and associated indirect costs, which may be represented together as a “loaded” labor rate. The program official is an essential advisor on reasonableness of the overall level of effort and its composition by labor category. The contracting officer also may rely on experience with other awards as the basis for determining reasonableness.

(b) Real property and equipment. In almost all cases, the project costs should normally include only depreciation or use charges for real property and equipment of for-profit participants, in accordance with §603.680. Remember that the budget for an expenditure-based TIA may not include depreciation of a participant's property as a direct cost of the project if that participant's practice is to charge the depreciation of that type of property as an indirect cost, as many organizations do.